Professional Documents
Culture Documents
mehu
mehu
CONTENTS
1.0 PURPOSE
2.0 SCOPE
3.0 REFERENCES
4.0 DEFINITIONS
5.0 ABBREVIATIONS
6.0 RESPONSIBILITIES
7.0 CONFIDENTIALITY
8.0 INSTRUCTIONS
LIST OF APPENDICES
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 3
1.0 PURPOSE
1.1 Standardize the Check List Forms of the Electrical activities which will be
performed during the different stages of the project and used by the Site
Discipline Supervisor (SDS) for the Electrical works as per contract bases for the
electrical construction activity.
1.2 Define the responsibilities for different parties involved in this Instruction.
2.0 SCOPE
3.0 REFERENCES
3.2 OTHERS
4.0 DEFINITIONS
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 4
5.0 ABBREVIATIONS
BT BATTERY
BCH BATTERY CHARGER
CB CIRCUIT BREAKER
ELDP EMERGENCY LIGHTING DISTRIBUTION PANEL
EPM ELECTRICAL POWER MODULES
FC FREQUENCY CONVERTER
G GENERATOR
HTS HEAT TRACING SYSTEM
LDP LIGHTING DISTRIBUTION PANEL
MCC MOTOR CONTROL CENTER
NA NAVIGATION AIDS
NGR NEUTRAL GROUND RESISTOR
OHL OVERHEAD LINE
PFCE POWER FACTOR CORRECTION EQUIPMENT
PDP POWER DISTRIBUTION PANEL
RMU RING MAIN UNIT
SCP SYNOPTIC CONTROL PANEL
SSPS SOLAR SYSTEM POWER SUPPLY
SWG SWITCHGEAR
SWR SWITCHRACK
TR TRANSFORMER
UPS UNINTERRUPTABLE POWER SUPPLY SYSTEM
6.0 RESPONSIBILITIES
EDM shall:
6.1.1 Revise and approve the revisions and/or deviations to this instruction if
specifically required in a project.
6.1.3 Coordinate with Company Instructions Coordinator (CIC) for new official
revision.
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 5
ELE shall:
6.2.1 Assign Electrical Engineer (EE) for preparing the Electrical Check List Forms.
6.2.2 Review, check and get the approval of the EDM or his authorized delegate on
the Electrical Check List Forms.
6.2.4 Keep record of the Electrical Check List Forms in project filing.
EE shall :
6.3.1 Prepare the Electrical Check List Forms for the electrical construction activity
related to the concerned project in coordination with Construction Department
and Commissioning & Start-up Supervisor.
6.3.2 Submit the Electrical Check List Forms to ELE for checking.
EL shall :
- Revise the Electrical Check Lists, as necessary after ELE checking, for
approval and issue to the Construction Site Manager (SM)/ Site Discipline
Supervisor for the Electrical Works (SDS).
SDS shall :
- Submit complete set from the Electrical Check Lists to the Construction
Contractor.
- Use the Electrical Check Lists, during the different stages of the project.
- Complete all signatures related to the Check Lists from the authorized
personnel (contractor/client).
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 6
7.0 CONFIDENTIALITY
In general the Electrical Check List Forms shall be issued to the successful
Construction Contractor; unless otherwise required by project instructions.
8.0 INSTRUCTIONS
8.1 GENERAL
8.1.1 Using the Electrical Check List Forms for all projects but it can be adapted in a
special project.
8.1.2 The Electrical Check List Forms shall be issued as a part of the project
documents (depending on the contract bases) to the successful Construction
Contractor.
8.1.3 The Electrical Check List Forms are grouped into three sections :
- Pre-installation activities
- Mechanical completion and pre-commissioning activities
- Commissioning activities
8.1.4 The hard copy of the Electrical Check List Forms listed in Appendices 1.0, 2.0
& 3.0 are available in the Electrical Department and are stored also on the
computer.
8.2.2 ELE shall check the conformity between the project electrical
equipment/materials and the Electrical Check List Forms.
8.2.3 The EDM (or EDM authorized delegate) shall approve the Check List Forms.
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 7
APPENDIX 1.0
PRE-INSTALLATION ACTIVITIES
CONTENTS
1.0 GENERAL
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 8
PREINSTALLATION ACTIVITIES.
1.0 GENERAL
These checks shall generally be performed at the warehouse, however, for some
materials, which must be transported to the place of installation (e.g SWG'S &
MCC panels) it can be carried out on this place. Item 2.0 includes all the electrical
preinstallation forms which indicate the checks required to be made for the
electrical equipment and materials. The preinstallation checks shall be carried out
by the Electrical Construction Contractor and supervised/approved by ENPPI
Electrical Construction Supervisor and Client.
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 9
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 10
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 11
ENPPI
PROJECT NO : SUPPLIER:
AREA : DATE :
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 12
ENPPI
Page 1 of 1
PROJECT NAME: COM. NO:500-03
PROJECT NO : SUPPLIER:
AREA : DATE :
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 13
ENPPI
Page 1 of 3
PROJECT NAME: COM. NO:510-02
PROJECT NO : SUPPLIER:
AREA : DATE :
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 14
PROJECT NO : SUPPLIER:
AREA : DATE :
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 15
ENPPI
Page 2 of 3
PROJECT NAME: COM. NO:510-02
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
16 All components are securely fixed and free from damage
17 Earthing connections are Verified
18 Loose material availability to be checked
19 Check availability of supplier documents , Including storage and
installation instructions
20 OFF-CIRCUIT TAP CHANGER :
20.1 Check tap-selector switch moves correctly in all positions
20.2 Check availability of a suitable padlock, complete with two keys
20.3 Robust mechanical stops at the ends shall be provided to prevent
overrunning
20.4 Check tap positions clearly marked in line with the data given on the
rating plate
20.5 Check the tap provided with metallic handle to allow operation
without the need of tools
20.6
20.7
20.8
20.9
20.10
20.11
REMARKS: If neutral ground resistor part of the power transformer, check pre-installation
check list of N.G.R (CLF- 510-09)
CONTRACTOR ENPPI CLIENT
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 16
ENPPI
Page 3 of 3
PROJECT NAME: COM. NO:510-02
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
21 ON-LOAD TAP CHANGER :
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 17
ENPPI
PROJECT NO : SUPPLIER:
AREA : DATE :
REMARKS:
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 18
ENPPI
PROJECT NO : SUPPLIER:
AREA : DATE :
14
checked
15 Spare parts and commissioning components to be verified
against their relevant lists
16 Check availability of supplier documents ,including storage and
installation instructions
17 Check availability of inspection certificate including tests
acceptance criteria values
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
REMARKS:
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 19
ENPPI
PROJECT NO : SUPPLIER:
AREA : DATE :
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 20
PROJECT NO : SUPPLIER:
AREA : DATE :
ENPPI
PROJECT NO : SUPPLIER:
AREA : DATE :
19
20
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 21
PROJECT NO : SUPPLIER:
AREA : DATE :
21
REMARKS:
ENPPI
PROJECT NO : SUPPLIER:
AREA : DATE :
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 22
PROJECT NO : SUPPLIER:
AREA : DATE :
ENPPI
PROJECT NO : SUPPLIER:
AREA : DATE :
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 23
PROJECT NO : SUPPLIER:
AREA : DATE :
ENPPI
PROJECT NO : SUPPLIER:
AREA : DATE :
1 ALTERNATOR :
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 24
PROJECT NO : SUPPLIER:
AREA : DATE :
1.6 Check all components are securely fixed and free from damage
1.8 Ensure that all covers giving access for connections are
fastened down
1.10 Check enclosure for moisture leaks and openings which may
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 25
ENPPI
PROJECT NO : SUPPLIER:
AREA : DATE :
1.12 Ventilation openings are not blocked off and are fitted with
gratings and insect nets
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 26
ENPPI
Page 3 of 3
PROJECT NAME: COM. NO:510-06
PROJECT NO : SUPPLIER:
AREA : DATE :
2 BATTERIES :-
2.7
2.8
2.9
2.10
2.11
REMARKS:
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 27
PROJECT NO : SUPPLIER:
AREA : DATE :
ENPPI
Page 1 of 3
PROJECT NAME: COM. NO:510-08
PROJECT NO : SUPPLIER:
AREA : DATE :
1.4 All panels and fans are free from mechanical damage
1.5 Check doors and panels close properly and there are keys for all
locks
1.6 Check all components are securely fixed and free from damage
1.7 Check all meters for loose glass
1.8 Check signal lamps are correctly rated and as per approved
dwg's
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 28
PROJECT NO : SUPPLIER:
AREA : DATE :
REMARKS:
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 29
ENPPI
Page 2 of 3
PROJECT NAME: COM. NO: 510-08
PROJECT NO : SUPPLIER:
AREA : DATE :
1.11 Ventilation openings are not blocked off and are fitted with
gratings and insect nets
1.17
REMARKS:
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 30
PROJECT NO : SUPPLIER:
AREA : DATE :
ENPPI
Page 3 of 3
PROJECT NAME: COM. NO:510-08
PROJECT NO : SUPPLIER:
AREA : DATE :
2 BATTERIES :-
2.1 Batteries are compliance with approved documents and data sheet
2.6
2.7
2.8
2.9
2.10
2.11
2.12
REMARKS:
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 31
PROJECT NO : SUPPLIER:
AREA : DATE :
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 32
ENPPI
Page 1 of 1
PROJECT NO : SUPPLIER:
AREA : DATE :
