Professional Documents
Culture Documents
1.120x30 Steel(Staff House)
1.120x30 Steel(Staff House)
Summary
Contingency 5,654,220.67
1
(120'x30') ONE-STOREYED SS STAFF HOUSE
Summary
Total 193,413,502.20
2
(120'x30') ONE-STOREYED SS STAFF HOUSE
Abstract of Cost
3
(120'x30') ONE-STOREYED SS STAFF HOUSE
Abstract of Cost
22 1:2:4 Cement Concrete Work For Frame, Window Sill and Lintel
Cft 144.72 5,247 Cft 759,320.00
23 Timber shuttering form work for Frame, Window Sill and Lintel
Sft 746.14 2,998 Sft 2,236,714.80
24 Installation of reinforcing mild steel for Frame, Window Sill and Lintel
Ton 0.60 2,426,850 Ton 1,456,110.00
4
(120'x30') ONE-STOREYED SS STAFF HOUSE
Abstract of Cost
5
(120'x30') ONE-STOREYED SS STAFF HOUSE
Abstract of Cost
Apron
45 Sand Filling Work Cft 158.00 747 Cft 117,960.00
6
(120'x30') ONE-STOREYED SS STAFF HOUSE
Abstract of Cost
7
(120'x30') ONE-STOREYED SS STAFF HOUSE
Bill of Quantity
Materials
1 Cement Bag 1297.72 13,000 Bag 16,870,360.00
2 Sand Sud 64.47 50,000 Sud 3,223,500.00
3 Brick No 60927.00 150 No 9,139,050.00
4 Chipping Sud 47.03 100,000 Sud 4,703,000.00
5 Hardcore Sud 8.87 58,400 Sud 518,008.00
6 Earth Sud 0.00 8,000 Sud -
7 Fuel Gal 92.81 12,000 Gal 1,113,720.00
8 5-Plywood(8'x4') Sht 55.81 43,000 Sht 2,399,830.00
9 Jungle wood scantling Ton 6.49 950,000 Ton 6,165,500.00
10 Hardwood Ton 1.11 1,950,000 Ton 2,164,500.00
11 Nail Viss 49.73 9,840 Viss 489,343.20
12 6.5mm Ø M.S bars Ton 0.07 1,700,000 Ton 119,000.00
13 8mm Ø M.S bars Ton 1.05 1,700,000 Ton 1,785,000.00
14 10mm Ø M.S bars Ton 0.81 1,700,000 Ton 1,377,000.00
15 12mm Ø M.S bars Ton 0.56 1,700,000 Ton 952,000.00
16 16mm Ø M.S bars Ton 6.36 1,700,000 Ton 10,812,000.00
17 Binding wire Viss 46.85 7,000 Viss 327,950.00
18 X-met Rft 6434.00 255 Rft 1,640,670.00
19 150x75x9x7-36.7kg/m Rft 550.33 6,000 Rft 3,301,980.00
20 150x75x9x7-29.6kg/m Rft 930.00 6,000 Rft 5,580,000.00
21 300mmx300mmx20mm tk base No 52.00 15,000 No 780,000.00
22 20mm Anchor Bolt& Nut No 312.00 6,500 No 2,028,000.00
23 16mm Boit&nut No 2360.00 300 No 708,000.00
24 4"x2" U Beam Rft 928.25 4,000 Rft 3,713,000.00
25 5"x2" U Beam Rft 330.00 4,000 Rft 1,320,000.00
26 4"x2"x1.6mm Lipped channel Rft 2028.50 2,000 Rft 4,057,000.00
27 Ms Plate No 42.00 2,000 No 84,000.00
28 Purlin Cleat No 177.00 300 No 53,100.00
29 3/8"Ø Bolt & Nut No 890.00 200 No 178,000.00
30 Teak Pannel Door(M+L) Sft 707.83 9,200 Sft 6,512,036.00
31 Aluminium Powder Coated Wi Sft 686.44 8,000 Sft 5,491,520.00
32 9"x3/4"x3/16" bracket No 444.00 500 No 222,000.00
33 4-Angle Sheet Rft 2086.56 4,500 Rft 9,389,520.00
8
(120'x30') ONE-STOREYED SS STAFF HOUSE
Bill of Quantity
Labours
1 Carpenter No 429.98 15,000 No 6,449,700.00
2 Machine driver No 23.20 15,000 No 348,000.00
3 Mason No 453.53 15,000 No 6,802,950.00
4 Smith No 983.94 15,000 No 14,759,100.00
5 Painter No 231.87 15,000 No 3,478,050.00
6 Surveyor No 0.47 15,000 No 7,050.00
9
(120'x30') ONE-STOREYED SS STAFF HOUSE
