Professional Documents
Culture Documents
Installation of Welded Steel
Installation of Welded Steel
PETRONAS Technical Standards (PTS) publications reflect the views, at the time of publication,
of PETRONAS OPUs/Divisions.
They are based on the experience acquired during the involvement with the design, construction,
operation and maintenance of processing units and facilities. Where appropriate they are based
on, or reference is made to, national and international standards and codes of practice.
The objective is to set the recommended standard for good technical practice to be applied by
PETRONAS' OPUs in oil and gas production facilities, refineries, gas processing plants, chemical
plants, marketing facilities or any other such facility, and thereby to achieve maximum technical
and economic benefit from standardisation.
The information set forth in these publications is provided to users for their consideration and
decision to implement. This is of particular importance where PTS may not cover every
requirement or diversity of condition at each locality. The system of PTS is expected to be
sufficiently flexible to allow individual operating units to adapt the information set forth in PTS to
their own environment and requirements.
When Contractors or Manufacturers/Suppliers use PTS they shall be solely responsible for the
quality of work and the attainment of the required design and engineering standards. In
particular, for those requirements not specifically covered, the Principal will expect them to follow
those design and engineering practices which will achieve the same level of integrity as reflected
in the PTS. If in doubt, the Contractor or Manufacturer/Supplier shall, without detracting from his
own responsibility, consult the Principal or its technical advisor.
Subject to any particular terms and conditions as may be set forth in specific agreements with
users, PETRONAS disclaims any liability of whatsoever nature for any damage (including injury
or death) suffered by any company or person whomsoever as a result of or in connection with the
use, application or implementation of any PTS, combination of PTS or any part thereof. The
benefit of this disclaimer shall inure in all respects to PETRONAS and/or any company affiliated
to PETRONAS that may issue PTS or require the use of PTS.
Without prejudice to any specific terms in respect of confidentiality under relevant contractual
arrangements, PTS shall not, without the prior written consent of PETRONAS, be disclosed by
users to any company or person whomsoever and the PTS shall be used exclusively for the
purpose they have been provided to the user. They shall be returned after use, including any
copies which shall only be made by users with the express prior written consent of PETRONAS.
The copyright of PTS vests in PETRONAS. Users shall arrange for PTS to be held in safe
custody and PETRONAS may at any time require information satisfactory to PETRONAS in order
to ascertain how users implement this requirement.
INSTALLATION OF WELDED STEEL STRUCTURES
1. GENERAL
1.1 Scope
This specification covers the load-out, sea-fastening, transportation, field erection and installation
of welded steel structures at marine locations, and any design work related to the same.
The structures to be installed have been engineered to the extent shown on the Contract
Drawings, and any additional design and engineering related to the installation of these
structures shall be performed by the CONTRACTOR, to the approval of the COMPANY.
2.1.1 The CONTRACTOR shall prepare a fully detailed procedure for each platform installation,
indicating the method and sequences he proposes to follow for jacket lifting or launching,
upending pile and conductor installation, jacket levelling, deck setting, jetting or drilling, grouting,
underwater cutting, and the like. Three (3) copies of the Installation Procedures and one (1) copy
of all supporting calculations and analyses shall be submitted to the COMPANY for approval no
later than five (5) weeks prior to installation of the fabricated structural components and loose
items.
The COMPANY shall return to the CONTRACTOR an approved or marked-up copy of the
installation procedure, whereupon the CONTRACTOR shall revise the procedure as applicable,
and re-issue to the COMPANY three (3) copies of the final approved procedure.
2.1.2 The structural integrity of the platform during its erection is based on a number of design
assumptions. The erection conditions assumed by the COMPANY, considering available
construction equipment, sea conditions, loadings on the structure and other items are stated on
the Contract Drawings. The CONTRACTOR shall ensure that his installation procedures will not
violate design assumptions in accordance with API RP 2A (latest edition) or special assumptions
which were specified in the Contract Documents.
More detailed installation procedures may be provided to the CONTRACTOR at the discretion of
the COMPANY.
2.1.3 The CONTRACTOR, at his discretion, may choose any erection procedure. However, any
change from procedures proposed by the COMPANY on the Contract Drawings or as stated
herein shall be submitted to the COMPANY for review and approval.
Such changes shall be submitted as part of the above-mentioned installation procedures with
supporting detailed calculations to verify that sufficient engineering has been carried out to
ensure a successful platform installation.
3. LOAD-OUT AND SEAFASTENING
3.1 Load-out
The FABRICATOR shall be responsible for preparing fully detailed engineering drawings
showing the manner in which he wishes the fabricated structural components and loose items to
be loaded in accordance with PTS 20.108.
The CONTRACTOR shall submit to the COMPANY SEVEN (7) weeks prior to the load-out date,
preliminary layout drawings showing clearly barge dimensions, barge fixed equipment above
deck, barge skid beams, required positions of jacket(s), decks(s), piles, conductors, fender(s),
and the like. This information is required for the FABRICATOR to prepare the load-out
procedure.
The CONTRACTOR shall transport, for CONTRACTOR's account, all lifting slings and shackles,
and rigging platforms, to the Fabrication Yard, where they will be installed prior to load-out (in
accordance with the drawings submitted by the CONTRACTOR) by the Fabricator for
CONTRACTOR's account.
In the event that the CONTRACTOR is unable to comply with the foregoing, he may install such
items in the field but all costs associated with this work will be for the CONTRACTOR's account;
however, the COMPANY reserves the right to delay such work when, in the COMPANY's
opinion, personnel or equipment/structures will be endangered by such an operation, and all
costs associated with such a delay will be for CONTRACTOR's account.
3.2 Seafastening
The CONTRACTOR shall be responsible for preparing fully detailed engineering designs and
drawings showing the manner in which he wishes the fabricated structural components and loose
items to be seafastened in accordance with PTS 20.108 and 20.109.
The CONTRACTOR shall submit to the COMPANY FIVE(5) weeks prior to the load-out date for
approval, the detailed seafastening design calculations and drawings certified by a Company
approved independent Marine Surveyor.
