Bharat Heavy Electricals Limited

3x800 MW,Patratu Site

Load details:- Crane Details:- Crane Details:-


Load weight Capacity of Capacity of Crane/EWM
Crane/EWM
Sling load Weight Working Radius Working Radius
Weight of Hook Operator Name Operator Name
Weight of Lifting Total load’s Total load’s percentage
Beam percentage of the of the rated capacity of
rated capacity of crane/EWM=
crane/EWM= Total load /crane
Weight of CPB Total load /crane capacity at working
capacity at working radius
radius
Others
Total Load
Details & Capacity of other T&P Used: -

S.No Description Identification No TPI SWL Visual Purpose


Validity Inspection Lifting Balancing

Rigging: -

Hitch Type (s) Size


No. Of Slings Tension on each leg of sling
Sling Assembly Capacity Total Tension on all leg of slings(T=L/H x
W/N)
Shackle Size(S): % sling capacity= Total slings tension/ sling
assembly capacity
Shackle rated Capacity (S)
T- total tension, L-sling length, H- vertical height of sling with load, W- weight of material, N-Nos of slings leg

Signature: -

Crane Operator Contractor Engineer


Rigger Contractor HSE
Signal Person BHEL Engineer
Lift Supervisor BHEL HSE
Cholams
Bharat Heavy Electricals Limited
3x800 MW,Patratu Site

LIFTING PLAN SKETCH

800 MT
80 MT

Material Weight _______Mt 80

Prepared Approved By

Workers Details
Sr.No Name Designation Date
1
2
3
4
Bharat Heavy Electricals Limited
3x800 MW,Patratu Site

Shifting Plan

Material Weight _______Mt

Workers Details
Sr.No Name Designation Date
Bharat Heavy Electricals Limited
3x800 MW,Patratu Site

LIFTING PLAN SKETCH

Workers Details
Sr.No Name Designation Date
Bharat Heavy Electricals Limited
3x800 MW,Patratu Site

LIFTING PLAN SKETCH

Workers Details
Sr.No Name Designation Date
Bharat Heavy Electricals Limited
3x800 MW,Patratu Site

LIFTING PLAN SKETCH

80

Material Weight _______Mt

Workers Details
Sr.No Name Designation Date
Bharat Heavy Electricals Limited
3x800 MW,Patratu Site

LIFTING PLAN SKETCH

Workers Details
Sr.No Name Designation Date
Bharat Heavy Electricals Limited
3x800 MW,Patratu Site

LIFTING PLAN SKETCH

80

Workers Details
Sr.No Name Designation Date
Bharat Heavy Electricals Limited
3x800 MW,Patratu Site

LIFTING PLAN SKETCH

Crane

Workers Details
Sr.No Name Designation Date
Bharat Heavy Electricals Limited
3x800 MW,Patratu Site

LIFTING PLAN SKETCH

Crane

Crane 80

Workers Details
Sr.No Name Designation Date
Bharat Heavy Electricals Limited
3x800 MW,Patratu Site

Ref. No: - Date:


LIFTING PLAN
Work Description: -
Normal lifting operations with single crane/EWM
Tandem lifting operation with two cranes/EWMs
Tandem lifting/ Tailing of lifting materials with two cranes/EWMs or crane and EWMs
Load details:- Crane Details:- Crane Details:-
Load weight Capacity of Capacity of Crane/EWM
Crane/EWM
Sling load Weight Working Radius Working Radius
Weight of Hook Operator Name Operator Name
Weight of Lifting Total load’s Total load’s percentage
Beam percentage of the of the rated capacity of
rated capacity of crane/EWM=
crane/EWM= Total load /crane
Weight of CPB Total load /crane capacity at working
capacity at working radius
radius
Others
Total Load
Details & Capacity of other T&P Used: -

S.No Description Identification No TPI SWL Visual Purpose


Validity Inspection Lifting Balancing

Rigging: -

Hitch Type (s) Size


No. Of Slings Tension on each leg of sling
Sling Assembly Capacity Total Tension on all leg of slings(T=L/H x
W/N)
Shackle Size(S): % sling capacity= Total slings tension/ sling
assembly capacity
Shackle rated Capacity (S)
T- total tension, L-sling length, H- vertical height of sling with load, W- weight of material, N-Nos of slings leg

Signature: -

Crane Operator Contractor Engineer


Rigger Contractor HSE
Signal Person BHEL Engineer
Lift Supervisor BHEL HSE