Confined Space_merged
Confined Space_merged
Confined Space_merged
Location: Govt. Gate, Main Gate, Computer Gate, Sulfur Gate, Main Plant Area(South, East ,West,North), Flare
Area (South, East ,West,North)and Sulfur Fence Area (South, East ,West,North, UPS Building)
Start Date: _June 1- June 30, 2024 Time: 5:00 A.M Duration: 4:00 P.M – 10:00 P.M.
Does the activity have the potential to develop sparks, flames or sufficient heat to cause ignition? √
Does the activity involve entry into process equipment or enclosures that has the potential to contain √
hazardous materials?
Does the activity require excavation around known or suspected underground lines, working at heights or √
crane lift?
Others [Please Specify]:
√
Have the necessary risk assessments, plans, and procedures been thoroughly reviewed and approved?
√
Are the necessary resources available for conducting the activities?
√
Will adequate supervision and oversight be provided during the execution?
√
Will required controls be implemented during the execution?
√
Is there a detailed Emergency Response Plan in place to address any potential incident during the execution?
I hereby authorize the execution of the above activities to be performed after normal working hours in accordance with Saudi
Aramco safety requirements and procedures.
Location: Govt. Gate, Main gate, Computer gate, Sulfur Gate, Main Plant Area(South, East ,West,North), Flare area
(South, East ,West,North)and Sulfur Fence Area (South, East ,West,North, UPS Building)
Start Date: _June 1- June 30, 2024______________ Time:_5:00 A.M Duration: 4:00 P.M – 10:00 P.M.
Excavation and Backfilling (Manual & Mechanical excavation for duct bank, MV & LV cable, Manhole)
Does the activity have the potential to develop sparks, flames or sufficient heat to cause ignition? √
Does the activity involve entry into process equipment or enclosures that has the potential to contain √
hazardous materials?
Does the activity require excavation around known or suspected underground lines, working at heights or √
crane lift?
Others [Please Specify]:
√
Have the necessary risk assessments, plans, and procedures been thoroughly reviewed and approved?
√
Are the necessary resources available for conducting the activities?
√
Will adequate supervision and oversight be provided during the execution?
√
Will required controls be implemented during the execution?
√
Is there a detailed Emergency Response Plan in place to address any potential incident during the execution?
I hereby authorize the execution of the above activities to be performed after normal working hours in accordance with Saudi
Aramco safety requirements and procedures.
Location: Govt. Gate, Main Gate, Computer Gate, Sulfur Gate, Main Plant Area(South, East ,West,North), Flare
Area (South, East ,West,North)and Sulfur Fence Area (South, East ,West,North, UPS Building)
Start Date: _June 1-June 30, 2024 Time:_5 A.M Duration: 4 P.M-10 P.M
Hot Work (Concrete Pouring with Pump, Heavy Equipment Operation, Entry & using of Light and Heavy
Vehicle, Cutting, grinding , brazing )
Does the activity involve entry into process equipment or enclosures that has the potential to contain
√
hazardous materials?
Does the activity require excavation around known or suspected underground lines, working at heights or
√
crane lift?
Others [Please Specify]:
√
Have the necessary risk assessments, plans, and procedures been thoroughly reviewed and approved? √
I hereby authorize the execution of the above activities to be performed after normal working hours in accordance with Saudi
Aramco safety requirements and procedures.
Location: Govt. Gate, Main Gate, Computer Gate, Sulfur Gate, Main Plant Area (South, East ,West,North), Flare
Area (South, East ,West,North)and Sulfur Fence Area (South, East ,West,North, UPS Building)
Start Date: _June 1- June 30, 2024 Time: 5:00 A.M Duration: 4:00 P.M – 10:00 P.M.
Lifting ( Loading , unloading , Shifting of Materials, Equipment , fence post, pipes , concertina , Electrical
Cable Drums, Camera poles, Lifting of Lighting Poles, Lifting of Precast Foundation, Transformers, Doors,
Panels, Space Frame, Shifting of Scaffolding Materials)
Does the activity have the potential to develop sparks, flames or sufficient heat to cause ignition? √
Does the activity involve entry into process equipment or enclosures that has the potential to contain √
hazardous materials?
Does the activity require excavation around known or suspected underground lines, working at heights or √
crane lift?
Others [Please Specify]:
√
Have the necessary risk assessments, plans, and procedures been thoroughly reviewed and approved?
√
Are the necessary resources available for conducting the activities?
√
Will adequate supervision and oversight be provided during the execution?
√
Will required controls be implemented during the execution?
√
Is there a detailed Emergency Response Plan in place to address any potential incident during the execution?
I hereby authorize the execution of the above activities to be performed after normal working hours in accordance with Saudi
Aramco safety requirements and procedures.