The CONTRACTOR shall supply all seafastening materials to the fabrication yard, and the
FABRICATOR shall supply all labour equipment and consumables required for the seafastening.
The CONTRACTOR shall be responsible for arranging a Company approved independent
Marine Surveyor to inspect and to certify that the seafastenings are sea-worthy for the specific
tows/transportations, and issuing a letter of acceptance that the seafastenings have been carried
out to his satisfaction.
4. TRANSPORTATION
Unless specified otherwise in the Contract Documents, the CONTRACTOR shall provide the
transportation barges and the tugs to transport the fabricated structural components and loose
items to the Installation Site in accordance with PTS 20.108 and 20.109, and return all unused
material, special equipment and scrap to the Fabrication Yards, at the discretion of the
COMPANY.
The CONTRACTOR shall inform himself of the Load-out facilities at the fabricator yards and
supply-transportation barges compatible to the load-out facilities and arrangements.
5. REMOVAL FROM TRANSPORT BARGE
5.1 Lifting
5.1.1 The design of the jackets (to be lifted and/or upended) and the decks, as shown on the Contract
Drawings, has been based on the sling, shackle and pad-eye design criteria as outlined below.
The CONTRACTOR shall therefore supply all necessary slings and shackles to the correct
rating to ensure safe execution of the work in accordance with these criteria.
5.1.1.2 Shackles
The shackles to be used for the lift shall have a manufacturer's safe working load, SWL,
equal to the static sling load, 1, provided the minimum ultimate strength, MUS, of the
shackle is at least 4 times the SWL.
5.1.1.3 Slings
The slings to be selected for the lift shall have a manufacturer's minimum breaking load,
MBL, of at least 4 times the static sling load, 1.
5.1.1.4 Padeyes
Padeyes are designed for the static sling load, 1, and a load factor of 2.0.
5.1.1.5 The angle which the slings makes with the horizontal plane shall be a minimum of 60
degrees.
5.2.1 The CONTRACTOR shall submit a complete launch analysis for the launch barge selected for
the launching of the jacket. The following criteria apply:
5.2.1.2 The launch barge shall not be considered anchored or restrained by a tug.
Coefficient Value
6.3.1 A jacket not linked to an adjacent jacket, shall be placed and positioned in accordance with PTS
20.122 and with tolerances stated in Section 6.7.
To position a jacket adjacent to an existing platform, distance wires shall be used (in cross
configuration) for preliminary positioning with the following back-up
(a) an approved short-range EDM to determine longitudinal distance between
structures,
(b) an approved 1" theodolite to determine lateral alignment and offset.
Approval of final position of jacket shall depend on readings (a) and (b) above.
6.3.2 Jacket levelling shall preferably be achieved by ballasting/deballasting selected jacket legs, or by
hanging off pile initials (and add-on's as applicable). Pulling up the jacket once piles have been
driven is generally not permitted. However if such action is necessary to bring the jacket into
level the following procedure shall be adopted:-
Levelling of the jacket shall be carried out before piles have been driven deeper than a
penetration 7.5 m beyond pile self-penetration, i.e. the penetration achieved due to pile self-
weight plus weight of the first pile driving hammer to be used, and not after piles have been
driven deeper unless specified otherwise in the Outline Installation Procedures. Once the
jacket is lifted, it should be 'dogged-off' as necessary to the piles by attachment plates. Any
levelling procedure by this method shall be approved by the COMPANY.
6.3.3 Final jacket level, position and heading shall be in accordance with Section 6.7 of this
Specification.
6.4.1 General
6.4.1.1 The CONTRACTOR shall be fully responsible for installing all piles to the required
design (target) penetrations in accordance with the Scope of-Work, and shall furnish
all necessary equipment (pile driving hammers, jetting strings, drilling rig, grouting
machinery, and the like) to achieve this. The CONTRACTOR shall maintain on board
the pile driving hammers required for the various aspects of the work.
6.4.1.2 The COMPANY's pile design has been based on the use of the Vulcan Pile Driving
Hammers. Should the CONTRACTOR wish to utilise alternative types of hammers,
these shall be of a similar energy rating to those specified 6.4.1.3 below and the
CONTRACTOR shall demonstrate to the COMPANY that these can be safely used
on the COMPANY's pile make-up. To this extent, the Contractor shall perform
buckling analyses to ensure that add-ons lengths/pile driving hammer combinations
are compatible, and drive-ability (wave equation) analyses to check on pile stresses
during driving as necessary.
6.4.1.3 As a minimum requirement, the following hammers complete with necessary spare parts
shall be available to ensure that all piles (and conductors) can be driven to design
(target) penetration:-
6.4.1.4 A maximum of 2 pile initials (and add-ons as applicable) may be hung off from a 4 pile
jacket during pile installation. For 8 pile jackets a maximum of 4 pile initials (and add-ons
as applicable) may be hung off. No piles may be hanging off from the jacket during pile
driving, i.e. any piles installed must be fully self-supporting.
6.4.1.5 For jackets with skirt piles which have to be grouted, the following procedure must be
followed :-
After placing the jacket, and before stabbing any skirt piles or commencing driving any
pre-installed skirt piles, the packer inflating lines shall be opened to atmosphere (at the
top brace elevation) for a few minutes, and then sealed again, by replacing the
hexagonal headed plugs, prior to stabbing or lowering the skirt piles.
This will allow the hydrostatic pressure to force all the air from the packer, thus keeping
any portion of the packer from extending beyond the guide fins of the skirt pile sleeve.
6.4.2 Driving
6.4.2.1 Initial driving after pile self-penetration shall always commence with a low energy
hammer to avoid pile tip damage in case the pile encounters a very hard layer at shallow
penetrations. Should blow counts suddenly increase to 200 blows per 0.3m (ft) at
shallow penetrations, driving must immediately be discontinued unless this high
blowcount is due to set-up in clay (e.g. while making an add-on connection); the pile
shall be jetted or drilled out to investigate the nature of the high blowcount.
