Date Time Activity WIR Remarks

Inspection of Rebar Installation for


Trimmer Bar of Paddle Pipe prior to
restoration of CW3 at Outlet Flowmeter
RL. +4.735 as per highlighted in the WIR-S-
16-Apr-24 3pm drawing. 9956

Inspection of Formworks Installation &


CPR of CW3 at Outlet Flowmeter RL.
+4.735 as per highlighted in the WIR-S-
8pm drawing. 9957

Survey Lay-out Inspection Prior for


Rebar Foundation at PERIMETER
FENCE , STA.493m-516m , AGL351-
RL.4.460m-4.860m as per highlighted EPC-WIR-
09:00AM in the drawing. S-9960

Rebar Inspection for Foundations at


PERIMETER FENCE , STA.493m- AGL351-
10:00AM 516m , RL.4.460m-4.860m as per EPC-WIR-
Onwards highlighted in the drawing. S-9961

FW and CPR Inspection for Foundation


at PERIMETER FENCE , STA.493m- AGL351-
02:00PM 516m , RL.4.460m-4.860m as per EPC-WIR-
Onwards highlighted in the drawing. S-9962
WIR-AR-
10:00AM Torque Test at Generato Room 1360
Inspection of Survey Lay-out for
CB1,CB2,CBR1,CBR2 & CBJ1 along
GL: 1-3/A-F, RL: 10.310 at Workshop
and Spareparts Storeroom as per
highlighted in the drawing.
3pm 9897
Inspection of Steel Reinforcement for
B1,CB2,CBR1,CBR2 & CBJ1 along WIR-S-
GL: 1-3/A-F, RL: 10.310 at Workshop 9898
and Spareparts Storeroom as per
highlighted in the drawing.
8pm
Inspection of Formworks and Concrete
Pouring Request for
B1,CB2,CBR1,CBR2 & CBJ1 along WIR-S-
GL: 1-3/A-F, RL: 10.310 at Workshop 9899
and Spareparts Storeroom as per
highlighted in the drawing.
11pm
WIR-S-
Inspection of Survey Lay-out for FC1 9946
along GL: 3/A, RL: 3.010 at Hazardous
Waste Storage as per highlighted in the
1pm drawing.

Inspection of Steel Reinforcement for


FC1 along GL: 3/C, RL: 3.010 at
Hazardous Waste Storage as per WIR-S-
6pm highlighted in the drawing. 9947

Inspection of Formworks and Concrete


Pouring Request for FC1 along GL:
3/C, RL: 3.010 at Hazardous Waste
Storage as per highlighted in the WIR-S-
10PM drawing. 9948
Date Time Activity WIR Remarks

Inspection of Rebar Installation for


Trimmer Bar of Paddle Pipe prior to
restoration of CW3 at Outlet Flowmeter
RL. +4.735 as per highlighted in the WIR-S-
16-Apr-24 3pm drawing. 9956

Inspection of Formworks Installation &


CPR of CW3 at Outlet Flowmeter RL.
+4.735 as per highlighted in the WIR-S-
8pm drawing. 9957

Survey Lay-out Inspection Prior for


Rebar Foundation at PERIMETER
FENCE , STA.493m-516m , AGL351-
RL.4.460m-4.860m as per highlighted EPC-WIR-
09:00AM in the drawing. S-9960

Rebar Inspection for Foundations at


PERIMETER FENCE , STA.493m- AGL351-
10:00AM 516m , RL.4.460m-4.860m as per EPC-WIR-
Onwards highlighted in the drawing. S-9961

FW and CPR Inspection for Foundation


at PERIMETER FENCE , STA.493m- AGL351-
02:00PM 516m , RL.4.460m-4.860m as per EPC-WIR-
Onwards highlighted in the drawing. S-9962
WIR-AR-
10:00AM Torque Test at Generato Room 1360
Inspection of Survey Lay-out for
CB1,CB2,CBR1,CBR2 & CBJ1 along
GL: 1-3/A-F, RL: 10.310 at Workshop
and Spareparts Storeroom as per
highlighted in the drawing.
3pm 9897
Inspection of Steel Reinforcement for
B1,CB2,CBR1,CBR2 & CBJ1 along WIR-S-
GL: 1-3/A-F, RL: 10.310 at Workshop 9898
and Spareparts Storeroom as per
highlighted in the drawing.
8pm
Inspection of Formworks and Concrete
Pouring Request for
B1,CB2,CBR1,CBR2 & CBJ1 along WIR-S-
GL: 1-3/A-F, RL: 10.310 at Workshop 9899
and Spareparts Storeroom as per
highlighted in the drawing.
11pm
WIR-S-
Inspection of Survey Lay-out for FC1 9946
along GL: 3/A, RL: 3.010 at Hazardous
Waste Storage as per highlighted in the
1pm drawing.

Inspection of Steel Reinforcement for


FC1 along GL: 3/C, RL: 3.010 at
Hazardous Waste Storage as per WIR-S-
6pm highlighted in the drawing. 9947

Inspection of Formworks and Concrete


Pouring Request for FC1 along GL:
3/C, RL: 3.010 at Hazardous Waste
Storage as per highlighted in the WIR-S-
10PM drawing. 9948