ESTIMATION FOR

Septic Tank & Soak pit Tank

( 7' x 3' x 5' )


SUMMARY OF COST

Name of work … Septic Tank & Soak pit Tank ( 7' x 3' x 5' )

Material cost = 630,627.70

Labour cost = 336,600.00

Total cost = 967,227.70

3 of 14
BILL OF QUANTITY

Name of work … Septic Tank & Soak pit Tank ( 7' x 3' x 5' )

Sr nos Particular Quantity Unit Rate(kyat) Per Amount(kyat) Remark

MATERIAL

1 cement 15.55 bag 13000 bag 202,150.00


2 brick 1421.47 nos 150 nos 213,220.50
3 sand 1.17 sud 50000 sud 58,500.00
4 chipping 0.41 sud 100000 sud 41,000.00
5 gravel 0.22 sud 50000 sud 11,000.00
6 timber scantling 0.040 ton 950000 ton 38,000.00 three times
7 5 layered plywood 0.330 nos 43000 nos 14,190.00 three times
8 nail 0.83 viss 9840 viss 8,167.20
9 18''x18'' manhole cover slab 3 nos 8000 nos 24,000.00
10 vent pipe 2 nos 2000 nos 4,000.00
11 reinforcing steel
10 mm dia m.s 0.020 ton 750000 ton 15,000.00
sub total = 0.020 ton
12 binding wire 0.40 viss 3500 viss 1,400.00
630,627.70
LABOUR
1 e-worker 2.14 nos 12000 nos 25,680.00
2 mason 6.34 nos 15000 nos 95,100.00
3 m-worker 14.46 nos 12000 nos 173,520.00
4 carpenter 1.66 nos 15000 nos 24,900.00
5 c-worker 0.55 nos 12000 nos 6,600.00
6 steel fixer 0.40 nos 15000 nos 6,000.00
7 steel fixer - worker 0.40 nos 12000 nos 4,800.00
336,600.00

Total cost = 967,227.70

4 of 14
ABSTRACT OF COST

Name of work … Septic Tank & Soak pit Tank ( 7' x 3' x 5' )

Sr no Particular Quantity Unit Rate Per Amount

Septic Tank & Manhole


1 Earthwork excavation for septic tank
209.0 cft 120 cft 25,080.00
2 6''thk;1:3:6 lean concrete under septic tank
25.0 cft 3979 cft 99,480.00
3 9''thk;Brickwork for wall at septic tank
97.5 cft 4379 cft 426,907.50
4 4.5''thk;Brickwork for wall at septic tank
9 sft 1887 sft 16,985.00
5 Gravel filling within septic tank
21.74 cft 627 cft 13,640.00
7 Plastering work for wall of septic tank
139.38 sft 589 sft 82,140.00
8 Sand filling around septic tank
49 cft 742 cft 36,380.00
9 Earthwork excavation for manhole
5.25 cft 114 cft 600.00
10 6''thk;1:3:6 lean concrete under manhole
5.25 cft 4025 cft 21,130.00
11 4.5''thk;Brickwork for wall at manhole
10.13 sft 1872 sft 18,968.00
12 Plastering work for wall of manhole
11.64 sft 613 sft 7,140.00
14 Formwork for septic tank & manhole cover slab
27.73 sft 3313 sft 91,857.20
15 Steelwork for septic tank & manhole cover slab
49.9 lbs 545 lbs 27,200.00
16 1:2:4 r.c.c for septic tank & manhole cover slab
12.58 cft 5701 cft 71,720.00
19 Fixing of (18''x18'')manhole cover slab
3 nos 8000 nos 24,000.00
20 Fixing of vent pipe
2 nos 2000 nos 4,000.00

Total Cost = 967,227.70

5 of 14
BUILDERʼS ESTIMATE

Name of work … Septic Tank & Soak pit Tank ( 7' x 3' x 5' )

Sr
Particular Quantity Unit Rate Per Amount Remark
no

Septic Tank & Manhole


1 Earthwork excavation for septic tank
209.0 cft
labour P-1/Sr.3
e-worker 2.09 nos 12000 nos 25,080.00
25,080.00
2 6''thk;1:3:6 lean concrete under septic tank
25.00 cft
material
cement 3.21 bags 13000 bags 41,730.00
sand 0.12 sud 50000 sud 6,000.00
chipping 0.24 sud 100000 sud 24,000.00
labour
mason 0.25 nos 15000 nos 3,750.00
m-worker 2.00 nos 12000 nos 24,000.00
99,480.00
3 9''thk;Brickwork for wall at septic tank
97.5 cft
material
brick 1316.25 nos 150 nos 197,437.50
cement 6.79 bags 13000 bags 88,270.00
sand 0.25 sud 50000 sud 12,500.00
labour
mason 3.90 nos 15000 nos 58,500.00
m-worker 5.85 nos 12000 nos 70,200.00
426,907.50
4 4.5''thk;Brickwork for wall at septic tank
9.00 sft
material P-82/Sr.8
brick 49.50 nos 150 nos 7,425.00