5 Check all components are securely fixed and free from damage.
EMARKS:
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 33
ENPPI
Page 1 of 5
PROJECT NO : SUPPLIER:
AREA : DATE :
5 Control panels close properly and there are keys for all locks
REMARKS:
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 34
EN P P I
Page 2 of 5
PROJECT NO : SUPPLIER:
AREA : DATE :
wiring
accessories
criteria values
15
16 BATTERIES :-
16.1 Batteries are compliance with approved documents and data sheet
REMARKS:
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 35
PROJECT NO : SUPPLIER:
AREA : DATE :
ENPPI
Page 3 of 5
PROJECT NO : SUPPLIER:
AREA : DATE :
16.8 Batteries are compliance with approved documents and data sheet
SUBSIDIARY LIGHTS :
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 36
PROJECT NO : SUPPLIER:
AREA : DATE :
REMARKS:
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 37
ENPPI
Page 4 of 5
PROJECT NAME: COM. NO:510-10
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
installation instructions
18 FOG HORN :
installation instructions
REMARKS:
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 38
ENPPI
Page 5 of 5
PROJECT NAME: COM. NO:510-10
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
19 FIXED RED LIGHT, RED FLASHING LIGHT AND
HELIDECK LIGHTING :
19.1 Characteristics of fixed red light, red flashing light and helideck
lighting to be checked w.r.t their related MRP and approved
documents
19.5
19.6
19.7
19.8
19.9
REMARKS:
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 39
ENPPI
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
nstallation instructions
any cable from the shipping container to ensure that the heat
REMARKS:
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 40
ENPPI
PROJECT NO : SUPPLIER:
AREA : DATE :
10 The heat tracing cables shall be tested again as per item (8) after
installation instructions
13
14
15
16
17
18
19
20
REMARKS:
(*) Continuity and insulation tests according to the supplier recommendations.
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 41
ENPPI
Page 1 of 4
PROJECT NAME: COM. NO:510-12
PROJECT NO : SUPPLIER:
AREA : DATE :
1.5 Check doors and panel close properly and there are keys for
all locks
1.6 Check all components are securely fixed and free from damage
1.8 Check signal lamps are correctly rated and as per approved
dwg's
REMARKS:
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 42
ENPPI
Page 2 of 4
PROJECT NAME: COM. NO:510-12
PROJECT NO : SUPPLIER:
AREA : DATE :
1.10 Check enclosure for moisture leaks and openings which may allow dirt
accumulation
1.11 Ventilation openings are not blocked off and are fitted with gratings and
insect nets
2.4 Check doors and panel close properly and there are keys for all locks
2.5 Check all components are securely fixed and free from damage
2.7 Check enclosure for moisture leaks and openings which may
REMARKS:
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 43
ENPPI
Page 3 of 4
PROJECT NAME: COM. NO:510-12
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
2.8 Ventilation openings are not blocked off and are fitted with
gratings and insect nets
3.0 BATTERIES :-
REMARKS:
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 44
ENPPI
Page 4 of 4
PROJECT NAME: COM. NO:510-12
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
5 List of spare parts and commissioning spare parts to be revised
w.r.t their relevant MRP
9
10
11
12
13
14
15
16
REMARKS:
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 45
ENPPI
"PI-CLF (510-13)"
Page 1 of 2
PROJECT NAME: COM. NO:510-13
PROJECT NO : SUPPLIER:
AREA : DATE :
5 Check doors and panels close properly and there are keys for all locks
6 Check all components are securely fixed and free from damage
8 Check signal lamps are correctly rated and as per approved dwg's
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 46
ENPPI
Page 2 of 2
PROJECT NO : SUPPLIER:
AREA : DATE :
11 Check enclosure for moisture leaks and openings which may allow
dirt accumulation
12 Ventilation openings are not blocked off and are fitted with
installation instructions
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 47
ENPPI
Page 1 of 2
PROJECT NO : SUPPLIER:
AREA : DATE :
5 Check doors and panels close properly and there are keys for all locks
6 Check all components are securely fixed and free from damage
8 Check signal lamps are correctly rated and as per approved dwg's
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 48
ENPPI
Page 2 of 2
PROJECT NO : SUPPLIER:
AREA : DATE :
11 Check enclosure for moisture leaks and openings which may allow
dirt accumulation
12 Ventilation openings are not blocked off and are fitted with
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 49
ENPPI
Page 1 of 2
PROJECT NO : SUPPLIER:
AREA : DATE :
5 Check doors and panels close properly and there are keys for all
locks
6 Check all components are securely fixed and free from damage
10 Check enclosure for moisture leaks and openings which may allow
dirt accumulation
REMARKS:
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 50
ENPPI
Page 2 of 2
PROJECT NO : SUPPLIER:
AREA : DATE :
REMARKS:
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 51
ENPPI
Page 1 of 2
PROJECT NO : SUPPLIER:
AREA : DATE :
5 Check doors and panels close properly and there are keys for all locks
6 Check all devices and components are securely fixed and free from damage
10 Check enclosure for moisture leaks and openings which may allow dirt
accumulation
REMARKS:
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 52
ENPPI
Page 2 of 2
PROJECT NO : SUPPLIER:
AREA : DATE :
installation instructions
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 53
ENPPI
Page 1 of 2
PROJECT NO : SUPPLIER:
AREA : DATE :
5 Check doors and panels close properly and there are keys for all locks
6 Check all components are securely fixed and free from damage
10 Check enclosure for moisture leaks and openings which may allow dirt
accumulation
REMARKS:
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 54
ENPPI
Page 2 of 2
PROJECT NO : SUPPLIER:
AREA : DATE :
12 Ventilation openings are not blocked off and are fitted with gratings
installation instructions
criteria values
19
REMARKS:
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 55
ENPPI
Page 1 of 2
PROJECT NO : SUPPLIER:
AREA : DATE :
outlets, ...etc
6 Check all components are securely fixed and free from damage
9 List of spare parts and commissioning spare parts to be revised w.r.t their
relevant MPR
REMARKS:
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 56
ENPPI
Page 2 of 2
PROJECT NAME: COM. NO:520-01
PROJECT NO : SUPPLIER:
AREA : DATE :
installation instructions
14
15
16
17
18
19
REMARKS:
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 57
ENPPI
Page 1 of 1
PROJECT NO : SUPPLIER:
AREA : DATE :
4 Free ends of conduits have no sharp edges which can damage the
cables
criteria values
installation instructions
REMARKS:
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 58
PROJECT NO : SUPPLIER:
AREA : DATE :
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 59
ENPPI
Page 1 of 1
PROJECT NAME: COM. NO:540-01
PROJECT NO : SUPPLIER:
AREA : DATE :
3 Check that cable drum has a full data of size, type, quantity , cable
installation instructions
criteria values
10
REMARKS:
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 60
ENPPI
Page 1 of 1
PROJECT NAME: COM. NO:550-01
PROJECT NO : SUPPLIER:
AREA : DATE :
installation instructions
criteria values
10
11
REMARKS:
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 61
ENPPI
Page 1 of 2
PROJECT NO : SUPPLIER:
AREA : DATE :
5 Indication lamp are of the correct colour and revised w.r.t approved
documents
6 Check all components are securely fixed and free from damage
REMARKS:
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 62
ENPPI
Page 2 of 2
PROJECT NAME: COM. NO:560-01
PROJECT NO : SUPPLIER:
AREA : DATE :
11 Boxes are complete with all bolts and are securely closed
installation instructions
criteria values
17
18
19
20
21
REMARKS:
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 63
ENPPI
Page 1 of 1
PROJECT NAME: COM. NO:570-01
PROJECT NO : SUPPLIER:
AREA : DATE :
installation instructions
criteria values
10
11
12
REMARKS:
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 64
APPENDIX 2.0
CONTENTS
1.0 GENERAL
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 65
ACTIVITIES
1.0 GENERAL
Electrical precommissioning , inspection and tests should be carried out to prove that
the quality of installation works are of the required standard and that the function of
electrical systems in a safe and proper manner.
Item 2.0 include all the electrical Mechanical completion and pre-commissioning forms
which indicates the checks required to be made for the electrical equipment and
materials.The pre-commissioning checks shall be carried out by the electrical
construction contractor and supervised/ approved by ENPPI electrical construction
supervisor and client.
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 66
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 67
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 62
ENPPI
Page 1 of 1
PROJECT NAME: COM. NO:500-02
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
1 CABLES :-
Refer to PC-CLF (540-01).
2 CABLE ACCESSORIES :-
Refer to PC-CLF (570-01).
5 MOTORS :-
Refer to PC-CLF (500-03).
7 LIGHTING SYSTEM :-
Refer to PC-CLF (520-01).