Location: Govt. Gate, Main Gate, Computer Gate, Sulfur Gate, Main Plant Area(South, East ,West,North), Flare
Area (South, East ,West,North)and Sulfur Fence Area (South, East ,West,North, UPS Building)
Start Date: _June 1- June 30, 2024 Time: 5:00 A.M Duration: 4:00 P.M – 10:00 P.M.
Scaffolding ( Erection, Altering , Dismantling), Using of Man lift for Space Frame Installation, Erection of
Precast Panel, Spreading gravel on the Roof, Installation of HVAC, Fire Fighting Systems, Lights , Gypsum
board, Acoustic Ceiling, Concreting & Grouting (above 1.8 m )
Does the activity have the potential to develop sparks, flames or sufficient heat to cause ignition? √
Does the activity involve entry into process equipment or enclosures that has the potential to contain √
hazardous materials?
Does the activity require excavation around known or suspected underground lines, working at heights or √
crane lift?
Others [Please Specify]:
√
Have the necessary risk assessments, plans, and procedures been thoroughly reviewed and approved?
√
Are the necessary resources available for conducting the activities?
√
Will adequate supervision and oversight be provided during the execution?
√
Will required controls be implemented during the execution?
√
Is there a detailed Emergency Response Plan in place to address any potential incident during the execution?
I hereby authorize the execution of the above activities to be performed after normal working hours in accordance with Saudi
Aramco safety requirements and procedures.
01-JUNE-2024 TO 30-JUNE-2024
4-Weeks Construction Look Ahead for Package-05 TANAJIB GAS PLANT
Stations Works
Work Station/s # Dicipline Activity Description Timing PERMIT TYPE
Heavy Equipment Operation, Entry & using of Light and Heavy Vehicle, Cutting, grinding , brazing
, Loading , unloading , Shifting of Materials, Equipment , Electrical Cable Drums, Camera poles,
1 MECHANICAL Lifting of Lighting Poles, Lifting of Precast Foundation, Transformers, Doors, Panels, Space Frame, 16:00 - 22:00 INTERNAL PERMIT
Shifting of Scaffolding Materials)Installation of HVAC, Fire Fighting Systems, Cutting, Grinding ,
Brazing.
GOVERNMENT
2 ELECTRICAL CABLE LAYING, FENCE AND WARNING TAPE INSTALLATION, GROUNDING WORK, CABLE 16:00 - 22:00 INTERNAL PERMIT
SECURITY GATE TERMINATION, MEGGER TESTING, CONDUITING , CONDUIT BENDING , CONDUIT INSTALLATION,
PANELS INSTALLATION , , PRECOMMISSIONING OF EQUIPMENT/ ENERGIZATION , FOC CABLE
PULLING, FOC SUBDUCT INSTALLATION, FOC SPLICING AND TERMINATION
Scaffolding ( Erection, Altering , Dismantling), Using of Man lift for Space Frame Installation,
Erection of Precast Panel, Spreading gravel on the Roof, Installation of HVAC, Fire Fighting
3
CIVIL Systems, Lights , Gypsum board, Acoustic Ceiling, Concreting & Grouting (above 1.8 m ) Manual & 16:00 - 22:00 INTERNAL PERMIT
Mechanical excavation for duct bank, MV & LV cable in Manhole, Concrete Pouring with Pump,
concrete Pouring .
Heavy Equipment Operation, Entry & using of Light and Heavy Vehicle, Cutting, grinding , brazing
, Loading , unloading , Shifting of Materials, Equipment , Electrical Cable Drums, Camera poles,
1 MECHANICAL Lifting of Lighting Poles, Lifting of Precast Foundation, Transformers, Doors, Panels, Space Frame, 16:00 - 22:00 INTERNAL PERMIT
Shifting of Scaffolding Materials)Installation of HVAC, Fire Fighting Systems, Cutting, Grinding ,
Brazing.
2 ELECTRICAL CABLE LAYING, FENCE AND WARNING TAPE INSTALLATION, GROUNDING WORK, CABLE 16:00 - 22:00 INTERNAL PERMIT
MAIN GATE TERMINATION, MEGGER TESTING, CONDUITING , CONDUIT BENDING , CONDUIT INSTALLATION,
PANELS INSTALLATION , , PRECOMMISSIONING OF EQUIPMENT/ ENERGIZATION , FOC CABLE
PULLING, FOC SUBDUCT INSTALLATION, FOC SPLICING AND TERMINATION
Scaffolding ( Erection, Altering , Dismantling), Using of Man lift for Space Frame Installation,
Erection of Precast Panel, Spreading gravel on the Roof, Installation of HVAC, Fire Fighting
3
CIVIL Systems, Lights , Gypsum board, Acoustic Ceiling, Concreting & Grouting (above 1.8 m ) Manual & 16:00 - 22:00 INTERNAL PERMIT
Mechanical excavation for duct bank, MV & LV cable, Manhole Concrete Pouring with Pump,
Concrete Pouring
Heavy Equipment Operation, Entry & using of Light and Heavy Vehicle, Cutting, grinding , brazing
, Loading , unloading , Shifting of Materials, Equipment , Electrical Cable Drums, Camera poles,
1 MECHANICAL Lifting of Lighting Poles, Lifting of Precast Foundation, Transformers, Doors, Panels, Space Frame, 16:00 - 22:00 INTERNAL PERMIT
Shifting of Scaffolding Materials)Installation of HVAC, Fire Fighting Systems, Cutting, Grinding ,
Brazing.