The COMPANY shall advise the CONTRACTOR whether driving is to continue, drilling
ahead of the pile tip is to be employed, or pile is to be abandoned. In the latter case
remedial action, such as the installation of an insert pile, shall also be advised by the
COMPANY.)
6.4.2.2 The CONTRACTOR shall exercise controlled driving to minimize set-up and to ensure
that piles can be driven to the required design (target) penetrations by straight driving
alone, without recourse to jetting or drilling. Once a pile has been driven 7.5m. beyond
self penetration, work on this pile shall be continued until the pile has met its acceptance
criteria and the work shall not be interrupted or delayed by welding/driving any of the
other piles.
6.4.2.3 The pile/pile driving hammer combination to be employed is a function of the soil
conditions being encountered, pile diameter and 'pile stick-up' above the top can. The
COMPANY's acceptable combinations of hammer and pile stick-up length are shown
graphically in Figure 2 through 13 attached to this Specification. Absolute batter referred
to in these figures is the compound batter if the pile has a double batter.
6.4.2.4 All pad-eyes shall be cut off close to the pile face. Final finish and removal shall be
carried out by power grinding to the original pile surface. Special care shall be taken to
ensure that the pile is not cut into when removing the lifting lugs.
On skirt piles to be grouted, the section of pile face which will pass through the packer
shall be 'washed' clean of all weld metal and checked to ensure that no burrs remain
which might damage the packer at the foot of the skirt pile sleeves.
6.4.2.5 Skirt piles shall be installed by using fully welded followers unless indicated otherwise on
the Contract Drawings. Followers shall be recovered and re-worked for re-use as
applicable. Explosives shall not be used for underwater cutting of skirt piles.
6.4.2.6 All field welds in piles shall be made and inspected in accordance with Section 8 of this
Specification. Cut-offs shall be held to a minimum.
6.4.2.7 Every effort must be made to ensure that once final penetration is reached, no pile girth
weld is located in the shim area. This shall be taken into consideration before design
(target) penetration is reached or when it is necessary to drive the pile to maximum
penetration. If the girth weld is above the jacket top can and when it is considered that
further driving will be very difficult, then grinding the girth weld flush with the outside of
the pile will be acceptable.
6.4.2.8 The definition of pile driving refusal given in API RP 2A, applies.
6.4.3 Jetting
6.4.3.1 If a driven pile meets refusal, it may be possible to drive the pile deeper after the internal
soil plug has been removed. No jetting shall be permitted closer than 1.5m from the pile
tip, and every effort shall be made to recommence pile driving as soon as possible after
jetting operations are complete.
6.4.3.2 Any jet string provided by the CONTRACTOR shall be linked to adequate capacity water
jet pumps and air compressors, and be fully capable of jetting out soils plugs at any of
the Installation Sites.
6.4.3.3 Grout plugs may have to be set inside piles which have been jetted, as advised by the
COMPANY. Preparatory cleaning of the inside of the pile and grout setting shall be in
accordance with Subsection 6.4.7.
6.4.4 Drilling
6.4.4.1 If a driving pile meets refusal, it may be possible to drive the pile deeper after drilling out
the internal soil plug; or after drilling out the internal soil plug and drilling an undersized
pilot hole ahead of the pile. Alternatively, a hole may be drilled ahead of the driven main
pile and a grouted insert pile installed.
6.4.4.2 Any drilling procedure proposed by the CONTRACTOR shall be fully documented, and
submitted to the COMPANY for approval. All drilling equipment provided by the
CONTRACTOR shall be fully capable of drilling out soil plugs and drilling straight,
stabilised holes, either as and undersized pilot hole or as an oversized hole to
accommodate the installation of a grouted insert pile. The equipment shall be fully
capable of drilling in the soils at any of the Installation Sites.
6.4.4.3 If the soil plug inside the pile is removed by drilling the procedure followed shall be
similar to that for jetting, including restoring of end bearing, as advised by the
COMPANY.
6.4.4.4 If it is decided to advance the pile by drilling an undersize pilot hole ahead of the main
pile tip, the procedures outlined below shall be followed.
6.4.4.5 The pilot hole shall be as small as practical and still allow the pile to be advanced. The
hole size shall be determined by trial in the field and the capability shall be provided to
drill holes of several hole sizes, such as 356(14), 432(17), 508(20), 610(24), 762(30)
and 914(36) mm (inch.) in diameter, depending on the pile diameter being installed. The
hole size for the initial trial shall be approximately one-half the pile diameter. If, after
drilling the pilot hole, the blow-count exceeds 80 blows per .3m (ft), the hole size shall
be increased for further drilling. If the blow-count is less than that, the hole size shall be
decreased.
6.4.4.6 The diameter of the pilot hole shall not exceed the following :-
610 mm. (24 inch) diameter pile - 508 mm. (20 inch)
762 mm. (30 inch) diameter pile - 610 mm. (24 inch)
1067 mm.(42 inch) diameter pile - 914 mm. (36 inch)
1372 mm.(54 inch) diameter pile - 1219 mm.(48 inch)
6.4.4.7 The maximum length of pilot hole that may be drilled ahead of the pile tip shall be limited
by the details of the drill string. The computed deflection at the drill bit (measured from
an extension of the pile centre line), due to the weight component of the drill string
perpendicular to the axis of the battered pile, shall not exceed 0.25 x (pile O.D. - hole
diameter). The computed deflection shall include the deflection due to clearances
between the centralizers and the inner pile surface plus the deflection due to elastic
deformations in the drill string. Spring type centralisers will be avoided, if possible,
unless their deflected configuration under load can be accurately determined. Support
from centralizers that are below the pile tip shall be neglected unless the computed
pressure between the surface of the centralizer and the soil is less than 1/10 of the
ultimate bearing capacity of the soil. The use of additional centralizers to increase the
contact area may be required to limit the soil contact stress.