8 GROUNDING SYSTEM :-
Refer to PC- CLF (550-01).
9 ELECTRICAL POWER DISTRIBUTION BOARD(S) :-
Refer to PC-CLF (510-04) and CLF (510-17).
10
11
REMARKS:
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 63
ENPPI
page 1 of 2
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
1 Check rating of anti- condensation heaters.
REMARKS: (*) Measure the phase to frame insulation resistance and phase to phase if the windings can
be separated, a 5000 v and 1000 v megger insulation tester should be used on M.V and L.V motors.
## H.V (5000 v megger , min. 150 M.OHMS)
## L.V (1000 v megger , min.10 M.OHMS).
(**) 500 v megger, min. 10 M.OHMS, before meggering ensure instrument cable disconnected.
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 64
ENPPI
page 2 of 2
PROJECT NO : SUPPLIER:
AREA : DATE :
13
14
15
16
17
18
REMARKS: (*) Measure the phase to frame insulation resistance and phase to phase if the windings can be
separated, a 5000 v and 1000 v megger insulation tester should be used on M.V and L.V motors.
## H.V (5000 v megger , min. 150 M.OHMS)
## L.V (1000 v megger , min.10 M.OHMS).
(**) 500 v megger, min. 10 M.OHMS, before meggering ensure instrument cable disconnected.
CONTRACTOR ENPPI CLIENT
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 65
ENPPI
page 1 of 4
PROJECT NAME: COM. NO:510-02
PROJECT NO : SUPPLIER:
AREA : DATE :
2 Check oil level or supply and fill up with oil as per specifications.
8 Check winding insulation resistance ( H.V to earth ,L.V to earth & H.V to
L.V). (**)
9 Apply 15 k.v D.C test voltage for one minute, H.V winding to earth.
record leakage current ,discharge H.V and L.V windings for a minimum
(30) minutes [leakage current in uA].
REMARKS:
(*) Insulation on transformer oil sample (Breakdown test)
(**) - H.V terminals: 5000 V megger, min. 150 M.
- L.V terminals: 1000 V megger, min. 10 M.
- H.V/L.V term.: 5000 V megger, min. 150 M.
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 66
ENPPI
page 2 of 4
PROJECT NAME: COM. NO:510-02
PROJECT NO : SUPPLIER:
AREA : DATE :
REMARKS:
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 67
ENPP I
page 3 of 4
PROJECT NAME: COM. NO:510-02
PROJECT NO : SUPPLIER:
AREA : DATE :
18.1 Check devices (tap and physical check, assembly, connections as per
approved documents, ..etc)of the tap changer oil compartment :
a. Oil level indicator.
b. Buchholz oil/gas device.
c. Oil sampling connection.
d. One filling/filter connection valve.
e. One drain/filter connection valve.
f. A breather with a silica gel dehydrating capsule.
18.2 Check the motor drive shall include but not limited to the following :
a. Padlockable incoming supply switch.
b. Manual operation facilities.
c. Local control facilities.
d. Local/remote selector switch.
e. Local mechanical tap position indicator.
f. Direction of rotation protection
g. Tap status indication lamps.
REMARKS:
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 68
ENPPI
page 4 of 4
PROJECT NAME: COM. NO:510-02
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
19 OFF-LOAD TAP CHANGER
19.1 Check tap-selector switch moves correctly in all positions.
19.2 Check tap positions clearly marked in line with the data given
on the rating plate.
19.3 Check the tap provided with metallic handle to allow operation
without the need of tools.
20 Check components of the remote control panel (function, tap
and physical check, assembly, connections as per approved
documents, ..etc) :
a. Manual control facilities.
b. Tap position indicator.
c. Tap status indication lamps.
d. Anti-condensation heater.
21
22
23
24
25
REMARKS:
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 69
ENPPI
page 1 of 5
PROJECT NAME: COM. NO:510-03
PROJECT NO : SUPPLIER:
AREA : DATE :
7 Check main, aux. fuses and relays correctly rated and undamaged.
REMARKS:
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 70
ENPPI
page 2 of 5
PROJECT NAME: COM. NO:510-03
PROJECT NO : SUPPLIER:
AREA : DATE :
15 Voltage withstand test of both the main and aux. circuits, this shall be
carried out between phases and phases to ground. (***).
REMARKS:
(*) Refer to table [II]
(**) 500 v megger, min. 10 meg.ohm
(***) Refer to table [I]
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 71
E N P PI
page 3 of 5
PROJECT NAME: COM. NO:510-03
PROJECT NO : SUPPLIER:
AREA : DATE :
Holes that are not used but are planned for future equipments
20
or instruments are correctly blanked off.
REMARKS:
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 72
ENPPI
page 4 of 5
PROJECT NAME: COM. NO:510-03
PROJECT NO : SUPPLIER:
AREA : DATE :
33
34
REMARKS:
(****) Conductivity testing shall be carried
with a low-resistance test set,
e.g. a "Ducter" with 20 A (d.c) output.
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 73
page 5 of 5
"PC-CLF(510-03)"
VOLTAGE WITHSTAND TEST
TABLE OF TEST VOLTAGES.
TABLE [I]
N.B :
- All current transformer secondaries shall be short circuit for the duration
of the test.
- Test shall be carried out with all circuit breakers, isolators and switches
closed, but with all the cable cores disconnected.
INSULATION TEST.
TABLE [II]
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 74
ENPPI
page 1 of 5
PROJECT NO : SUPPLIER:
AREA : DATE :
2 Check all busbar connections (Torque check with a torque wrench) and
recommendations.
up instructions.
8 Check main, aux. fuses and relays correctly rated and undamaged.
REMARKS:
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 75
ENPPI
page 2 of 5
PROJECT NO : SUPPLIER:
AREA : DATE :
to ground.
16 Voltage withstand test of both the main and aux. circuits, this shall be
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 76
ENPPI
page 3 of 5
PROJECT NO : SUPPLIER:
AREA : DATE :
20 Holes that are not used but are planned for future equipments or
instruments are correctly blanked off.
REMARKS:
(*) Refer to table [II]
(**) 500 v megger, min. 10 meg.ohm
(***) Refer to table [I]
CONTRACTOR ENPPI CLIENT
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 77
ENPPI
page 4 of 5
PROJECT NO : SUPPLIER:
AREA : DATE :
REMARKS:
(****) Conductivity testing shall be carried
with a low-resistance test set,
e.g. a "Ducter" with 20 A (d.c) output.
CONTRACTOR ENPPI CLIENT
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 78
page 5 of 5
"PC-CLF(510-04)"
VOLTAGE WITHSTAND TEST
TABLE OF TEST VOLTAGES.
TABLE [I]
N.B :
- All current transformer secondaries shall be short circuit for the duration
of the test.
- Test shall be carried out with all circuit breakers, isolators and switches
closed, but with all the cable cores disconnected.
INSULATION TEST.
TABLE OF MINIMUM TEST VOLTAGES.
TABLE [II]
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 79
ENPPI
page 1 of 5
PROJECT NO : SUPPLIER:
AREA : DATE :
8 Check main, aux. fuses and relays correctly rated and undamaged.
REMARKS:
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 80
ENPPI
page 2 of 5
PROJECT NO : SUPPLIER:
AREA : DATE :
15 Voltage withstand test of both the main and aux. circuits, this shall
be carried out between phases and phases to ground (***).
16 Apply 15 k.v (Bus-bar system) D.C for one minute connect phases to
ground,record leakage current in m.amp.
REMARKS:
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 81
ENPPI
page 3 of 5
PROJECT NO : SUPPLIER:
AREA : DATE :
20 Holes that are not used but are planned for future equipments or
instruments are correctly blanked off.
REMARKS:
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 82
ENPPI
page 4 of 5
PROJECT NO : SUPPLIER:
AREA : DATE :
32
33
34
REMARKS:
(****) Conductivity testing shall be carried with a low-resistance test set,
e.g. a "Ducter" with 20 A (d.c) output.
CONTRACTOR ENPPI CLIENT
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 83
page 5 of 5
"PC-CLF (510-05)"
VOLTAGE WITHSTAND TEST
TABLE OF TEST VOLTAGES.
EQUIPMENT RATED VOLTAGE (KV) TEST VOLTAGE (KV)
0.66 2
3.3 8.6
6.6 15.2
11 24
15 32
22 46
TABLE [I]
N.B :
- All current transformer secondaries shall be short circuit for the duration
of the test.
- Test shall be carried out with all circuit breakers, isolators and switches
closed, but with all the cable cores disconnected.
INSULATION TEST.
TABLE OF MINIMUM TEST VOLTAGES.
SWITCHGEAR VOLTAGE TEST MINIMUM INSULATION
(KV) VOLTAGE(V) RESISTANCE (M.OHMS)
33 5000 200
22 5000 200
11 5000 200
6.6 1000 200
3.3 1000 200
0.6 1000 100
0.4 1000 100
CONTROL WIRING 500 10
TABLE [II]
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 84
ENPPI
page 1 of 5
PROJECT NO : SUPPLIER:
AREA : DATE :
1.6 Remove any accidental connections between phases and from phases to
ground.
