E2841-M0602 / PK-750

PU 1595 CP Chem C3 Splitter CP Chem


Fabrication/Production Schedule
Customer: S&B Engineers and Constructors, Ltd.

Owner: Chevron Phillips Chemical Company LP

Description: Bridge Crane, 20 US Ton

Tag Number: PK-750

TYPE / SEQ: SCHD / 200

DRT Doc. No.: SBEC-ANG-SO035076-SCHD-00001

S&B Doc. No.:

A 19-Apr-2022 ISSUED FOR REVIEW TW TW TW


REV DATE DESCRIPTION/ISSUE PURPOSE ORIG CHK APPR

JOB: E2841 PKG: 1720 CNTRL NO: M0602-009 RCPT: 1 PG. 1 OF 2


Rev. A Fabrication/Production Schedule
19-Apr-2022 SBEC-ANG-SO035076-SCHD-00001

Vendor Deliverables Register


Project Name: PU 1595 CP Chem C3 Splitter Document No:
PO / PKG Tag No.: E2841-M0602 / PK-750 Revision No.: A
Owner: Chevron Phillips Chemical Company LP Issue Purpose: Issued for Review
Customer: S&B Engineers and Constructors LTD Revision Date: 0

March 2022 April 2022 May 2022 June 2022


Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16

Su M Tu W Th F Sa Su M Tu W Th F Sa Su M Tu W Th F Sa Su M Tu W Th F Sa Su M Tu W Th F Sa Su M Tu W Th F Sa Su M Tu W Th F Sa Su M Tu W Th F Sa Su M Tu W Th F Sa Su M Tu W Th F Sa Su M Tu W Th F Sa Su M Tu W Th F Sa Su M Tu W Th F Sa Su M Tu W Th F Sa Su M Tu W Th F Sa Su M Tu W Th F Sa SU

EQUIPMENT 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
Anticipated
PO Issuance
Week of
PK-750, Bridge Crane 20 US Ton

Submittal of General Arrangement

Receipt of Approval Drawing

Long lead item procurement

Receipt of long lead items 9/19/2022


End Trucks

Hoists

Fabrication/Final Weld-out

Construction - Catwalk & Girders 9/26/2022


NDE 10/10/2022
Painting 10/17/2022
Assembly & Wiring 10/31/2022
Final Inspection-LA Crane 11/14/2022
Packaging 11/21/2022
Shipment 11/28/2022

**PRELIMINARY SCHEDULE, WITH BEST INFORMATION TO DATE

Page 1 of 1

JOB: E2841 PKG: 1720 CNTRL NO: M0602-009 RCPT: 1 PG. 2 OF 2