6 of 14
BUILDERʼS ESTIMATE

Name of work … Septic Tank & Soak pit Tank ( 7' x 3' x 5' )

Sr
Particular Quantity Unit Rate Per Amount Remark
no

cement 0.24 bags 13000 bags 3,120.00


sand 0.01 sud 50000 sud 500.00
labour P-82/Sr.8
mason 0.18 nos 15000 nos 2,700.00
m-worker 0.27 nos 12000 nos 3,240.00
16,985.00
5 Gravel filling within septic tank
21.74 cft
material
gravel 0.22 sud 50000 sud 11,000.00
labour
m-worker 0.22 nos 12000 nos 2,640.00
13,640.00

6 Plastering work for wall of septic tank


139.38 sft
material
cement 1.87 bags 13000 bags 24,310.00
sand 0.07 sud 50000 sud 3,500.00
labour
mason 1.39 nos 15000 nos 20,850.00
m-worker 2.79 nos 12000 nos 33,480.00
82,140.00
7 Sand filling around septic tank
49 cft
material
sand 0.61 sud 50000 sud 30,500.00
labour
m-worker 0.49 nos 12000 nos 5,880.00
36,380.00

7 of 14
BUILDERʼS ESTIMATE

Name of work … Septic Tank & Soak pit Tank ( 7' x 3' x 5' )

Sr
Particular Quantity Unit Rate Per Amount Remark
no

8 Earthwork excavation for manhole


5.25 cft
labour
e-worker 0.05 nos 12000 nos 600.00
600.00
9 6''thk;1:3:6 lean concrete under manhole
5.25 cft
material
cement 0.68 bags 13000 bags 8,840.00
sand 0.03 sud 50000 sud 1,500.00
chipping 0.05 sud 100000 sud 5,000.00
labour
mason 0.05 nos 15000 nos 750.00
m-worker 0.42 nos 12000 nos 5,040.00
21,130.00

10 4.5''thk;Brickwork for wall at manhole


10.13 sft
material
brick 55.72 nos 150 nos 8,358.00
cement 0.27 bags 13000 bags 3,510.00
sand 0.01 sud 50000 sud 500.00
labour
mason 0.20 nos 15000 nos 3,000.00
m-worker 0.30 nos 12000 nos 3,600.00
18,968.00
11 Plastering work for wall of manhole
11.64 sft

8 of 14
BUILDERʼS ESTIMATE

Name of work … Septic Tank & Soak pit Tank ( 7' x 3' x 5' )

Sr
Particular Quantity Unit Rate Per Amount Remark
no

material
cement 0.16 bags 13000 bags 2,080.00
sand 0.01 sud 50000 sud 500.00
labour
mason 0.12 nos 15000 nos 1,800.00
m-worker 0.23 nos 12000 nos 2,760.00
7,140.00

12 Formwork for septic tank & manhole cover slab


27.73 sft
material
5 layered plywood 0.33 nos 43000 nos 14,190.00 three times
timber scantling 0.04 ton 950000 ton 38,000.00 three times
nail 0.83 viss 9840 viss 8,167.20
labour
carpenter 1.66 nos 15000 nos 24,900.00
c-worker 0.55 nos 12000 nos 6,600.00
91,857.20

13 Steelwork for septic tank & manhole cover slab


49.9 lbs
material P-133/Sr.9
10 mm dia m.s 0.02 ton 750000 ton 15,000.00
binding wire 0.40 viss 3500 viss 1,400.00
labour
steel fixer 0.40 nos 15000 nos 6,000.00
steel fixer - worker 0.40 nos 12000 nos 4,800.00
27,200.00
14 1:2:4 r.c.c for septic tank & manhole cover slab

9 of 14
BUILDERʼS ESTIMATE

Name of work … Septic Tank & Soak pit Tank ( 7' x 3' x 5' )

Sr
Particular Quantity Unit Rate Per Amount Remark
no

12.58 cft
material
cement 2.33 bags 13000 bags 30,290.00
sand 0.06 sud 50000 sud 3,000.00
chipping 0.12 sud 100000 sud 12,000.00
labour
mason 0.25 nos 15000 nos 3,750.00
m-worker 1.89 nos 12000 nos 22,680.00
71,720.00
15 Fixing of (18''x18'')manhole cover slab
3 nos
material
18''x18'' manhole cover slab 3 nos 8000 nos 24,000.00
24,000.00
16 Fixing of vent pipe
2 nos
material
vent pipe 2 nos 2000 nos 4,000.00
4,000.00

Total Cost = 967,227.70 0


0

10 of 14
DETAILED MEASUREMENT

Name of work … Septic Tank & Soak pit Tank ( 7' x 3' x 5' )

Measurement
Sr Total of
Particular No L B H Content Unit Remark
no each
Ft In Ft In Ft In
Septic Tank & Manhole
1 Earthwork excavation for septic tank