1.9 All supports needed for power and control cables to be checked.
1.10 Holes that are not used but are planned for future equipments or
instruments are correctly blanked off.
REMARKS:
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 85
ENPPI
PROJECT NO : SUPPLIER:
AREA : DATE :
1.19
1.20
1.21
REMARKS:
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 86
ENPPI
page 3 of 5
PROJECT NO : SUPPLIER:
AREA : DATE :
2.2
2.3
3.1 Check generator control panel refer to PC-CLF (510-04) and CLF
(510-13)
3.4 Check all components such as: meters, lamps,....etc. w.r.t approved
drawings.
REMARKS:
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 87
ENPPI
page 4 of 5
PROJECT NO : SUPPLIER:
AREA : DATE :
3.7 Wire identifications and cable markers to be checked w.r.t cable list.
3.8 Insulation test of both the main and aux. circuits, this shall be carried
out between phases and phases to ground. (*).
3.9
3.10
3.11
8
REMARKS:
(*) Refer to table [I]
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 88
"PC-CLF (510-06)"
page 5 of 5
TABLE [I]
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 89
ENPPI
page 1 of 5
PROJECT NO : SUPPLIER:
AREA : DATE :
1.5 Check all components such as: meters, lamps,....etc, w.r.t approved
rawings.
1.8 Wire identifications and cable markers to be checked w.r.t cable list.
REMARKS:
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 90
ENPPI
page 2 of 5
PROJECT NO : SUPPLIER:
AREA : DATE :
1.12 All supports needed for power and control cables to be checked.
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 91
ENPPI
page 3 of 5
PROJECT NO : SUPPLIER:
AREA : DATE :
2 BATTERIES :
2.1 Batteries are installed as Indicated in the design.
2.5 Terminals are clean, well tightened and fitted with protective caps.
2.6 Check the electrolyte level in all cells after filling and measure the
specific gravity of the electrolyte and compare this with the
recommended value
REMARKS:
0000-000-5-EI-O-850-186-1-X
PAGES 186
PAGE 92
ENPPI
page 4 of 5
PROJECT NO : SUPPLIER:
AREA : DATE :
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 93
"PC-CLF(510-08)"
page 5 of 5
TABLE [I]
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 94
ENPPI
page 1 of 2
PROJECT NAME: COM. NO:510-09
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
1 Fixation, alignment and installation of N.E.R to
be checked.
2
Inspect the frame earthing arrangement and
3
measure the equipment earth path resistance at the
main earthing terminal to the general earthing
system.
4 Check the space heater and circuit where fitted.
5 Measure the insulation resistance of the resistor
to earth with incoming outgoing connections
disconnected , measure the vaiue of the
N.E.R.
6 All supports needed for cables to be checked.
7 All equipments to be cleaned.
8 Check availability of vendor documents,
including commissioning and start-up
instruction.
REMARKS:
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 95
ENPPI
page 2 of 2
PROJECT NAME: COM. NO:510-09
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
9 Equipment test report and inspection certificate
to be checked.
Acceptance criteria values of the above
mentioned tests to be revised.
10
11
12
13
14
15
16
17
18
19
20
21
22
REMARKS:
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 96
ENPPI
page 1 of 5
PROJECT NAME: COM. NO:510-10
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
1 Check size, type, and rating of all fuses and
protectective devices w.r.t approved
documents.
2 Check earthing connections to the earthing
system.
3 Measure the equipment earthing path resistance
at the earthing terminal to the general earthing.
4 Cable terminations to be checked w.r.t
approved
documents
5 Fixation of all components to be checked such
as: Fog horns, flashing devices,..etc.
6 Wire identifications and cable markers to be
checked w.r.t approved documents.
7 Check D.C system Refer to PC-CLF 510-08).
8 Holes that are not used but are planned for
future equipments or instruments are correctlyt
blanked off.
REMARKS:
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 97
ENPPI
page 2 of 5
PROJECT NAME: COM. NO:510-10
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
9 All equipments to be cleaned internally and
externally.
10 Cable entries to be sealed wherever indicated in
the dwg,s
11 Remove any accidental connections between
components.
12 Tie raps to be used for cables and wires
fixation.
13 All supports needed for cables to be checked.
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 98
ENPPI
Page 3 of 5
PROJECT NAME: COM. NO:510-10
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
18 All internal wiring connection are secure.
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 99
ENPPI
Page 4 of 5
PROJECT NAME: COM. NO:510-10
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
24.3 Check availability , type, and preparation of
electrolyte w.r.t approved documents.
24.4 Check availability of supplier documents
,including storage and installation instructions.
25 Batteries type: solar cells.
25.1 Cells are mechanically undamaged.
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 100
ENPPI
Page 5 of 5
PROJECT NAME: COM. NO:510-10
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
27 FOG HORN :
Characteristics of fog horn to be checked w.r.t their
27.1
related MRP and approved documents.
Equipment installation to be checked w.r.t
27.2
approved supplier documents and installation
instructions.
28 FIXED RED LIGHT, RED FLASHING
LIGHT, AND HELIDECK LIGHTING :
Characteristics of fog horn to be checked w.r.t their
28.1
related MRP and approved documents.
28.2 Equipment installation to be checked w.r.t
approved supplier documents and installation
instructions.
28.3
28.4
Check availability of vendor documents ,including
29
commissioning and start-up instructions.
30
REMARKS:
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 101
ENPPI
page 1 of 4
PROJECT NAME: COM. NO:510-11
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
1 Insulation resistance and continuity of all
connections to be carried out. ( applied 500v
D.C
and insulation resistance not less than 5
M.ohm)
2 Stainless steel strapping to be used to hold the
cables to the pipe surfaces as per supplier
installation recommendation and on small
diameter, low temp. pipe, nylon ties or glass
tape may be used.
3 Heat tracing cables to be laid according to the
installation recommendation.
4 Thermostat bulb to be located as per supplier
recommendation.
5 Thermostat capillary and control wires shall
have mechanical protection between the
equipments and pipe lines.
6 pipe line to be insulated within (24) hours upon
tracer installation and acceptance.
REMARKS:
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 102
ENPPI
page 2 of 4
PROJECT NAME: COM. NO:510-11
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
8 Check that traced pipe line to be clearly marked
by labels.
9 All internal wiring connection are secure.
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 103
ENPPI
page 3 of 4
PROJECT NAME: COM. NO:510-11
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
18 Check continuity and insulation of heater cables
after insulation has been put on the pipes
and the installation is complete and if the heater
cables test satisfactory, connect the power
cables.
19 Cold-lead joints including a small portion of the
cold] lead. shall be fixed to the heated surface
to ensure a good contact of the heater.
20 Check that heating cables fixed to the pumps,
valves, flanges,...etc shall allow easy removal
of the equipment without damaging the cable.
21 Additional fixing straps shall be provided on
both sides of the pumps, valves, flanges, ..etc.
to avoid loosing of the heater from the
associated pipes.
22 Check that J.B's, thermostat.. ...etc, not to be
attached to the insulation, but shall be
mounted on brackets.
REMARKS:
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 104
ENPPI
page 4 of 4
PROJECT NAME: COM. NO:510-11
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
23 Check all materials as indicated on the related
data
sheet (highly corrosion resistant, suitable for
salty,..etc)
24 DISTRIBUTION PANEL
24.1 Distr. panels close properly and there are keys
for all locks.
24.2 Equipment test report and inspection certificate
to b checked. Acceptance criteria values of the
above mentioned tests to be revised.
24.3 All internal wiring connection are secure.
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 105
ENPPI
page 1 of 5
PROJECT NAME: COM. NO:510-12
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
1 D.C CHARGER PANEL :
1.1 Check equipment assembly for alignment,
levelness and foundation fixing details.
1.2 Check equipment earthing connections.
0000-000-5-EI-O-850-186-1-X
PAGES 186 PAGE 106
ENPPI
page 2 of 5
PROJECT NAME: COM. NO:510-12
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
1.10 Insulation test of both the main and aux.
circuits, this shall be carried out between phases
and phases to ground. (**).
1.11 Check connection of gland plate to the earthing
busbar.
1.12 Cable entries to be sealed wherever indicated in
the dwg,s
1.13 Tie raps to be used for cables and wires
fixation.
1.14 All supports needed for power and control
cables to be checked.
1.15 All internal wiring connection are secure.
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 107
ENPPI
page 3 of 5
PROJECT NAME: COM. NO:510-12
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
1.18 Check cable glands (sizes, tightened,....etc) and
gland plates.
2 INVERTER & STATIC SWITCH
COMPARTMENT :
2.1 Check equipment earthing connections.
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 108
ENPPI
page 4 of 5
PROJECT NAME: COM. NO:510-12
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
4 Check availability of vendor documents,
including commissioning and start-up
instructions.
5 BATTERIES :
5.1 Batteries are installed as indicated in the design.
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 109
"PC-CLF (510-12)"
page 5 of 5
TABLE [I]
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 110
ENPPI
page 1 of 5
PROJECT NAME: COM. NO:510-13
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
1 Check equipment assembly for alignment,
levelness and foundation fixing details.
