A PRELIMINARIES
Allow for bringing plant equipment to site and all works
necessary for erecting , dismantling, removal and making
1 good all the relevant works on site 750,000.00
Preliminaries 1,600,000.00
Carried to summary
6
Formation and preparation of sub-grade in earth cut
compacted to 100% West African Standard Compaction soil
cement stabilized material as granular Sub Base, Aggregate
Sub Base and Asphaltic Base Course) as approved 165 m3 12,000 1,980,000.00
8
Provide and lay first coat surface dressing using cut back
butimen 100/150 second STV at 40 deg. @ 1.12 litres per
sq.m and 12mm single sized crushed chippings 35 m3 700 24,500.00
C CONCRETE WORKS
Reinforcement Work
Fabric Reinforcement
23 125mm x 125mm x 10mm angle iron 18.2 kg/m 787 m 11,500 9,050,500.00
27 16mm diameter high yield steel sag rod. 159 m 1,140 181,260.00
33 250mm long 125 x 75 x 8mm thick angle cleat. 306 No 4,650 1,422,900.00
34 12mm diameter x 40mm long stud bolt with nut and 2,448 No 1,500 3,672,000.00
washers
35 Prepare and shop apply one coat of red oxide and two
coats of site applied oil paint on:
Erection
Under floors
Block Work
Metal Works
Finishings
Floor Finishings
52 Tiling to floors laid on cement and sand (1:3) base 30 m2 4,650 139,500.00
53 20mm paving to floor laid on cement and sand 102 m2 9,500 969,000.00
(1:3) base
Wall Finishings
G ROOF COVERING
Covering
58 1.5mm gauge long span oven baked and coloured 415 m2 11,500 4,772,500.00
fibre roofing sheets fixed with complete accessories
and having 200mm minimum end and side laps.
SUMMARY
A Preliminaries 1,600,000.00