1 9.5 0 5.5 0 4 0 209.00

209.00 209.00 cft P-1/Sr.3

.
2 6''thk;1:3:6 lean concrete under septic tank

1 9.5 0 5.5 0 0 6 26.13


Deduction for
hollow -1 1.5 0 1.5 0 0 6 -1.13

25.00 25.00 cft

3 9''thk;Brickwork for wall at septic tank

horizontal 2 8.5 0 0 9 5 0 63.75


vertical 3 3.0 0 0 9 5 0 33.75

97.50 97.50 cft

4 4.5''thk;Brickwork for wall at septic tank

vertical 1 3.0 0 1 0 3 0 9.0

9.0 9.0 sft

5 Gravel filling within septic tank

(1'-6"x1'-6") 1 1.5 0 1.5 0 0 6 1.13


(2'-3.5"x3'-0") 1 2.29 0 3.0 0 3 0 20.61

21.74 21.74 cft

6 Plastering work for wall of septic tank

Inner
horizontal 2 6.25 0 1 0 5 0 62.50
-2 0 4.5 1 0 3 0 -2.25
vertical 4 3 0 1 0 5 0 60.00
2 3 0 1 0 3 0 18.00

11 of 14
DETAILED MEASUREMENT

Name of work … Septic Tank & Soak pit Tank ( 7' x 3' x 5' )

Measurement
Sr Total of
Particular No L B H Content Unit Remark
no each
Ft In Ft In Ft In
1 3 0 0 4.5 1 0 1.13

139.38 139.38 sft

7 Sand filling around septic tank

1 9.5 0 5.5 0 3.5 0 182.88


Deduction for
-1 8.5 0 4.5 0 3.5 0 -133.88

49.00 49.00 cft

8 Earthwork excavation for manhole

1 3.5 0 3 0 0 6 5.25

5.25 5.25 cft

9 6''thk;1:3:6 lean concrete under manhole

1 3.5 0 3 0 0 6 5.25

5.25 5.25 cft

10 4.5''thk;Brickwork for wall at manhole

horizontal 2 2.5 0 1 0 1 6 7.50


vertical 1 1.75 0 1 0 1 6 2.63

10.13 10.13 sft

11 Plastering work for wall of manhole

inner
horizontal 2 2.13 0 1 0 1 6 6.39
vertical 2 1.75 0 1 0 1 6 5.25

11.64 11.64 sft

12 Formwork for septic tank & manhole cover slab

(8'-6"x4'-6") 1 6.250 0 3 0 1 0 18.75

12 of 14
DETAILED MEASUREMENT

Name of work … Septic Tank & Soak pit Tank ( 7' x 3' x 5' )

Measurement
Sr Total of
Particular No L B H Content Unit Remark
no each
Ft In Ft In Ft In
2 8.5 0 1 0 0 4 5.67
2 4.5 0 1 0 0 4 3.00
(2'-6"x2'-6") 1 1.75 0 2.125 0 1 0 3.72
2 2.5 0 1 0 0 4 1.67
2 2.5 0 1 0 0 4 1.67
Deduction for
(18''x18'') manhole cover -3 0 18 0 18 1 0 -6.75

27.73 27.73 sft

13 Steelwork for septic tank & manhole cover slab

number nos lb/ft dia; ( mm)

(8'-6"x4'-6")
X-direction 1 1 7 1 7 8.84 0 61.88 0.414 10
Y-direction 1 1 13 1 13 4.84 0 62.92 0.414 10
(2'-6"x2'-6")
X-direction 1 1 4 1 4 2.84 0 11.36 0.414 10
Y-direction 1 1 4 1 4 2.84 0 11.36 0.414 10
Deduction for
(18''x18'') manhole cover
X-direction -3 1 3 1 -9 1.5 0 -13.50 0.414 10
Y-direction -3 1 3 1 -9 1.5 0 -13.50 0.414 10

sub total
10 121 0.414 10 49.9
49.9

material P-133/Sr.9
10 mm dia m.s 0.023 ton
binding wire 0.124 viss

14 1:2:4 r.c.c for septic tank & manhole cover slab

(8'-6"x4'-6") 1 8.5 0 4.5 0 0 4 12.75


(2'-6"x2'-6") 1 2.5 0 2.5 0 0 4 2.08
Deduction for
(18''x18'') manhole cover -3 0 18 0 18 0 4 -2.25

12.58 12.58 cft

13 of 14
DETAILED MEASUREMENT

Name of work … Septic Tank & Soak pit Tank ( 7' x 3' x 5' )

Measurement
Sr Total of
Particular No L B H Content Unit Remark
no each
Ft In Ft In Ft In

15 Fixing of (18''x18'')manhole cover slab

for manhole(18''x18'') 3 1 0 1 0 1 0 3

3 3 nos

16 Fixing of vent pipe

for vent pipe 2 1 0 1 0 1 0 2

2 2 nos

14 of 14