2 Check all busbar connections and covers
according to the approved documents and
supplier recommendations.
3 Check equipment earthing connections.
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 111
ENPPI
page 2 of 5
PROJECT NAME: COM. NO:510-13
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
11 Remove any accidental connections between
phases and from phases to ground.
12 Insulation resistance test of busbar bolted
connections (Between phases and phases to
ground) (*)
13 Check equipment anti- condensation heaters
and test insulation resistance.(**)
14 Voltage withstand test of both the main and
aux. circuits, this shall be carried out between
phases and phases to ground (***).
15 Termination of power and control cables to be
checked.
16 Wire identifications and cable markers to be
checked w.r.t cable list.
17 Check all internal components such as:
Relays,fuses,....etc
REMARKS:
(*) Refer to table [II]
(**) 500 v megger, min. 10 meg.ohm
(***) Refer to table [I]
CONTRACTOR ENPPI CLIENT
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 112
ENPPI
page 3 of 5
PROJECT NAME: COM. NO:510-13
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
18 Check cable glands (sizes,tightness,...etc) and
gland plates.
19 Check connection of gland plate to the earthing
busbar.
20 Cable entries to be sealed wherever indicated in
the dwg,s
21 Tie raps to be used for cables and wires
fixation.
22 Holes that are not used but are planned for
future equipments or instruments are correctly
blanked off.
23 Check D.C system (Refer to PC-CLF 510-08).
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 113
ENPPI
page 4 of 5
PROJECT NAME: COM. NO:510-13
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
26 All internal wiring connection are secure.
31
32
33
34
35
36
REMARKS: (****) Conductivity testing shall be carried
with a low-resistance test set,
e.g. a "Ducter" with 20 A (d.c) output.
CONTRACTOR ENPPI CLIENT
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 114
"PC-CLF (510-13)"
page 5 of 5
TABLE [I]
N.B :
- All current transformer secondaries shall be short circuit for the duration
of the test.
- Test shall be carried out with all circuit breakers, isolators and switches
closed, but with all the cable cores disconnected.
INSULATION TEST.
TABLE [II]
0000-000-5-EI-0-850-
186-1-X
PAGES 186 PAGE 115
ENPPI
page 1 of 5
PROJECT NAME: COM. NO:510-14
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
1 Check equipment assembly for alignment,
levelness and foundation fixing details.
2 Check all busbar connections (Torque check
with a torque wrench) and covers according to
the approved documents and supplier
recommendations.
3 Check equipment earthing connections.
REMARKS:
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 116
ENPPI
page 2 of 5
PROJECT NAME: COM. NO:510-14
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
10 Check connection and data of voltage
transformers.
11 Remove any accidental connections between
phases and from phases to ground.
12 Insulation resistance test of busbar bolted
connections (Between phases and phases to
ground). (*)
13 Check equipment anti- condensation heaters
and test insulation resistance.(**)
14 Voltage withstand test of both the main and
aux. circuits, this shall be carried out between
phases and phases to ground (***).
15 Termination of power and control cables to be
checked.
16 Wire identifications and cable markers to be
checked w.r.t cable list.
REMARKS:
(*) Refer to table [II]
(**) 500 v megger, min. 10 meg.ohm
(***) Refer to table [I]
CONTRACTOR ENPPI CLIENT
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 117
ENPPI
page 3 of 5
PROJECT NAME: COM. NO:510-14
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
17 Check cable glands (sizes,tightness,....etc) and
gland plates.
18 All internal wiring connection are secure.
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 118
ENPPI
page 4 of 5
PROJECT NAME: COM. NO:510-14
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
25 Check D.C system [Refer to PC-CLF(510-08)].
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 119
"PC-CLF (510-14)"
page 5 of 5
VOLTAGE WITHSTAND TEST
TABLE [I]
N.B :
- All current transformer secondaries shall be short circuit for the duration
of the test.
- Test shall be carried out with all circuit breakers, isolators and switches
closed, but with all the cable cores disconnected.
INSULATION TEST.
TABLE [II]
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 120
ENPPI
page 1 of 4
PROJECT NAME: COM. NO:510-15
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
1 Check equipment assembly for alignment,
evelness and foundation fixing details.
2 Remove any accidental connections between
components.
3 Check equipment earthing connections.
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 121
ENPPI
page 2 of 4
PROJECT NAME: COM. NO:510-15
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
11 Tie raps to be used for cable and wires fixation.
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 122
ENPPI
page 3 of 4
PROJECT NAME: COM. NO:510-15
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
20 Check wire ends to be fitted with crimped type
terminals.
21 Holes that are not used but are planned for
future equipments or instruments are correctly
blanked off.
22 Equipment test report and inspection certificate
to be checked. Acceptance criteria values of
the all mentioned tests to be revised.
23 Check availability of vendor documents
,including commissioning and start-up
instructions.
24 Wiring of control and protection devices to be
checked w.r.t approved documents.
25
26
27
28
29
REMARKS:
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 123
"PC-CLF(510-15)"
page 4 of 4
TABLE [I]
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 124
ENPPI
page 1 of 5
PROJECT NAME: COM. NO:510-17
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
1 Check equipment assembly for alignment,
evelness and foundation fixing details.
2 Check all busbar connections (Torque check
with a torque wrench)and covers according to
the approved documents and supplier
recommendations.
3 Check equipment earthing connections.
REMARKS:
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 125
ENPPI
page 2 of 5
PROJECT NAME: COM. NO:510-17
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
10 Check connection and data of voltage
transformers.
11 Remove any accidental connections between
phases and from phases to ground.
12 Insulation resistance test of busbar bolted
connections (Between phases and phases to
ground). (*)
13 Check equipment anti- condensation heaters
and test insulation resistance.(**)
14 Voltage withstand test of both the main and au,
this shall be carried out between phases and
phases to ground (***).
15 Wire identifications and cable markers to be
checked w.r.t cable list.
16 Check cable glands (sizes,tightened,....etc) and
gland plates.
REMARKS:
(*) Refer to table [II]
(**) 500 v megger, min. 10 meg.ohm
(***) Refer to table [I]
CONTRACTOR ENPPI CLIENT
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 126
ENPPI
page 3 of 5
PROJECT NAME: COM. NO:510-17
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
17 Termination of power and control cables to be
checked.
18 Check all internal components such as:
Relays,fuses,....etc
19 Check connection of gland plate to the earthing
busbar.
20 Cable entries to be sealed wherever indicated in
the dwg,s
21 Tie raps to be used for cables and wires
fixation.
22 Holes that are not used but are planned for
future equipments or instruments are correctly
blanked off.
23 Check D.C system Refer to PC-CLF(510-08).
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 127
ENPPI
ELECTRICAL MECHANICAL COMPLETION &
PRE-COMMISSIONING CHECK LIST
L.V EXPLOSION PROOF SWR.
"PC-CLF (510-17)"
page 4 of 5
PROJECT NAME: COM. NO:510-17
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
26 All internal wiring connection are secure.
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 128
"PC-CLF (510-17)"
page 5 of 5
TABLE [I]
N.B :
- All current transformer secondaries shall be short circuit for the duration
of the test.
- Test shall be carried out with all circuit breakers, isolators and switches
closed, but with all the cable cores disconnected.
INSULATION TEST.
TABLE [II]
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 129
ENPPI
page 1 of 4
PROJECT NAME: COM. NO:510-21
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
1 Check equipment assembly for alignment,
levelness and foundation fixing details.
2 Check all internal connections related to the
capacitor banks and to be according to the
approved documents and supplier
recommendations.
3 Check equipment earthing connections.
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 130
ENPPI
page 2 of 4
PROJECT NAME: COM. NO:510-21
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
9 Voltage withstand test of both the main and
aux. circuits, this shall be carried out between
phases and phases to ground (***).
10 Check all internal components such as:
Relays,fuses,....etc
11 Check equipment anti condensation heaters and
test insulation resistance.(**)
12 Wire identifications and cable markers to be
checked w.r.t cable list.
13 Check cable glands (sizes,tightened,....etc) and
gland plates.
14 Check connection , polarity and ratio of C.T's.
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 131
ENPPI
page 3 of 4
PROJECT NAME: COM. NO:510-21
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
17 Check rating and type of all internal
components such as: Relays,fuses,....etc, w.r.t
approved documents.
18 Equipment test report and inspection certificate
to be checked. Acceptance criteria values of
all mentioned tests to be revised.
19 Conductivity tests shall be carried out on
switchgear bus- bar connections and
switchgear
earth system joints in order to check their
tightness.(****)
20 Apply 15 k.v D.C (Bus-bar system)for one
minute connect phases to ground, record
leakage current in m.amp.
21
22
23
24
25
REMARKS: (****) Conductivity testing shall be carried
with a low-resistance test set,
e.g. a "Ducter" with 20 A (d.c) output.
CONTRACTOR ENPPI CLIENT
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 132
"PC-CLF (510-21)"
page 4 of 4
TABLE [I]
N.B :
- All current transformer secondaries shall be short circuit for the duration
of the test.
- Test shall be carried out with all circuit breakers, isolators and switches
closed, but with all the cable cores disconnected.
