Professional Documents
Culture Documents
Peer Review Report on Center for Brain Research Iisc Bangalore 06.03.2020
Peer Review Report on Center for Brain Research Iisc Bangalore 06.03.2020
Peer Review Report on Center for Brain Research Iisc Bangalore 06.03.2020
ISSUE RECORD:
The building is essentially RC Structure with Beam slab system. These are located
so as to deal with all the functional requirement of the space. The columns and shear
walls are connected to each other with a network of R.C.C beams and with the slabs acting
as in plane-rigid diaphragms for each of the floor.
Agencies involved:
Preliminary checks were done on the shared documents wrt General arrangement drawing,
Soil report, structural behavior in ETABS and our input was shared to each one as below.
3.1.1 Geometry:
3.2.1.Material properties:
Material Properties defined are in good agreement with Design basis report.
-Frame section material properties defined are in good agreement with Design Basis
Report.
We have asked to correct the clear cover assigned to beams and columns as well as
arrangement of bars assigned to each individual frame section. The same is been
Resubmitted with necessary changes.
Few beams that are shown in the GA drawing are not considered in the ETABS
Model. For instance ( In ground floor beam sections located between grids H,K and
8,12 are missing. The revised detail have been resubmitted with necessary changes.
-Correct the beam situated between grids 8 and J,N in first floor.
Floor openings provided in architectural drawing and structural drawing were not
matching between grids j,k and 5,8. The detail have been resubmitted with necessary
changes.
Slab openings between grids 8,9 and j,k were corrected and revised drawings have
been resubmitted with necessary changes.
- General SFD and BMD behaviour of frames (Beams and Columns) is found to be in
order for given loading provided. However first floor Beam located on grids between
L,M and 4 were failing due to shear force and torsion put together. In 3rd,4th, 5th and
terrace floor beams located between grids K and 1,4 fail due to shear force and
torsion put together.
3.4.EARTHQUAKE ANALYSIS:
The permissible displacement as per IS 1893-2016 clause 7.11, shall not exceed 0.004
times the height ie 0.004 x 24.8 = 86.8 mm. The permissible storey drift as per
IS 1893-2016 clause 7.11, shall not exceed 0.004 times the storey height ie 0.004
X 3.9 = 15.6 mm. Hence the deformations of the structure is within acceptable limits.
Further, as per IS-1893 – 2016 clause 7.10.3b, the lateral stiffness in the open
- When base shear estimated using response spectrum method is compared with static
load method, the ratio is 1. Further, the analysis results are conforming to the codal
provisions as specified in IS1893-2016 table 6.
The detailed summary report is enclosed below.
LOAD CASE
STIFFNESS IN X STIFFNESS VARIATION
CONSIDERED
STOREY DIRECTION (kN/ BETWEEN SUCCESSIVE
FOR
m) LEVELS
STIFFNESS
LOAD CASE
STIFFNESS Iny STIFFNESS VARIATION
CONSIDERED
STOREY DIRECTION (kN/ BETWEEN SUCCESSIVE
FOR
m) LEVELS
STIFFNESS
ALLOWABLE
LOAD CASE DRIFT (mm) AS
STOREY
STOREY CONSIDERED DRIFT Y (mm) PER CLAUSE
HEIGHT (m)
FOR DRIFT 7.11.1 OF IS
1893 (2016)
TF EQY 0.719 15.6 3.9
5 EQY 0.784 15.6 3.9
4 EQY 0.793 15.6 3.9
3 EQY 0.795 15.6 3.9
2 EQY 0.712 15.6 3.9
1 EQY 0.528 15.6 3.9
0 EQY 0.47 20 5
-1 EQY 0.186 16.8 4.2
The following General arrangement drawings were attached with marked sections, Where in
discripancies were found wrt column, beam and slab sections when compared with ETABS
model. The same is been corrected and Re-submitted.
1. CF9 footing area in safe model is not matching as per the drawing and please check the
reinforcement
2. CF2 footing safe model that you have shared second time is also not matching as per the
drawing
4. Column C20 still needs to be updated in ETABS model as per the drawing.
6. As per the calculation details given for commented columns, it seems the calculations
stands for the old ETABS model as we foud variations in the forces taken by RCDC
compared to ETABS model, Kindly recheck or clarify.
7. Calculation sheets of column C10 and C20 are missing after the inundation.
8.Please share calculation sheet for CF6 & CF9 as it is not included in safe model.
10.CF2 footing area and depth in safe model in grid Q9 is not matching as per the
drawing.
11.CF1 SBC indicated in drawing is not matching with the safe model.
13.F7 SBC shown in drawing is not matching with SBC considered for design.
15.As per the soil report the SBC mentioned for independent footings at the depth of 7m is 60
tons/sqmt and at higher levels it is 45 tons/ sqmt. kindly clarify as the footing levels are at
higher levels and considered SBC is different.
16.mismatch found in the values of SBC mentioned in the drawing to the considered SBC
values in SAFE model for CF! footing.
17. There are significant variations in the total axial load considered for the design of footings
(ETABS and SAFE), clarify the same.