Bill of Quantity
10
(120'x30') ONE-STOREYED SS STAFF HOUSE
Builder's Estimate
11
(120'x30') ONE-STOREYED SS STAFF HOUSE
Builder's Estimate
12
(120'x30') ONE-STOREYED SS STAFF HOUSE
Builder's Estimate
13
(120'x30') ONE-STOREYED SS STAFF HOUSE
Builder's Estimate
14
(120'x30') ONE-STOREYED SS STAFF HOUSE
Builder's Estimate
15
(120'x30') ONE-STOREYED SS STAFF HOUSE
Builder's Estimate
22 1:2:4 Cement Concrete Work For Frame, Window Sill and Lintel
Material Cft 144.72
Cement Bag 26.75 13,000 Bag 347,750.00
Chipping Sud 1.33 100,000 Sud 133,000.00
Sand Sud 0.67 50,000 Sud 33,500.00
Fuel Gal 2.89 12,000 Gal 34,680.00
Labour
Mason No 2.89 15,000 No 43,350.00
Worker No 13.02 12,000 No 156,240.00
Machine driver No 0.72 15,000 No 10,800.00
23 Timber shuttering form work for Frame, Window Sill and Lintel
Sft 746.14
Material
Jungle wood scantling Ton 0.99 950,000 Ton 940,500.00
5-Plywood(8'x4') Sht 8.94 43,000 Sht 384,420.00
Nail Viss 6.22 9,840 Viss 61,204.80
Labour
Carpenter No 44.77 15,000 No 671,550.00
Worker No 14.92 12,000 No 179,040.00
24 Installation of reinforcing mild steel for Frame, Window Sill and Lintel
6.5mm Ton 0.07
12mm Ton 0.53
Material 0.60
6.5mm Ø M.S bars Ton 0.07 1,700,000 Ton 119,000.00
12mm Ø M.S bars Ton 0.56 1,700,000 Ton 952,000.00
Binding wire Viss 3.33 7,000 Viss 23,310.00
Labour
Smith No 13.40 15,000 No 201,000.00
Worker No 13.40 12,000 No 160,800.00
16
(120'x30') ONE-STOREYED SS STAFF HOUSE
Builder's Estimate
17
(120'x30') ONE-STOREYED SS STAFF HOUSE
Builder's Estimate
18
(120'x30') ONE-STOREYED SS STAFF HOUSE
Builder's Estimate
Sft 11,691.40
Material
Wall Putty Gal 58.46 16,000 Gal 935,360.00
Sandpaper Doz 38.97 12,000 Doz 467,640.00
Putty Trowel No 19.49 1,000 No 19,490.00
Labour
Painter No. 77.94 15,000 No. 1,169,100.00
Worker No. 77.94 12,000 No. 935,280.00
37 Sunshade Work
Material Sft 81.00
Sunshade Work (M+L) Sft 81.00 12,000 Sft 972,000.00
38 Tiling Work
Floor Tile Sft 192.00
Wall Tile Sft 864.00
Material Sft 966.00
19
(120'x30') ONE-STOREYED SS STAFF HOUSE
Builder's Estimate
20
(120'x30') ONE-STOREYED SS STAFF HOUSE
Builder's Estimate
ii Formwork
Material Sft 36.00
Jungle wood scantling Ton 0.05 950,000 Ton 47,500.00
5-Plywood(8'x4') Sht 0.43 43,000 Sht 18,490.00
Nail Viss 0.30 9,840 Viss 2,952.00
Labour
Carpenter No 2.16 15,000 No 32,400.00
Worker No 0.72 12,000 No 8,640.00
iii MS Work
10mm Ton 0.03
Material 0.03
10mm Ø M.S bars Ton 0.03 1,700,000 Ton 51,000.00
Binding wire Viss 0.18 7,000 Viss 1,260.00
Labour
Smith No 0.67 15,000 No 10,050.00
Worker No 0.67 12,000 No 8,040.00
Apron
45 Sand Filling Work
21
(120'x30') ONE-STOREYED SS STAFF HOUSE
Builder's Estimate
22
(120'x30') ONE-STOREYED SS STAFF HOUSE
Detail of Measurements
23
(120'x30') ONE-STOREYED SS STAFF HOUSE
Detail of Measurements
24
(120'x30') ONE-STOREYED SS STAFF HOUSE
Detail of Measurements
25
(120'x30') ONE-STOREYED SS STAFF HOUSE
Detail of Measurements