INSULATION TEST.
TABLE OF MINIMUM TEST VOLTAGES.
TABLE [II]
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 133
ENPPI
page 1 of 3
PROJECT NAME: COM. NO:520-01
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
1 Check that lighting equipments are correctly
located and not obstructed by other
equipments.
2 Check that lighting panels are correctly fixed to
the structure or walls (as per installation
details).
3 Check mechanical operation of circuit breakers.
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 134
ENPPI
page 2 of 3
PROJECT NAME: COM. NO:520-01
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
9 Position of socket outlets as per approved
documents.
10 Check the distribution board circuit numbering
and the fuse ratings & check any safety
features such as interlocks, padlocks ,...etc.
11 Check that the distribution board supply cable
has been tested in accordance with the cable
inspection and test procedures.
12 Check cable termination at circuit j.box's and
each fixture.
13 Insulation resistance (500 v megger, min. 10 M.
OHMS).
14 Check availability of vendor documents,
including commissioning and start-up
instructions.
15 Equipment test report and inspection certificate
to be checked. Acceptance criteria values of all
mentioned tests to be revised.
REMARKS:
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 135
ENPPI
page 3 of 3
PROJECT NAME: COM. NO:520-01
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
16 Connection and function of photo-cells to be checked as
per approved documents.
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
REMARKS:
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 136
ENPPI
page 1 of 2
PROJECT NAME: COM. NO:530-01
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
1 Trays, supports and conduits are correctly fixed
to structure and aligned.
2 Check that bending radius of conduits is not
less the minimum established.
3 Check trays to be fitted with covers and
correctly fixed, if anticipated in the design.
4 Check threaded joints of conduits, fittings are
well tightened and oiled.
5 Check that conduits for road crossings, that are
not used are internally cleaned and plugged.
6 Earthing loops of cable trays to be checked.
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 137
ENPPI
page 2 of 2
PROJECT NAME: COM. NO:530-01
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
Check installation of conduits and cable trays as
9
per supplier instructions and approved documents.
Check cable conduits to be fitted with conduit
10
clamps at a proper locations, enough quantities
and suitable size.
11
12
13
14
15
16
17
18
19
20
21
22
23
REMARKS:
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 138
ENPPI
page 1 of 6
PROJECT NAME: COM. NO:541-01
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
1 Check that all cables (power/ control) are
installed in accordance with cable lists and
approved documents.
2 Check that the bending radius of cables is not
less than the minimum stablished.
3 Cables to be tested ( continuity/insulation
resistance) between phases and phases to
ground and in both directions at splice points
before
splicing and then retested after completion of
splicing.(*)
4 Cable markers to be installed before covering
buried cables or cables in cable trays.
5 Check that buried cables are correctly covered
and protected.
6 Check connection, termination and joints of
cables are correctly executed.
REMARKS:
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 139
ENPPI
page 2 of 6
PROJECT NAME: COM. NO:541-01
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
7 Check cables are correctly fixed to trays and
supports.
8 Check cables through walls or ceilings are
correctly sealed.
9 Check identification tag's of all conductors and
wires.
10 Check cable glands for tightnss and good work
manship and check the correct type of gland
has been used for the size and type of installed
cables.
11 Check that the gland plates has been
manufactured from non-magnetic materials.
12 Check where conductors have been terminated
using crimped connections, ensure that the
correct size and type of crimping lugs has
been used.
13 Cables test report and inspection certificate to
be
checked. Acceptance criteria values of all
mentioned tests to be revised.
REMARKS:
(*) Refer to table (III).
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 140
ENPPI
page 3 of 6
PROJECT NAME: COM. NO:541-01
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
14 Trench markers to be checked w.r.t approved
documents.
15 SUBMARINE POWER CABLES :
15.1 Check installation and erection as per supplier
instruction of all accessories required for
submarine power cables protection, laying,
termination and testing. These shall include,
but not limited to, kits for cable splicing and
termination, clamping system, interfacing
joint boxes,...etc.
15.2 Cables test report and inspection certificate to
be
checked. Acceptance criteria values of all tests
to be revised.
15.3 Check that route of submarine cables according
to the site survey report to avoid any
unexpected situation that may affect the correct
cable positioning.
REMARKS:
(*) Refer to table (III).
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 141
ENPPI
page 4 of 6
PROJECT NAME: COM. NO:541-01
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
15 SUBMARINE POWER CABLES : cont'n
15.4 D.C insulation test to be performed before
energizing the cables .
15.5 Check that submarine cables laid in J-tubes up
to the platform deck.
15.6 sealing ends connections and termination to the
interface junction boxes to be executed
according to the supplier instructions.
15.7 Cable armour should be protected against
corrosion, which is due to the cathodic
reaction.
15.8 Check that submarine cables when crossing
coral reef is to be protected by a suitable
method, recommended by the supplier (e.g
split cast iron
shells).
15.9 check anchoring and clamping of submarine
cables.
REMARKS:
(*) Refer to table (III).
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 142
ENPPI
page 5 of 6
PROJECT NAME: COM. NO:541-01
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
15 SUBMARINE POWER CABLES : cont'n
15.10 Check that submarine cables in the proximity of
the platform, the cable shall be protected by
sand/cement bags for an extension of 50
meters sea- wards.
15.11 The submarine cables to be tested after the two
relevant sealing-ends are assembles and before
connecting the cables to the junction box.
15.12 The submarine cables to be tested after the two
relevant sealing-ends are assembles and before
connecting the cables to the junction box.
15.13
15.14
15.15
16
17
18
REMARKS:
(*) Refer to table (III).
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 143
"PC-CLF (541-01)"
INSULATION TEST
page 6 of 6
TABLE (III)
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 144
ENPPI
page 1 of 6
PROJECT NAME: COM. NO:542-01
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
1 Check that all cables are installed in accordance
with cable lists and approved documents.
2 Check that the bending radius of cables is not
less than the minimum stablished.
3 Cables to be tested ( continuity/insulation
resistance) between phases and phases to
ground and in both directions at splice points
before
splicing and then retested after completion of
splicing.(*)
4 Cable markers to be installed before covering
buried cables or cables in cable trays.
5 Check that buried cables are correctly covered
and protected.
6 Check connection, termination and joints of
cables are correctly executed.
REMARKS:
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 145
ENPPI
page 2 of 6
PROJECT NAME: COM. NO:542-01
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
7 Check cables are correctly fixed to trays and
supports.
8 Check cables through walls or ceilings are
correctly sealed.
9 Check identification tag's of all conductors and
wires.
10 Check cable glands for tightness and good work
manship and check the correct type of gland
has been used for the size and type of installed
cables.
11 Check that the gland plates has been
manufactured from non-magnetic materials.
12 Check where conductors have been terminated
using crimped connections, ensure that the
correct size and type of crimping lugs have
been used.
13 Apply 15 K.V D.C test voltage leakage for (15)
min. between phases and earth and record
leakage current in m.amp.
REMARKS:
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 146
ENPPI
page 3 of 6
PROJECT NAME: COM. NO:541-01
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
14 Trench markers to be checked w.r.t approved
documents.
15 SUBMARINE POWER CABLES :
15.1 Check installation and erection as per supplier
instruction of all accessories required for
ubmarine power cables protection, laying,
termination and testing. These shall include,
but not limited to, kits for cable splicing and
termination, clamping system, interfacing
joint boxes,...etc.
15.2 Cables test report and inspection certificate to
be
checked. Acceptance criteria values of all tests
to be revised.
15.3 Check that route of submarine cables according
to the site survey report to avoid any
unexpected situation that may affect the correct
cable
positioning.
REMARKS:
=
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 147
ENPPI
ELECTRICAL MECHANICAL COMPLETION &
PRE-COMMISSIONING CHECK LIST
MEDIUM VOLTAGE CABLES.
"PC-CLF (542-01)"
page 4 of 6
PROJECT NAME: COM. NO:541-01
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
15 SUBMARINE POWER CABLES : cont'n
15.4 The following tests to be performed before
energizing the cables
- D.C insulation test
- D.c voltage test
15.5 Check that submarine cables laid in J-tubes up
to the platform deck.
15.6 check anchoring and clamping of submarine
cables.
15.7 sealing ends connections and termination to the
interface junction boxes to be executed
according to the supplier instructions.
15.8 Check that submarine cables when crossing
coral reef is to be protected by a suitable
method, recommended by the supplier (e.g
split cast iron
shells).
15.9 Cable armour should be protected against
corrosion, which is due to the cathodic
reaction.
REMARKS:
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 148
ENPPI
page 5 of 6
PROJECT NAME: COM. NO:541-01
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
15 SUBMARINE POWER CABLES : cont'n
15.10 Check that submarine cables in the proximity of
the platform, the cable shall be protected by
sand/cement bags for an extension of 50
meters sea- wards.
15.11 The submarine cables to be tested after the two
relevant sealing-ends are assembles and before
connecting the cables to the junction box.
15.12 The submarine cables to be tested after the two
relevant sealing-ends are assembles and before
connecting the cables to the junction box.
