Tool Manufactuing Time Plan for V15 Rivetting Tool 15.04.2021

You might also like

Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 1

TOOL MANUFACTURING TIME PLAN

SUPPLIER: Hari Bhargo CUSTOMER: MEKHOS TECHNOLOGY TOOL NUMBER: TBD

PART NAME: V15700 or V15800 RAW MATERIAL : NO OF IMPRESSIONS :1

PART NUMBER: V15700 or V15800 T0 TRIAL DATE:

DESCRIPTION P/A
SL NO WEEK 1 WEEK 2 WEEK 3 WEEK 4 WEEK 5 WEEK 6
DATES 22-Mar 23-Mar 24-Mar 25-Mar 26-Mar 27-Mar 28-Mar 29-Mar 30-Mar 31-Mar 1-Apr 2-Apr 3-Apr 4-Apr 5-Apr 6-Apr 7-Apr 8-Apr 9-Apr 10-Apr 11-Apr 12-Apr 13-Apr 14-Apr 15-Apr 16-Apr 17-Apr 18-Apr 19-Apr 20-Apr 21-Apr 22-Apr 23-Apr 24-Apr 25-Apr 26-Apr 27-Apr 28-Apr 29-Apr 30-Apr 1-May 2-May
Planned
UNDERSTAND CUSTOMER
1 Revise
REQUIREMENTS
Actual
Planned
2 CONCEPT SUBMISSION AND REVIEW Revise
Actual
Planned
2 DESIGN APPROVAL Revise
Actual
Planned
3 PREPERATION OF BOM Revise
Actual
Planned
4 RAW MATERIAL PROCURING Revise
Actual
Planned
PRE MACHING MILLING / GRINDING /
5 Revise
TURNING
Actual
Planned
6 JIG BORING/ DRO DRILLING Revise Revise Revise Revise Revise Revise
Actual
Planned
7 CNC MILLING Revise Revise Revise Revise Revise Revise
Actual
Planned
8 HEAT TREATMENT Revise
Actual
Planned
9 GRINDING / CYCINDERICAL GRINDING Revise Revise Revise
Actual
Planned
8 CNC MILLING(FINISH M/C) Revise
Actual
Planned
9 WIRE CUT / EDM Revise Revise Revise Revise Revise
Actual
Planned
10 ASSEMBLY Revise Revise Revise Revise
Actual
Planned
11 T0 TRIAL Revise
Actual
Planned
12 PART INSPECTION Revise
Actual
Planned
13 FINE TUNE Revise
Actual
Planned
14 T1 TRIAL Revise
Actual
Planned
15 PART INSPECTION Revise
Actual
Planned
16 PART DESPATCH Revise
Actual
Planned
17 DISPATCH Revise
Actual
Prepared By : Manoj Approved By : Nanda
Date : 23-Jan-2021 Date : 25-Jan-2021

P= PLAN
LEGENDS R= REVISED

A= ACTUAL