Vertical Line 8' 1x 13 7.08'- 0" 1'- 1.5" 0'- 6" 51.80 Cft
Vertical Line 8' 1x 6 6.50'- 0" 1'- 1.5" 0'- 6" 21.94 Cft
9" Brick retaining wall (Up to N.G.L)
Horizontal Line 120' 1x 1 110.00'- 0" 0'- 9" 1'- 0" 82.50 Cft
Horizontal Line 120' 1x 3 108.00'- 0" 0'- 9" 1'- 0" 243.00 Cft
Horizontal Line 10' 1x 6 8.50'- 0" 0'- 9" 1'- 0" 38.25 Cft
Vertical Line 22' 1x 13 20.00'- 0" 0'- 9" 1'- 0" 195.00 Cft
Vertical Line 8' 1x 13 7.08'- 0" 0'- 9" 1'- 0" 69.06 Cft
Vertical Line 8' 1x 6 6.50'- 0" 0'- 9" 1'- 0" 29.25 Cft
1149.87 Cft
9" Brick retaining wall (N.G.L to Plinth level)
Horizontal Line 120' 1x 1 110.00'- 0" 0'- 9" 0'- 9" 61.88 Cft
Horizontal Line 60' 1x 3 108.00'- 0" 0'- 9" 1'- 0" 243.00 Cft
Horizontal Line 10' 1x 6 8.50'- 0" 0'- 9" 1'- 0" 38.25 Cft
Vertical Line 22' 1x 13 20.00'- 0" 0'- 9" 1'- 0" 195.00 Cft
Vertical Line 8' 1x 13 7.08'- 0" 0'- 9" 0'- 9" 51.80 Cft
Vertical Line 8' 1x 6 6.50'- 0" 0'- 9" 0'- 9" 21.94 Cft
For Brick Step 12x 8 4'- 0" 0'- 12" 0'- 5" 168.00 Cft
779.87 Cft
1929.74 1929.74 Cft
26
(120'x30') ONE-STOREYED SS STAFF HOUSE
Detail of Measurements
for10'x3' Room 1x 6 9'- 3" 2'- 3" 0'- 4.5" 46.83 Cft
for4'x8' Room 1x 6 3'- 3" 7'- 3" 0'- 4.5" 53.02 Cft
for6'x8' Room 1x 6 5'- 3" 7'- 3" 0'- 4.5" 85.64 Cft
1127.25 Cft
22 1:2:4 Cement Concrete Work For Frame, Window Sill and Lintel
10' Span W1 6x 2 9'- 0" 0'- 4.5" 0'- 6" 20.25 Cft
11' Span W1 4x 2 10'- 0" 0'- 4.5" 0'- 6" 15.00 Cft
11' Span tiffener 22x 2 10'- 0" 0'- 5.0" 0'- 3" 45.83 Cft
10' Span W2,MD 6x 1 14'- 0" 0'- 4.5" 0'- 6" 15.75 Cft
10' Span D2 6x 1 9'- 0" 0'- 4.5" 0'- 6" 10.13 Cft
8' Span 13x 1 7'- 2" 0'- 5.0" 0'- 3" 9.70 Cft
10' Span W3,D2 6x 1 14'- 0" 0'- 4.5" 0'- 6" 15.75 Cft
Sunshade W1 10x 1 8'- 0" 0'- 5.0" 0'- 4" 11.11 Cft
Sunshade W3 2x 1 4'- 4" 0'- 5.0" 0'- 4" 1.20 Cft
144.72 Cft
23 Timber shuttering form work for Frame, Window Sill and Lintel
10' Span W1 6x 2 9'- 0" 0'- 12" 108.00 Sft
11' Span W1 4x 2 10'- 0" 0'- 12" 80.00 Sft
11' Span tiffener 22x 2 10'- 0" 0'- 6" 220.00 Sft
10' Span W2,MD 6x 1 14'- 0" 0'- 12" 84.00 Sft
10' Span D2 6x 1 9'- 0" 0'- 12" 54.00 Sft
27
(120'x30') ONE-STOREYED SS STAFF HOUSE
Detail of Measurements
28
(120'x30') ONE-STOREYED SS STAFF HOUSE
Detail of Measurements
29
(120'x30') ONE-STOREYED SS STAFF HOUSE
Detail of Measurements
30
(120'x30') ONE-STOREYED SS STAFF HOUSE
Detail of Measurements
38 Tiling Work
Floor Tile 1x 6 4'- 0" 8'- 0" 192.00
Wall Tile 1x 6 24'- 0" 6'- 0" 864.00 966.00 Sft
Deduction 1x 6 2'- 6" 6'- 0" 90.00
39 Bamboo Scaffolding Work 1x 1 300'- 0" 14'- 0" 4,200.00 4200.00 Sft
31
(120'x30') ONE-STOREYED SS STAFF HOUSE
Detail of Measurements
i 1:2:4 Cement Concrete Work 1x 12 2'- 0" 1'- 9" 0'- 3" 10.50 10.50 Cft
ii Formwork
1x 12 2'- 0" 1'- 0" 24.00
2x 12 2'- 0" 0'- 3" 12.00 36.00 Sft
iii MS Work
10mm Deform Bar 4x 12 2'- 0" 96.00
4x 12 1'- 9" 84.00 180.00 Rft
0.03 Ton
Apron
45 Sand Filling Work 1x 1 316'- 0" 2'- 0" 0'- 3" 158.00 158.00 Cft
32