15.13
14.14
15.15
16
17
18
REMARKS:
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 149
"PC-CLF (542-01)"
INSULATION TEST
page 6 of 6
TABLE (III)
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 150
ENPPI
page 1 of 2
PROJECT NAME: COM. NO:550-01
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
1 Calibration test certificate of testing equipment
to be checked.
2 Check that cables rising from ground are
protected means of a conduits ( PVC
CONDUITS).
3 Check that buried connections of cables are
protected against damp with adhesive tape.
4 All Grounding terminals to be cleaned by wire
brush and greased with petroleum jelly.
5 Check that all Grounding bus- bar joints or
conductor fixing bolts are well tightened.
6 All Grounding bus-bars to be cleaned by wire
brush and greased with petroleum jelly.
7 Check connections of all grounding well rods.
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 151
ENPPI
page 2 of 2
PROJECT NAME: COM. NO:550-01
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
9 Check continuity test of grounding branches.
11
12
13
14
15
..... 16
17
18
19
20
21
22
23
REMARKS:
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 152
ENPPI
page 1 of 1
PROJECT NAME: COM. NO:560-01
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
1 Type of control stations and selector switches
to be checked w.r.t approved documents.
2 Location of control stations are correctly as per
approved documents.
3 Termination of control cables to be checked.
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 153
APPENDIX 3.0
COMMISSIONING ACTIVITIES
CONTENTS
1.0 GENERAL.
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 154
COMMISSIONING ACTIVITIES
1.0 GENERAL
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 155
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 156
ENPPI
ELECTRICAL COMMISSIONING CHECK LIST
PACKAGE EQUIPMENT.
"C-CLF (500-02)"
Page 1 of 1
PROJECT NAME: COM. NO:500-02
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
1 Vendor document to checked for
commissioning and start-up instructions
2 Calibration test certificate of testing equipment
to be checked.
3 BATTERIES AND CHARGER :-
Refer to C-CLF (510-08).
4 LIGHTING SYSTEM :-
Refer to C-CLF (520-01).
5 ELECTRICAL POWER DISTRIBUTION
BOARD(S) :- Refer to C-CLF (510-13) and
C-CLF (510-04).
6 LOCAL MOTOR CONTROL STATIONS :-
Refer to C-CLF (530-01).
7 MOTORS :-
Refer to C-CLF (500-03).
8 Approved test result record forms to be used.
9
10
11
12
13
14
15
16
REMARKS:
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 157
ENPPI
ELECTRICAL COMMISSIONING CHECK LIST.
MOTORS.
"C-CLF (500-03)"
page 1 of 2
PROJECT NAME: COM. NO: 500-03
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
1 Vendor document to checked for
commissioning and start-up instructions
2 Calibration test certificate of testing equipment
to be checked.
3 Running test of two hours and maintain
constant check of bearing and housing temp. to
detect abnormal temp raise or vibration.
4 Check that all instrument such as : oil level
indicators are calibrated and functioning
correctly (applicable to H.V motors).
5 Measure the terminals voltage and line current
of the free running motors.
6 Functional checking of motors from remote
locations such as: control room and local
control
stations.
7 Test report including test results and test
acceptance criteria values to be attached
with commissioning check list forms.
REMARKS:
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 158
ENPPI
ELECTRICAL COMMISSIONING CHECK LIST.
MOTORS.
"C-CLF (500-03)"
page 2 of 2
PROJECT NAME: COM. NO: 500-03
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
8 Check functional operation of space heater.
9 Approved test result record forms to be used.
11.2
11.3
11.4
11.5
12
13
14
15
16
REMARKS:
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 159
ENPPI
ELECTRICAL COMMISSIONING CHECK LIST.
POWER TRANSFORMER.
"C-CLF 510-02)"
page 1 of 2
PROJECT NAME: COM. NO:510-02
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
1 Vendor document to checked for
commissioning and start-up instructions
2 Calibration test certificate of testing equipment
to be checked.
3 check fan controls.
4 Check alarm indications.
5 Check no load and full load voltages at main
bus.
6 Mechanical and electrical operation of aux.
devices such as: tap changer, breathers, shut
off valves, meters, temp. indicators,
relays,....etc. to be checked.
7 Check with transformer energized at rated
voltage record tap position and secondary open
circuit voltage at switch board terminals.
8 Test reports including test results and
acceptance certificate values to be attached with
commissioning check list forms.
9 Check alarm and trip controls for proper
operation.
10 Inspection, testing and functional checks to be
performed according to supplier instructions.
11 Approved test result record forms to be used.
REMARKS:
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 160
ENPPI
ELECTRICAL COMMISSIONING CHECK LIST.
POWER TRANSFORMER.
"C-CLF (510-02)"
page 2 of 2
PROJECT NAME: COM. NO:510-02
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
12 Check for correct phase, rotation and polarity
before energizing.
13
14
15
16
17
18
19
20
21
22
23
24
25
REMARKS:
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 161
ENPPI
ELECTRICAL COMMISSIONING CHECK LIST.
M.V SWITCHGEAR AND MOTOR CONTROL GEAR
"C-CLF (510-03)"
page 1 of 2
PROJECT NAME: COM. NO: 510-03
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
1 Calibration test certificate of testing equipment
to be checked.
2 Approved test result record forms to be used.
3 Test and calibration of all relays and, meters
using secondary injection & setting of all
protective devices to be checked w.r.t
approved documents.
4 Check operation and function of C.B's(
outgoing, bus-tie, ...etc) and motor starters.
5 Check breaker electrical indications at all
positions.
6 Functional checking of switchgear from remote
locations such as: control room, motor local
control stations.
7 Check function operation of space heaters.
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 162
E N P P.I
ELECTRICAL COMMISSIONING CHECK LIST.
MV SWITCHER AND MOTOR CONTROL GEAR
"C-CLEF (510-03)"
Page 2 of 2
PROJECT NAME: COM. NO: 510-03
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
11 Check operation of truck/tray aux. contacts.
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
REMARKS:
================================================================
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 163
ENPPI
ELECTRICAL COMMISSIONING CHECK LIST.
L.V SWITCHGEAR AND MOTOR CONTROL CENTER.
"C-CLF (510-04)"
page 1 of 2
PROJECT NAME: COM. NO: 510-04
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
1 Calibration test certificate of testing equipment
to be checked.
2 Approved test result record forms to be used.
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 164
ENPPI
ELECTRICAL COMMISSIONING CHECK LIST.
L.V SWITCHGEAR AND MOTOR CONTROL CENTER.
"C-CLF (510-04)"
page 2 of 2
PROJECT NAME: COM. NO: 510-04
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
11 Check operation of truck/tray aux. contacts
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
REMARKS:
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 165
ENPPI
ELECTRICAL COMMISSIONING CHECK LIST.
M.V INDEPENDENT CIRCUIT BREAKERS.
"C-CLF (510-05)"
page 1 of 2
PROJECT NAME: COM. NO: 510-05
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
1 Calibration test certificate of testing equipment
to be checked.
2 Approved test result record forms to be used.
0000-000-5-EI-0-
850-186-1-X
PAGES 186 PAGE 166
ENPPI
ELECTRICAL COMMISSIONING CHECK LIST.
M.V INDEPENDENT CIRCUIT BREAKERS.
"C-CLF (510-05)"
page 2 of 2
PROJECT NAME: COM. NO: 510-05
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
11 Check operation of truck/tray aux. contacts.
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
REMARKS:
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 167
ENPPI
ELECTRICAL COMMISSIONING CHECK LIST.
A.C GENERATOR .
"C-CLF (510-06)"
page 1 of 3
PROJECT NAME: COM. NO: 510-06
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
1 Calibration test certificate of testing equipment
to be checked.
2 Functional checking of A.C generator from
remote location such as : control panel.
3 Test report including test results and test criteria
values to be attached with commissioning
check list forms.
4 Inspection, testing and functional checks to be
performed according to supplier instructions.
5 Check operation and function of C.B's, relays,
indicators, protection devices,.....etc.
6 Approved test result record forms to be used.
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 168
ENPPI
ELECTRICAL COMMISSIONING CHECK LIST.
A.C GENERATOR.
"C-CLF (510-06)"
page 2 of 3
PROJECT NAME: COM. NO: 510-06
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
7.3 Generator phase rotation: verify phase rotation
of
generator by means of an L.V phase rotation
meter.
7.4 Protection tests:
- Differential relay stability check.
- Differential relay sensi tivity check.
- Other items of protection and indication
devices may also be verified at this time if
not already done by primary current injection.
- Over speed test.
- Over temp. test.
- Vibration measurement.
- Noise level test.
8 Post synchronizing checks (generator
running, loaded).
8.1 Synchronize test to grid. (As interfacing with
L.V swg)
8.2 Function tests: the following shall be
confirmed:
- Auto and manual synchronizing
- Control of power factor over full range of
power generation.
- The change over of AVR from power factor to
voltage control.
- Over load test.
8.3 12 hours full load test.
9 Protection tests:
9.1 Functions of governor to be checked.
REMARKS:
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 169
ENPPI
ELECTRICAL COMMISSIONING CHECK LIST.