COMPUTER GATE 2 ELECTRICAL CABLE LAYING, FENCE AND WARNING TAPE INSTALLATION, GROUNDING WORK, CABLE 16:00 - 22:00 INTERNAL PERMIT
TERMINATION, MEGGER TESTING, CONDUITING , CONDUIT BENDING , CONDUIT INSTALLATION,
PANELS INSTALLATION , , PRECOMMISSIONING OF EQUIPMENT/ ENERGIZATION , FOC CABLE
PULLING, FOC SUBDUCT INSTALLATION, FOC SPLICING AND TERMINATION
Scaffolding ( Erection, Altering , Dismantling), Using of Man lift for Space Frame Installation,
Erection of Precast Panel, Spreading gravel on the Roof, Installation of HVAC, Fire Fighting
3 CIVIL Systems, Lights , Gypsum board, Acoustic Ceiling, Concreting & Grouting (above 1.8 m ) Manual & 16:00 - 22:00 INTERNAL PERMIT
Mechanical excavation for duct bank, MV & LV cable, Manhole Concrete Pouring with Pump,
Concrete Pouring.
Heavy Equipment Operation, Entry & using of Light and Heavy Vehicle, Cutting, grinding , brazing
, Loading , unloading , Shifting of Materials, Equipment , Electrical Cable Drums, Camera poles,
1 MECHANICAL Lifting of Lighting Poles, Lifting of Precast Foundation, Transformers, Doors, Panels, Space Frame, 16:00 - 22:00 INTERNAL PERMIT
Shifting of Scaffolding Materials)Installation of HVAC, Fire Fighting Systems, Cutting, Grinding ,
Brazing. Fence post , Concertina, V support , Vinyl Coted Wire Mesh,
Scaffolding ( Erection, Altering , Dismantling), , Concreting & Grouting (above 1.8 m ) Manual &
3 CIVIL Mechanical excavation for duct bank, MV & LV cable, Manhole Concrete Pouring with Pump, 16:00 - 22:00 INTERNAL PERMIT
Concrete Pouring.
Heavy Equipment Operation, Entry & using of Light and Heavy Vehicle, Cutting, grinding , brazing
, Loading , unloading , Shifting of Materials, Equipment , Electrical Cable Drums, Camera poles,
1 MECHANICAL Lifting of Lighting Poles, Lifting of Precast Foundation, Transformers, Doors, Panels, Space Frame, 16:00 - 22:00 INTERNAL PERMIT
Shifting of Scaffolding Materials), Cutting, Grinding , Brazing. Fence post , Concertina, V support ,
Vinyl Coted Wire Mesh,
Scaffolding ( Erection, Altering , Dismantling), , Concreting & Grouting (above 1.8 m ) Manual &
3 CIVIL Mechanical excavation for duct bank, MV & LV cable, Manhole Concrete Pouring with Pump, 16:00 - 22:00 INTERNAL PERMIT
Concrete Pouring.
Heavy Equipment Operation, Entry & using of Light and Heavy Vehicle, Cutting, grinding , brazing
, Loading , unloading , Shifting of Materials, Equipment , Electrical Cable Drums, Camera poles,
1 MECHANICAL Lifting of Lighting Poles, Lifting of Precast Foundation, Transformers, Doors, Panels, Space Frame, 16:00 - 22:00 INTERNAL PERMIT
Shifting of Scaffolding Materials), Cutting, Grinding , Brazing. Fence post , Concertina, V support ,
Vinyl Coted Wire Mesh,
CABLE LAYING, FENCE AND WARNING TAPE INSTALLATION, GROUNDING WORK, CABLE
SULFUR FENCE (WEST , TERMINATION, MEGGER TESTING, CONDUITING , CONDUIT BENDING , CONDUIT INSTALLATION,
2 ELECTRICAL 16:00 - 22:00 INTERNAL PERMIT
EAST, SOUTH, PANELS INSTALLATION , , PRECOMMISSIONING OF EQUIPMENT/ ENERGIZATION , FOC CABLE
NORTH,UPS BUILDING) PULLING, FOC SUBDUCT INSTALLATION, FOC SPLICING AND TERMINATION
Scaffolding ( Erection, Altering , Dismantling), , Concreting & Grouting (above 1.8 m ) Manual &
3 CIVIL Mechanical excavation for duct bank, MV & LV cable, Manhole Concrete Pouring with Pump, 16:00 - 22:00 INTERNAL PERMIT
Concrete Pouring.