6.4.4.8 The pilot hole shall not be drilled ahead of the pile tip by a distance greater than the
length of the next section of pile to be driven, or as advised by the COMPANY. Every
effort shall be made to minimize the time between the drilling of the pilot hole and the
driving of the pile through the drilled interval.
6.4.4.9 If the pile meets refusal in a relatively thin sand layer or cemented layer and it is
believed that driving can be resumed after the layer has been penetrated, the pilot hole
should be terminated at the base of the layer.
6.4.4.10 After a pile has been driven to grade, the procedure given in Subsection 6.4.7 for
restoring end bearing shall be followed, as advised by the COMPANY.
6.4.5 Grouting
6.4.5.1 General
6.4.5.1.1 The CONTRACTOR shall provide all equipment, grout, additives, fresh water, and
experienced personnel for the grouting operations and shall arrange for transport of all
samples and testing.
6.4.5.1.2 The grouting crew, diving team, and all field personnel involved with the grouting
operations shall be thoroughly briefed regarding the procedure to be followed and the
extreme importance of obtaining a good grout job. Where the grouting of skirt piles,
insert piles and installation of grout plugs inside piles is concerned the structural integrity
of the platform is dependent upon the placement and retention of sound uncontaminated
cement grout.
6.4.5.1.3 All grout shall be made with neat Portland Cement Type I (API Class A, B, G or H). A
minimum of five(5) weeks before any grouting operations commence, the
CONTRACTOR shall furnish the COMPANY written details relating to the cement,
including details on its source.
6.4.5.1.4 The neat Portland Cement Type I shall be mixed to a density of 1885 kg/m3 (15.7 lb. /US
gal.), with an allowable variation of ± 36 kg/m3 (0.3 lb./US gal., using clean freshwater;
calcium chloride shall be added as an accelerator in an amount equal to two per cent by
weight of the mix water. The calcium chloride may be added to the mix water or blended
with the cement.
6.4.5.1.5 The use of filtered seawater may be considered subject to tests confirming that the
requirements regarding strength and setting times, as defined in this Specification, can
be met.
6.4.5.1.6 Also, a minimum of five (5) weeks in advance the CONTRACTOR shall present to the
COMPANY a written procedure on the proposed grouting and sampling procedures to
be adopted. The CONTRACTOR shall also arrange for a test mix, preferably with the
equipment which will actually be used for the grouting operations, and six samples,
using a standard 150 mm diameter compression test cylinder (or cube, subject to
approval by the COMPANY), shall be taken from various parts of the mix. This test shall
be witnessed by the COMPANY, and the samples shall be cured under conditions
similar to the actual conditions which will exist at site.
After 24 hours, four of the samples shall be tested by an independent test laboratory,
witnessed by the COMPANY. The compressive strength after 24 hours shall be a
minimum of 10.4 MPa (1500 psi).
The remaining two samples shall be tested in a similar manner after seven days.
6.4.6.1 Drilling requirements shall be similar to those for undersized pilot hole drilling, except
that the diameter of the hole drilled ahead of the driven main pile shall be 150 mm (6
inches) larger in diameter than the size of the insert pile to be installed, unless advised
otherwise by the COMPANY.
6.4.6.2 The insert pile shall be fully centralized inside the main pile and the drilled hole.
6.4.6.3 The CONTRACTOR shall develop adequate grouting techniques (subject to the
approval of the COMPANY) to ensure a good grout bond between the insert pile and the
soil formation, and between the insert pile and the driven main pile.
6.4.6.4 Cleaning of the drilled hole and the inside surface of the driven main pile shall be in
accordance with requirements outlined under Subsection 6.4.7, as will be the installation
of a grout plug inside the insert pile if required, as advised by the COMPANY.
6.4.6.5 Grout mix and sampling requirements shall also be in accordance with the requirements
outlined under Subsection 6.4.7.
6.4.7.1 In the event that a pile has been installed with recourse to jetting out or drilling out the
pile internal soil plug, or with recourse to drilling ahead of the pile tip, then installation of
a grout plug inside the pile to restore the internal skin friction lost may be required, as
advised by the COMPANY.
6.4.7.2 After a pile has been driven to final penetration, the pile must be cleaned out to the
maximum depth to which jetting or drilling out of the soil plug occurred, to the maximum
depth of the pilot hole, or to the top of the driving shoe, as directed by the COMPANY.
The method proposed by the CONTRACTOR (subject to approval by the COMPANY)
must be capable of thoroughly cleaning the soil from the inner surface of the pile in order
to permit adequate bonding of the grout plug to the steel. The inner surface of the pile
shall therefore be substantially free of soil over the length required for the grout plug.
6.5.1.6 All field welds in conductors shall be made and inspected in accordance with Section 8
of this Specification. Cut-offs shall be held to a minimum.
6.5.1.7 Conductors shall be cut off at the correct level, extended up to deck level and cover
plates installed, as indicated on the Contract Drawings or in the Outline Installation
Procedures.
6.5.2 Driving
6.5.2.1 A hammer having a rated striking energy not exceeding 122 KJ (90,000 ft lbs), shall be
used for driving the conductors.
6.5.2.2 The CONTRACTOR shall exercise controlled driving to minimize set-up and to ensure
that conductors can be driven to the required design (target) penetrations by straight
driving alone, without recourse to jetting or drilling. Once a conductor has been driven
7.5m beyond self penetration, work on this conductor shall be continued until the
conductor has met its acceptance criteria and the work shall not be interrupted or
delayed by driving/welding any of the other conductors.
In the event that this driving resistance is low at target penetration, driving must be
continued until all available conductor length is utilized.
6.5.2.3 In general the blowcount should always be limited to a maximum of 200 blows per 3 m
(ft) for the type of hammer recommended above. In the event that such blowcounts are
encountered before the target penetration is reached, driving must be discontinued when
such hard driving resistance is obviously caused by a hard layer at the tip of the
conductor and not due to set up in clay (e.g. while making an add-on connection).
Remedial measures in such an instance shall be advised by the COMPANY.