A.C GENERATOR.
"C-CLF (510-06)"
page 3 of 3
PROJECT NAME: COM. NO: 510-06
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
9.2 The operation of the reverse power relay to be
verified by decreasing the governor setting.
9.3 The operation of the field failure relay to be
verified by decreasing the excitation at
minimum load. setting.
9.4 Functions of AVR to be checked.
10 Check D.C system Refer to C-CLF (510-08).
14
15
16
17
18
19
REMARKS:
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 170
ENPPI
ELECTRICAL COMMISSIONING CHECK LIST.
BATTERIES AND BATTERY CHARGER.
"C-CLF (510-08)"
page 1 of 2
PROJECT NAME: COM. NO: 510-08
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
1 Calibration test certificate of testing equipment
to be checked.
2 Approved test result record forms to be used.
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 171
ENPPI
ELECTRICAL COMMISSIONING CHECK LIST.
BATTERIES AND BATTERY CHARGER.
"C-CLF (510-08)"
page 2 of 2
PROJECT NAME: COM. NO: 510-08
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
9 Check connected loads to ensure that it is still
accordance with approved documents.
10 Test report including test results and test criteria
values to be attached with commissioning
check list forms.
11 Inspection, testing and functional checks to be
performed according to supplier instructions.
12 Check operation and function of C.B's, relays,
indicators, protection devices,.....etc.
13 Check function operation of space heaters.
16
17
18
19
20
REMARKS:
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 172
ENPPI
ELECTRICAL COMMISSIONING CHECK LIST.
NAVIGATION AIDS SYSTEM.
"C-CLF (510-10)"
page 1 of 2
PROJECT NAME: COM. NO: 510-10
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
1 Approved test result record forms to be used.
2 Check of all power, control, auxiliary circuits
and equipment.
3 Tests shall be carried out on the completed
equipment and not limited to the following:
* charger/batteries tests. and functional
operation, interlocks,..etc
* operation of white lights, including lamp
changeover.
* operation of subsidiary lights including lamp
changeover.
* synchronizing between existing and new
equipments.
* operation of fog horns,helideck lights,...etc.
* Operation of controls & alarms on battery
charger
* Photo-cell control operation.
4 Check operation of protective devices such as :
* Battery earth fault alarm.
* Charge failure alarm.
* D.C over and under voltage alarms.
* Battery charger rectifier failure alarm.
5 Test report including test results and test criteria
values to be attached with commissioning
check list forms.
REMARKS:
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 173
ENPPI
ELECTRICAL COMMISSIONING CHECK LIST.
NAVIGATION AIDS SYSTEM .
"C-CLF (510-10)"
page 2 of 2
PROJECT NAME: COM. NO: 510-10
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
Calibration test certificate of testing equipment to be
checked.
8 Check operation and function of C.B's, relays, indicators,
protection devices,.....etc.
9 Inspection, testing and functional checks to be performed
according to supplier instructions.
10
11
12
13
14
15
16
17
18
19
20
REMARKS:
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 174
ENPPI
ELECTRICAL COMMISSIONING CHECK LIST.
HEAT TRACING SYSTEM .
"C-CLF (510-11)"
page 1 of 1
PROJECT NAME: COM. NO: 510-11
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
1 Calibration test certificate of testing equipment
to be checked.
2 Check correct operation of all indication lamps
and remote indications.
3 Approved test result record forms to be used.
10
11
12
REMARKS:
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 175
ENPPI
ELECTRICAL COMMISSIONING CHECK LIST.
UNINTERRUPTABLE POWER SUPPLY.
C-CLF (510-12)"
page 1 of 2
PROJECT NAME: COM. NO: 510-12
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
1 Calibration test certificate of testing equipment
to be checked.
2 Approved test result record forms to be used.
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 176
ENPPI
ELECTRICAL COMMISSIONING CHECK LIST.
UNINTERRUPTABLE POWER SUPPLY.
"C-CLF (510-12)"
page 2 of 2
PROJECT NAME: COM. NO: 510-12
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
10 Check function operation of space heaters.
11 Inspection, testing and functional checks to be
performed according to supplier instructions.
12 Check alarm and trip indication of protection
and control signaling.
13 Check operation and functions of BY-PASS
circuits.
14 Check operation and functions
of TRANSFER SWITCH circuits.
15 Check functions of INVERTER CIRCUITS
operation.
16 Check D.C system Refer to C-CLF (510-08).
19
20
21
22
REMARKS:
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 177
ENPPI
ELECTRICAL COMMISSIONING CHECK LIST.
SMALL POWER DISTRIBUTION PANEL.
"C-CLF (510-13)"
page 1 of 2
PROJECT NAME: COM. NO: 510-13
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
1 Calibration test certificate of testing equipment
to be checked.
2 Approved test result record forms to be used.
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 178
ENPPI
ELECTRICAL COMMISSIONING CHECK LIST.
SMALL POWER DISTRIBUTION PANEL.
"C-CLF (510-13)"
page 2 of 2
PROJECT NAME: COM. NO: 510-13
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
11 Check bus bar and circuit shutters.
14
15
16
17
18
19
20
21
22
23
24
25
REMARKS:
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 179
ENPPI
ELECTRICAL COMMISSIONING CHECK LIST.
RING MAIN UNITS.
"C-CLF (510-14)"
page 1 of 2
PROJECT NAME: COM. NO: 510-14
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
1 Calibration test certificate of testing equipment
to be checked.
2 Approved test result record forms to be used.
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 180
ENPPI
ELECTRICAL COMMISSIONING CHECK LIST.
RING MAIN UNITS.
"C-CLF (510-14)"
page 2 of 2
PROJECT NAME: COM. NO: 510-14
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
11 Check bus bar and circuit shutters.
14
15
16
17
18
19
20
21
17
18
19
20
REMARKS:
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 181
ENPPI
ELECTRICAL COMMISSIONING CHECK LIST.
SYNOPTIC CONTROL PANEL.
"C-CLF (510-15)"
page 1 of 1
PROJECT NAME: COM. NO: 510-15
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
1 Calibration test certificate of testing equipment
to be checked.
2 Approved test result record forms to be used.
3 Functional checking of synoptic control panel
and all related elect. equipment such as :
M.Vswitchgear & low voltage M.C.C,...etc.
4 Check function operation of space heaters.
11
12
REMARKS:
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 182
ENPPI
ELECTRICAL COMMISSIONING CHECK LIST.
LOW VOLTAGE EXPLOSION PROOF SWITCHRACK.
"C-CLF (510-17)"
page 1 of 2
PROJECT NAME: COM. NO: 510-17
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
1 Calibration test certificate of testing equipment
to be checked.
2 Approved test result record forms to be used.
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 183
ENPPI
ELECTRICAL COMMISSIONING CHECK LIST.
LOW VOLTAGE EXPLOSION PROOF SWITCHRACK.
"C-CLF (510-17)"
page 2 of 2
PROJECT NAME: COM. NO: 510-17
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
11 Check bus bar and circuit shutters.
14
15
16
17
18
19
20
21
22
23
24
25
REMARKS:
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 184
ENPPI
ELECTRICAL COMMISSIONING CHECK LIST.
POWER FACTOR CORRECTION EQUIPMENT.
"C-CLF (510-21)"
page 1 of 1
PROJECT NAME: COM. NO: 510-21
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
1 Check function operation of power factor
regulator.
2 Mechanical and electrical operation of all
functional parts to be checked.
3 Test report including test results and test criteria
values to be attached with commissioning
check list forms.
4 Inspection, testing and functional checks to be
performed according to supplier instructions.
5
10
11
12
13
REMARKS:
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 185
ENPPI
ELECTRICAL COMMISSIONING CHECK LIST.
LIGHTING AND SMALL POWER.
"C-CLF (520-01)"
page 1 of 1
PROJECT NAME: COM. NO: 520-01
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
1 Illumination levels of out door and indoor
locations to be measured and compared w.r.t
approved documents.
2 Check functional operation of photo-cells.
3 Normal lighting shall be momentirily
interrupted for checking of functional operation
of
emergency lighting system.
4 Test report including test results and test
acceptance criteria values to be attached with
commissioning check list forms.
5
6
7
8
9
10
11
12
13
14
15
16
REMARKS:
0000-000-5-EI-0-850-186-1-X
PAGES 186 PAGE 186
ENPPI
ELECTRICAL COMMISSIONING CHECK LIST.
CONTROL STATIONS.
"C-CLF (560-01)"
page 1 of 1
PROJECT NAME: COM. NO: 560-01
PROJECT NO : SUPPLIER:
AREA : DATE :
ITEM DESCRIPTION YES NO N/A
1 Approved test result record forms to be used.
2 Check functional operation of control stations
and selector switches from remote or local
locations.
3 Check functional operation of indication lamps
or ammeters.
4 Inspection, testing and functional checks to be
performed according to supplier instructions.
5 Check selector switch operation and locking
facilities.
6 Test report including test results and test criteria
values to be attached with commissioning
check list forms.
7
8
9
10
11
12
13
14
15
REMARKS:
0000-000-5-EI-0-850-186-1-X