UANTITIES ON 1.00 Typical Bldg. (1) = TOTAL ON 1.00 Typical Bldg.

(2) =
VIL WORKS Bldg. (1) - Total (1) Typ Blg (1) Bldg (2) - Total (2)
OUNDATIONS F1 F2 F3 F3 F1 SF1 F3
No. No. 16.00 7.00 1.00 24.00 24.00 4.00 1.00 - 5.00
Lx m 1.80 2.10 3.20 1.40 20.50 -
Ly m 1.40 1.60 3.00 1.20 0.60 -
D m 0.50 0.50 0.40 0.50 0.40 -
Volume m3 20.16 11.76 3.84 35.76 35.76 3.36 4.92 - 8.28
Curing Area (water, Hessian, polythene 500) m2 91.52 49.42 14.56 155.50 155.50 17.12 29.18 - 46.30
Bitumen Paint 3 coats m2 91.52 49.42 14.56 155.50 155.50 17.12 29.18 - 46.30
Horizontal Water proofing Membrane -1000GA m2 - - - - - - - - -
Vertical Water proofing Membrane -1000GA Pom2 - - - - - - - - -
Protection board m2 - - - - - - - - -
Shuttering (footing shuttering area)
Side Shutter , 18 mm plywood m2 51.20 25.90 4.96 82.06 82.06 10.40 16.88 - 27.28
Bottom & Top Support,White wood 1x4" CuM 0.46 0.23 0.05 0.74 0.74 0.10 0.17 - 0.26
Edges Support, White wood 3x3" CuM 1.93 0.97 0.20 3.10 3.10 0.40 0.67 - 1.07
Sides Props White wood 3x3" CuM 1.26 0.62 0.13 2.01 2.01 0.28 0.37 - 0.65
Earth support White wood 3x3" CuM 0.59 0.30 0.07 0.97 0.97 0.12 0.25 - 0.37
Shuttering Bars 12mmx45cm (6 times) No. 256.00 126.00 26.00 408.00 408.00 56.00 76.00 - 132.00

Re-bars
Dia of Bottom Rebars B/Ys mm 16.00 16.00 14.00 14.00 12.00 -
Spacing m 0.15 0.15 0.15 0.15 0.15 0.20
Wt. of rebars (B/Ys) Ton 1.23 0.68 0.18 0.17 0.21 -
Dia of Top Rebars B/Ys mm 14.00 - - -
Spacing m 0.15 0.15 0.15 0.15 0.15 0.15
Wt. of rebars (B/Ys) Ton - - 0.18 - - -
Dia of CHAIRS Rebars mm - - - - - -
Rebar CHAIR (for double mesh) Ton - - - - - -
Steel Rebars (Top & Bott) Ton 1.23 0.68 0.36 2.28 2.28 0.17 0.21 - 0.38
PVC Spacers No. 528.00 280.00 65.00 873.00 873.00 132.00 152.00 - 284.00

BLINDING
PCC Thickness m 0.10 0.10 0.10 0.10 0.10
PCC Area / Polythene m2 51.20 28.98 10.88 91.06 91.06 8.96 16.56 - 25.52
PCC Shuttering White wood 1" x 4 " CuM 0.36 0.18 0.04 0.58 0.58 0.08 0.12 - 0.19
Shuttering Bars 12mmx45cm (6 times) No. 192.00 98.00 18.00 308.00 308.00 48.00 48.00 - 96.00
PCC Volume m3 5.12 2.90 1.09 9.11 9.11 0.90 1.66 - 2.55
PCC Bitumen Paint m2 51.20 28.98 10.88 91.06 91.06 8.96 16.56 - 25.52
Anti Termite
Anti Termite (Horizontal Surface) m2 124.80 64.68 18.48 207.96 207.96 24.96 39.06 - 64.02
Anti Termite (Vertical Surface) m2 268.80 128.10 25.80 422.70 422.70 60.00 70.50 - 130.50
EXCAVATION
Excavation ( Isolated footings) m2 187.20 97.02 27.72 311.94 311.94 37.44 58.59 - 96.03
Excavation ( strips) m2 - - - - - - - - -
Excavation ( Whole Area) m3 - - - - -