6.6.1 Before setting the stub piles, and hence the deck(s), the piles must be cut off at the correct level
(2.13 m or 7 ft. above the centre line of the jacket top elevation), and in such a manner that the
deck(s) will be level. This should be accomplished as follow:-
Set up an engineer's level on the top of the jacket, as central as possible, and such that all piles
can be seen. The elevation of the instrument should be slightly below the pile cut-off elevation.
Take level readings adjacent to all legs for 3, 4 or 6 pile jackets, and adjacent to the centre four
legs for 8 pile jackets.
The cut-off level for all piles shall then be established, and marked correctly on the piles, relative
to the average elevation given by readings.
Piles shall be cut off horizontally or at an angle, in accordance with the Contract Drawings.
6.6.2 Stub piles shall be installed vertically and the horizontal distance from the outside face of any
stub pile to the outside face to the adjacent stub pile, in any direction, shall be within a tolerance
of ± 6 mm of the dimensions shown on the Contract Drawings.
6.6.3 Final pile cut-off shall be in accordance with the Contract Drawings and Section 6.7 (Tolerances)
of this Specification.
6.6.4 All stub piles are provided with overlength in order that deck elevations can be corrected and that
the deck(s) is (are) installed at the correct elevation relative to actual mean sea level, as stated in
the Contract Drawings.
6.6.5 All stub piles shall be installed onto the piles and welded out and inspected in accordance with
Section 8 and 9 of this Specification.
6.6.6. The stub piles shall then be cut off horizontally as shown on the Contract Drawings in order that
the deck(s) may be installed level, and at the correct elevation.
6.7 Tolerances
6.7.1 Jackets
6.7.1.1 The CONTRACTOR shall be solely responsible for the correct installation of the jacket
at the location marked by the COMPANY. The COMPANY shall mark only the location
of free standing jackets.
6.7.1.2 The CONTRACTOR shall accurately position jackets in accordance with the following
maximum tolerances, or to the satisfaction of the COMPANY:
(a) For a jacket not to be linked to another platform, and for a jacket which forms
the first part of a development which will have further jackets added at a future
date:
- jacket orientation ± 4 degrees of that specified on the Contract Drawings
- centre of jacket to be within a radius of 15 m from the location specified on
the Contract Drawings.
(b) For a jacket to be linked to an existing (installed) jacket or completed platform;
- jacket orientation ± 2 degrees of that specified on the Contract Drawings
- lateral offset not to exceed ±.5 m.
- longitudinal distance between jacket and existing jacket or platform not to
exceed ±.5 m of that shown on the Contract Drawings.
A graphical explanation of the tolerances under (b) is given in Figure 1, attached to this
Specification.
6.7.1.3 All jackets shall be levelled to within an elevation differential as shown below, this being
the maximum difference in height permitted between the highest and the lowest points
found at the top of jacket elevation.
3 pile jackets : 50 mm ) subjected to a maximum
4 pile jackets : 75 mm ) slope of 1 in 200 in
6 pile jackets : 150 mm ) any direction on the
8 pile jackets : 200 mm ) top of the jacket
) elevation.
The level taking procedures shall be as follows
A set of level readings shall be made at readily identifiable points near each jacket leg
(i.e. 4 readings for a 4-pile jacket, 8 for an 8-pile) using an engineer's automatic level (of
an approved type) and staff, with the instrument sat up on a firm support, in the centre of
the jacket whenever possible. Each set of level readings should be taken at the same
point, and all level readings shall be permanently recorded by the CONTRACTOR. After
initial jacket levelling, a set of levels shall be taken whenever a shift in jacket position is
suspected, or at the request of the COMPANY.
When taking levels, corrections shall be made for differing top brace diameters and
fabrication tolerances.
7.1 Deck
7.1.1 The deck(s) shall be set as one complete unit or in separate sections, as shown on the Contract
Drawings and in accordance with Section 5.1 of this Specification.
7.1.2 Deck sections shall be jacked into position to give correct line up for making field welds, as
required.
7.1.3 All field installed structural shapes shall be site cut to required length, bevelled, accurately fitted,
welded out and inspected in accordance with the Contract Drawings and Section 8 & 9 of this
Specification.
7.1.4 All field installed handrail panels, timber, grating, sump and pump caisson and drain line spools,
and the like, shall be accurately located and fitted in accordance with the Contract Drawings.
7.1.5 Welding out the deck legs to the stub piles, and inspection, shall be in accordance with Section 8
and 9 of this Specification and the Contract Drawings. Similarly for welding out an upper deck
onto a lower deck.
7.2 Boat Fenders, Sump Pump Deck, Toilets, Stairways, and the like
7.2.1 Items such as boat fenders, sump pump decks, toilets, and similar structures shall be installed,
located and connected (by welding or bolting as applicable) as shown on the Contract Drawings.
7.2.2 All stairways shall be adjusted to suit field dimensions, installed and connected as shown on the
Contract Drawings.
7.3 Bridges
7.3.1 Field dimensions between centre lines of bridge seats shall be accurately determined prior to
setting a bridge. Based on these dimensions, the bridge end beams shall be shortened by cutting
from the fixed end as necessary.
7.3.2 Bridges shall be accurately positioned, and the fixed end and sliding shoe end welded out, all in
accordance with the Contract Drawings.
7.3.3 Grating, grating supports and handrail panels shall be shortened or lengthened as required in
order that the bridge is tied-in to the existing structures at either end.
7.4 Helideck
7.4.1 The helideck(s) shall be set as shown on the Contract Drawings and in accordance with Section
5.1 of this Specification.
7.4.2 All field installed structural shapes shall be site cut to required length, bevelled, accurately fitted,
welded out and inspected in accordance with the Contract Drawings and Section 8 & 9 of this
specification.