19. Mismatch in the column dimentions of C10 and SW5 with regard to GA drawing.
1.Please share calculation sheet for CF6 & CF9 as it is not included in safe model-
separate safe model for the footing is being shared.
2.CF8 area is not matching in safe model as per drawings- model for the same is
shared
3.CF2 footing area and depth in safe model in grid Q9 is not matching as per the -
model for the same is shared
drawing
4.CF1 SBC indicated in drawing is not matching with the safe model- sbc considered
is 100T/sqm
5.Please clarify whether the F1 footing is step footing or pad footing- Footing F1 is
pad footing
6.F7 SBC shown in drawing is not matching with SBC considered for design- footing
is design for 60t\sqm and calculation for the same as been shared earlier and the
same is resent again for your review.
8.Please find the attached Design calculation for Isolated footing and the foundation drawing.
9.The SBC considered is as per the soil report and recommendation by Prof. B.R. Srinivasa
Murthy and the same is attached. The recommendation for 60T/m^2
Is mentioned for footing with smaller loads and of smaller size (2mX2m). The same is
mentioned in the foundation dwg.
10.The mismatch of loads is been check from over end and we find there is no mismatch and
the same is conveyed over the phone. Kindly relook on the same.
11.Mismatch in column dimension is considered in the footing and column design after the
priliminary comments on the same for received.
12. The toe wall considered for the lift wall is design for the filling being done
simultaneously inside and outside the pit. The modeling of the same is not considered, we are
considering the toe wall to just retain the soil and not bet part of the load carrying system.
On reviewing the canopy structural design drawings and details of the canopy
structure, the following observations were made.
Steel ISMC members provided as tie between canopy structure and main
structure to be checked along with insert plate and lugs specification with
respect to dia and anchorage length provided for forces in range of 300kn as
per staad model and the documents to be provided.
Principal structural consultant have replied to the same saying “ The canopy scheme
was proposed considering the steel members for the overall stability and we are not
considering canopy structure separately.” The same was discussed in the joint
meeting and agreed on it with the precautionary measures as follows
For the structural steel members which is critical from stability of canopy
structure, fire resistant paint and anti corrosion treatment to be done to ensure
the longevity of these members.
The type of treatment to be done in the drawings itself and submit along with
the other details sought for final checking.
DRAWING DRAWING
JOB NO REMARKS
TITLE NUMBER
Design basis
SFCS.18.1347(A) - APPROVED
report.
Reinforcement
SFCS.18.1347(A) details of CBRST.BSMT.02.BM APPROVED
plinth beam
Grade slab
SFCS.18.1347(A) details at CBR.ST.MD.05.CS APPROVED
plinth lvl
CBR.ST.00.FDN.CS
Column
SFCS.18.1347(A) schedule APPROVED
details
(SHEET 01 OF 02)
CBR.ST.00.FDN.CS
Lift wall
SFCS.18.1347(A) APPROVED
details
(SHEET 02 OF 02)
Mass
SFCS.18.1347(A) excavation CBR.ST.00.01.ME APPROVED
layout
General
arrangement
SFCS.18.1347(A) APPROVED
of beams and
slabs at
Ground floor
SFCS.18.1347(A) CBR.ST.GR.01.GA APPROVED
lvl
General
arrangemrnt
SFCS.18.1347(A) of beams and CBR.ST.1ST.01.GA APPROVED
slabs at first
floor lvl
Reinforcement
detail of
SFCS.18.1347(A) CBR.ST.1ST.02.BM APPROVED
beams at first
floor lvl
Reinforcement
detail of slab
SFCS.18.1347(A) CBR.ST.1ST.03.SL APPROVED
at first floor
lvl
Reinforcement
detail of
SFCS.18.1347(A) beams at CBR.ST.02.02.BM APPROVED
second floor
lvl
General
arrangemrnt
SFCS.18.1347(A) of beams and CBR.ST.3RD.01.GA APPROVED
slabs at third
floor lvl
Reinforcement
detail of
SFCS.18.1347(A) CBR.ST.03.02.BM APPROVED
beams at third
floor lvl
Reinforcement
detail of slab
SFCS.18.1347(A) CBR.ST.03.03.SL APPROVED
at third floor
lvl
Reinforcement
detail of
SFCS.18.1347(A) CBR.ST.04.02.BM APPROVED
beams at
fourth floor lvl
Reinforcement
detail of slab
SFCS.18.1347(A) CBR.ST.02.03.SL APPROVED
at fourth floor
lvl
General
arrangemrnt
SFCS.18.1347(A) of beams and CBR.ST.05.01.GA APPROVED
slabs at fifth
floor lvl
Reinforcement
detail of
SFCS.18.1347(A) CBR.ST.05.02.BM APPROVED
beams at fifth
floor lvl
Reinforcement
detail of slab
SFCS.18.1347(A) CBR.ST.05.03.SL APPROVED
at fifth floor
lvl
Reinforcement
detail of
SFCS.18.1347(A) beams at CBR.ST.06.02.BM APPROVED
terrace floor
lvl
Reinforcement
detail of slab
SFCS.18.1347(A) CBR.ST.06.03.SL APPROVED
at terrace floor
lvl
Footing reinf.
SFCS.18.1347(A) APPROVED
details