SIMERA, BEA MICHAELA C. 2. Fabrication and installation of tubular steel rafters and battens.

DEL PILAR, ANNE CLARISSE P. 3. Welding works and cutting lists of tubular steel.
ARCH 401-N 4. Base plates of 0.15m x 0.15m x 8mm with 4-12mm Ø holes
5. Fully welded at the base of the tubular steel column.
WORK BREAKDOWN SCHEDULE OF WAITING SHED 6. Full weld installation will be used for the installation of tubular steel rafters and battens
A. SITE PREPARATION
1. CLEARING THE SITE I. BENCH STEEL WORK
2. STAKES AND BATTER BOARDS (Structural Steel Works may also apply to this process)
3. ROUGH GRADING
• Cut and fill machine grade the site area. J. PAINTING WORKS
1. Application of epoxy primer for steel painting
B. EXCAVATION WORK 2. Applying of 2 coats of enamel or oil-based paints to add treatment
1. Excavate to grade indicated
2. Dewatering – Pump water out of excavated K. ROOF INSTALLATION
3. Sub-drainage 1. Installation of tempered sheet (thk of 6mm)
4. Soil compaction 2. 1-inch self-tapping screw spaced for installing tempered solid sheet
5. Disposal of Excavated Materials 3. Silicon sealant as sticking agent for connecting the tempered solid sheet.
6. Laying out of foundations 4. Aluminum U-clip ¼” x 12’ at the edge of the installed polycarbonate.
7. Foundation of Concrete Pedestals
8. Proper used of equipment such as shovel and digging bar will be observed.
9. Pouring of 2-inch gravel (G1) beddings

C. STEEL WORKS (REBARS)


1. Fabrication of concrete pedestal Footing rebars and concrete pedestal rebars.
2. rebars and tie wires in the fabrication shall be 12mm Ø and 10mm Ø bars and #16 GI tie wire
3. Footing rebar composing of 12mm Ø bars and pedestal rebar composing of 10mm Ø both bar and lateral ties.
4. Proper Installation of fabricated rebars.
5. Concrete spaces for foundations with height of 75m

D. FORMWORKS
1. Proper installation of formworks for the concreting of concrete pedestals.
2. The use of phenolic board ½” and coco lumber is required.
3. Concrete spacers for the concrete pedestal with height of 50mm is also required.

E. CONCRETING
1. Class A mix of concrete and the proper concreting of the footing and the pedestal.
2. Mix must have strength of 3,000 to 5,000 psi.
3. Pouring and Spreading of the concrete evenly throughout the form.
4. Before the concrete pedestal, 4-12mm Ø anchor bold with 300mm length should be placed and attached to
the installed main rebar of the pedestal.
5. Curing of concrete
7. Back-filling of excavated soil

F. STRUCTURAL STEEL WORKS


1. Installation of G.I pipe columns to be installed at the concrete pedestal.