7.5 Tolerances
7.5.1 Decks
7.5.1.1 The deck(s) shall be set level such that their final elevation is within a tolerance of ± 75.0
mm of that shown on the Contract Drawings, relative to actual mean sea level. Any field
welds in the top flange of drilling platform skid beams shall be ground flush in order that
the beams are flushed at such field splices, and level to a tolerance of ± 12.5 mm
throughout along their total length.
7.5.2 Fenders
7.5.2.1 All boat fenders and landings shall be set in accordance with Contract Drawings, at the
correct elevation relative to actual mean sea level.
7.5.3 Bridges
7.5.3.1 All bridges shall be accurately set in accordance with the actual dimensions between
centre lines of bridge seats, and with the centre lines of the flowlines on both the bridges
and platform.
7.5.4 Helidecks
All helidecks shall be set such that the final position is within a tolerance of ± 25 mm of that
shown in the Contract Drawings.
8.1 General
8.1.1 All structural welding shall be in accordance with the American Welding Society's Structural
Welding Code AWS D1.1 - latest edition, including any revisions (hereafter referred to as "AWS
D1.1"), the Contract Drawings, and as further required in this specification. Welding symbols
shown on the Contract Drawings are those of the American Welding Society. The Gas Metal Arc
Welding process shall not be permitted.
8.1.2 Welding Procedures, repair and tacking procedures, qualification of welders, welding operators
and tackers, inspection and testing procedures applicable to all structural welding shall be in
accordance with AWS D1.1, and this specification. The essential variables of AWS D1.1 shall
apply to all welding procedures.
8.1.3 "The Engineer" as specified in AWS D1.1 shall mean the person(s) authorized by the COMPANY
to act for and on behalf of the COMPANY on all matters within the Scope of the Work.
"The Inspector" as specified in AWS D1.1 shall mean the person(s) authorized by the COMPANY
to act for and on behalf of the COMPANY on all inspection and quality matters within the Scope
of the Work.
The "Contractor" or "Fabricator" as specified in AWS D1.1 shall mean the 'CONTRACTOR'.
8.1.4 General and detailed welding procedures and welding instructions shall be typed, thoroughly
detailed and displayed in the working area of the fabrication site. Detailed welding instructions
for each specific job shall be clearly typed on proper work forms and given to the welder doing
the work. The CONTRACTOR's foremen shall be familiar with the approved welding procedures
and sequences, and shall see that they are followed. High heat input welding processes such as
electrogas or electroslag welding, and any welding process operating to give a heat input
exceeding 5KJ/mm are not acceptable.
8.1.5 All structural welding shall be performed by welders and operators who have been qualified prior
to employment on the COMPANY's work. A "Qualification Test Record" shall be submitted to the
COMPANY for each test a welder completes.
8.1.6 Material used is basically ASTM A36 steel, fabricated according to ASTM A6, API 5L Grade B,
or API Spec. 2B. However, in certain instances 290 or 345 MPa yield stress steel may have
been used.
8.3.1 General
The electrodes, wires and fluxes used, shall be in accordance with AWS Dl.1 and shall be
chosen to produce welds with mechanical properties not less than, and chemical properties
compatible to, those specified for the base material and shall be subject to inspection and
approval at the discretion of the COMPANY. Permanent backing rings or copper backing strips,
shall not be used. Low hydrogen consumables/electrodes shall be used throughout. Vertical-
down welding will not be permitted.
Submerged arc fluxes shall be of the basic type.
8.4.1 General
All welding procedures, including repair, tacking, plate repair, fusion face repair and fillet welds
shall be in accordance with AWS. D1.1 and as further qualified by this specification. Procedures
shall be submitted to the COMPANY for review and shall be established and qualified before any
welding is commenced. The welding procedure sheet found at the back of this specification shall
be used for this purpose. Incomplete procedure information shall not be accepted. No
qualification test shall be performed until the procedure specification has been granted
preliminary approval by the COMPANY. Qualification of a welding procedure must be witnessed
by the C.S.R. In addition to the requirements set forth in the AWS D1.1 the welding procedures
shall also include:-
(1) Detailed, numbered weld pass sequence.
(2) Preheat temperature and method of application and checking. Post weld heat treatment
procedure.
(3) Minimum and maximum interpass temperature and method of checking.
(4) Electrode, wire, and flux, trade name, code classification, storage, baking and issue
procedures.
(5) Humidity condition at location of use. Hydrogen content of consumables at time of use
(based on manufacturers data).
(6) All preventative measures for Lamellar tearing of T-type joints.
(7) Heat input (Maximum) of welding process.
(8) The number of heat cycles that will be used in production, and the maximum time that
the production weld will remain part welded.
Prequalification under AWS D1.1 Section 2 shall not be permitted.
In addition to the testing requirements of AWS D1.1 the following tests are required.
(A) Macro and hardness survey of weld and heat affected zone. This should be done to
figure 15 and the maximum recorded hardness using Vickers 10 kg load shall not
exceed 300 V.P.N.
(B) An all weld metal tensile test to include elongation and reduction of area measurement.
(C) A full set of Charpy V impact tests. This should be done to figure 16. The test
temperature shall be -10 °C and the results obtained shall be 34 joules average of three
specimens, 29 joules individual minimum.
Full details of the welding procedure and the test results shall be submitted on the forms detailed
at the back of this specification.
8.4.3 Performance
Should a test weld fail any of the required tests, the cause of the failure shall be established,
rectified and the complete procedure test shall be repeated. No fabrication welding shall
commence until the appropriate procedure tests have been approved by the COMPANY. Should
a qualified welding procedure show poor production performance the causes of the poor
performance shall be assessed and a modified welding procedure shall be qualified and
submitted to COMPANY for approval.
8.4.4 Essential variables in Qualification of Welding Procedures
Requalification of a welding procedure is required when changes are made with respect to any
of the essential variables of AWS D1.1, or a change in the trade name of any of the welding
consumables has occurred. Changes in one or more of the non-essential variables will call for a
new weld procedure specification.
8.5.1 General
All welders, welding operators and tackers shall be qualified prior to employment on the
COMPANY's work. All qualification tests shall be done in the presence of a COMPANY
representative. Qualification shall be to AWS D1.1 and this specification. All costs associated
with qualification shall be at the CONTRACTOR's expense. The decision of the COMPANY
regarding qualification shall be final. Qualification tests shall be as outlined in AWS DI.1 but in
addition the following extra tests shall be done.
(1) All destructive tests as per AWS D1.1.
(2) 100% visual examination.
(3) 100% Radiography.
Backing strips as outlined in AWS D1.1 shall not be used. Qualification tests involving back
gouging shall qualify only butt joints in production that involve back-gouging. The depth of the
back gouge profile shall be controlled at 6 mm max. depth.
Operators not passing the tests are disqualified from working on the job. The CONTRACTOR
shall ensure that only qualified welders/tackers and welding operators are employed on the work
and that each man is qualified for the process, position, butt joint detail and material in use. A
welder, tacker or operator may be required to requalify if inspection during fabrication reveals
that extensive repairs are necessary due to unacceptable defects. This shall be done by
documenting a period of retraining. The length of this period shall be at the discretion of the
COMPANY.
8.6.1 General
Each welding procedure shall be qualified, in accordance with Subsection 8.4 "Qualification of
Welding Procedures" of this Specification before it is used for fabrication welds.
No welding shall be done until the structures are properly aligned and stiffened.
Welds shall develop not less than the net area of the sections joined and shall be continuous to
seal the members from corrosion, unless otherwise indicated on the Contract Drawings.
Members shall be carefully contour fitted, bevelled to a suitable edge and a full penetration weld
obtained. Where strength welds are required by the Contract Drawings or otherwise to extend
only partially around a member (including plates) joining another member (including plates), 3
mm minimum fillet seal welds shall be applied continuously throughout the remaining distance
around the member (plate), but a weld metal and heat affected zone hardness of 300 V.P.N.
shall not be exceeded.
Where accessible the root side of full penetration welds shall be back-gouged to sound metal
before any weld is applied to the back-side. When the air-carbon arc process is used for
backgouging particular care shall be taken to ensure that the minimum required air pressure and
flow rate, recommended by the manufacturer, are maintained and that the arc is not established
before the air flow is established. Grinding and 100% magnetic particle or dye penetrant testing
shall follow all gouging operations. Flame gouging shall not be used.
8.8.1 General
The AWS Dl.1 code shall be the authority for structural welding and structural welding inspection
with the exceptions noted herein.
The COMPANY may elect to check the quality of welds by any applicable method.
The CONTRACTOR shall provide on site complete facilities for radiographic and ultrasonic
inspection of welds, including equipment for development and viewing films and the full-time
services of qualified technicians conversant with radiographic and ultrasonic inspection
techniques, to operate the above equipment.
The qualification of all NDT technicians is subject to COMPANY approval. Ultrasonic operators
shall be qualified to current C.S.W.I.P. 3.6 or the revised qualification C.S.W.I.P. 3.9. Lloyds or
DNV equivalent is acceptable. Radiographic Technicians shall be licensed or government
approved. CONTRACTOR's personnel interpreting radiographs shall hold recognized formal
qualifications.
All testing of structural welds, or repairs to structural welds, shall be carried out as soon as
possible after the completed welds have cooled to ambient temperature, with the exception of
pile and conductor butt welds which may be tested once the weld/weld area has cooled to 65 °C
(will be checked by thermostick). Final acceptance testing of PWHT joints shall be done after
PWHT. Test results shall be submitted within 12 hours of test completion.
The COMPANY shall be the sole judge of the acceptability of all welds and COMPANY's
decision will be final an in this respect all completed welds must be approved by the COMPANY.
8.8.2.1 Radiographic
A butt weld is defined as a full penetration circumferential or longitudinal weld made in
tubular members or as a full penetration splice weld to join sections of a plate or rolled
shapes (i.e. wide flanges beams, channels, etc.).
All butt welds in tubular members with a diameter of 250 mm (10 inch) and above shall
be fully radiographed. Ten per cent of all other butt welds in tubular members shall be
fully radiographed. All butt welds in rolled or fabricated shapes with a nominal height of
350 mm (14 inch) and above, or flange thickness of 12.5 mm and above shall be fully
radiographed. Ten percent of all other butt welds in rolled or fabricated shapes shall be
fully radiographed. Butt welds which are impractical to radiograph, shall be ultrasonically
tested.
If, in the opinion of the COMPANY, additional radiography of butt welds is required, the
CONTRACTOR shall radiograph all additional welds so designated and shall perform
this work at the Unit Price. If difficulty is experienced in interpreting defects revealed by
radiography, ultrasonic testing shall also be used to aid interpretation, or vice versa.
8.8.3 Examination
If ultrasonics or magnetic particle inspection of welds appears to indicate any defect, then such
weld may be thoroughly re-examined by any means, including radiographic, as directed by the
COMPANY.
Welds shall be uniform and the transition to base material adjacent to the weld shall be smooth
and free from undercut, and in accordance with AWS Dl.1.
Welds shall also be examined for incomplete penetration, lack-of fusion, burned-through areas,
slag inclusions, porosity, under cutting and improper weld geometry. If these or any other
defects are discovered which in the opinion of the COMPANY are detrimental to the integrity of
the structure then all such welds shall be repaired or replaced by the CONTRACTOR to the
satisfaction of the COMPANY, at no cost of the COMPANY.
If spot checking of welds reveals that a particular weld appears to be defective, the entire weld
shall be examined and the spot checking of all other welds made by the same welder(s) may be
carried out at the discretion of the COMPANY and may be extended as specified below :-
Group I Group II Group III Group IV
Extent of first In case of defective In case of defective In case of defective
spot checking welds in checking welds in checking welds in checking
Group I, to be extended Group II, to be extended Group III, to be
to : to : extended to :
If subsequent faults are found, the COMPANY may require that the welder be re-tested as
prescribe in AWS D1.1 and this Specification.
If a weld proves to be defective, it shall be repaired to the complete satisfaction of the
COMPANY in accordance with Subsection 8.6 "Fabrication Welding Procedures".
The CONTRACTOR shall be solely responsible for the cost of all testing, repairing or replacing
and retesting all welds found to be defective as well as for the additional testing specified in the
above table.
The percentage of welds to be inspected shall mean the thorough inspection of the stated
percentage of all welded connections of a given type and shall NOT mean the inspection of
stated percentages of total weld length.
9.1 The COMPANY shall have the right to inspect the materials, fabricated, erection and surface
preparation of all items concerned with these Contract Documents and the Contract Drawings,
without limitation.
9.2 The COMPANY shall have free access at all times to the Work, and to any part of the
CONTRACTOR's equipment that concerns the Work. When, in the COMPANY's judgement, any
working area or section should be inspected, the CONTRACTOR must thoroughly clean it of all
excess and waste materials, such as sand, slag, welding rods and the like, provide adequate
access to it, and allow sufficient time for it to be properly inspected.
9.3 The COMPANY shall be notified before any repairs are made to welds when defects are found
and NOT after same defects have been corrected. Whenever any piece is to be assembled that
will prevent inspected and any defects corrected before proceeding with the
assembly/erection/installation.
9.4 The COMPANY shall have the right to inspect at any time, tools and/or equipment to be used in
any part of the Work, and shall have the right to condemn any equipment or work which does not
conform with the Contract Documents or the Contract Drawings. Defective work or work not
conforming to the Contract Documents or the Contract Drawings shall be redone by the
CONTRACTOR at no additional cost to the COMPANY.
9.5 The COMPANY must approve all phases of the testing and assembly/erection/installation.
9.6 The COMPANY shall have the right to request any additional inspection to ensure that Work
conforms to these Contract Documents.
9.7 The CONTRACTOR shall furnish, install and maintain in a safe operating condition all
scaffolding, ladders, walkways, adequate lighting, and the like, necessary for safe and thorough
inspection by the COMPANY. The safety and condition of the above scaffolding, ladders, lighting,
and the like, must conform with Local Industrial Safety Codes, or applicable International Codes
in the event that Local Codes do not exist for such operations, and the COMPANY reserves the
right to halt the Work should the foregoing not be complied with. In such an event, the
CONTRACTOR shall take all necessary steps to correct the situation and all costs in complying
with same (including delays to the progress of the Work) shall be for CONTRACTOR's account.
9.8 The CONTRACTOR must establish, before COMMENCEMENT OF THE WORK, a numbering
system to identify each section, member shall be used for identification purposes on any
CONTRACTOR prepared drawings or documentation.
10. DOCUMENTATION
10.1 The CONTRACTOR shall compile an Installation Report in A4 size paper and shall submit two
(2) copies to the COMPANY not later than six (6) weeks after the completion of each installation
for approval. The COMPANY shall return to the CONTRACTOR an approved or marked-up copy
of the report as applicable and re-issued the COMPANY (3) copies of the final approved report.
The report shall contain but not limited to the followings:
a) Acceptance Certificate(s)
b) Narrative Reports with lift weights/hook load, slings and shackles arrangement etc.
c) Planned vs actual work schedule with Daily Status Reports
d) Geodetic Survey Report
e) Pile Driving Records and graphs
f) Grouting Records and test results
g) Damages and Repairs
i) Test Reports (NDT, Radiographic, etc.)
j) Diving Reports, including video recording of post-installation survey and grouting
survey
k) Others
10.4 All drawings shall be Al, A3 or A4 sizes with the title block in the lower right hand corner.
Drawings submitted for formal approval shall used the revision numbers 0, 01, 02 and the like.
Drawings after being approved shall use the revision numbers A, B, C and the like.
All drawings shall be signed by a CONTRACTOR's engineer familiar with the work.
NOTES:
1. ANODES SHALL BE MANUFACTURED IN ACCORDANCE WITH SPECIFICATION FOR ALUMINIUM ANODES FOR
THE CATHODIC PROTECTION OF FIXED OFFSHORE PLATFORMS.
2. ANODES SHALL BE SUPPLIED WITH A350 STAND-OFF, SQUARE CUT AT THE END
3. WHERE APPROXIMATE DIMENSIONS ARE SHOWN, MANUFACTURED DIMENSIONS ARE SUBJECT TO
COMPANY APPROVAL.
2
4. MINIMUM ALLOY WEIGHT 356 KG = 783 LBS. MINIMUM CROSS SECTIONAL AREA 579 cm
5. APPROXIMATE GROSS ANODE WEIGHT 398 KG. = 875 LBS.
6. CORE MATERIAL SHALL BE TO API 5L GRADE B OR EQUIVALENT.
7. PREPARATION OF STAND-OFF AND DOUBLER PLATE (WHERE APPLICABLE) TO BE DONE BY JACKET
FABRICATOR.
8. ANODES SHALL BE LOCATED SO THAT THEY ARE VERTICALLY IN LINE WITH BRACING WHEN JACKET IS
PLACED.
9. ALL DIMENSION IN MILLIMETERS UNLESS OTHERWISE STATED.
ANODE TYPE C (30 YEARS)
NOTES:
1. ANODES SHALL BE MANUFACTURED IN ACCORDANCE WITH SPECIFICATION FOR ALUMINIUM ANODES FOR
THE CATHODIC PROTECTION OF FIXED OFFSHORE PLATFORMS.
2. ANODES SHALL BE SUPPLIED WITH A 14” STAND-OFF, SQUARE CUT AT THE END.
3. WHERE APPROXIMATE DIMENSIONS ARE SHOWN, MANUFACTURED DIMENSIONS ARE SUBJECT TO
COMPANY APPROVAL.
4. APPROX. ALLOY WEIGHT 619KG. = 1362 LBS.
5. APPROXIMATE GROSS ANODE WEIGHT 676 KG. = 1487LBS.
6. CORE MATERIAL SHALL BE TO API 5L GRADE B OR EQUIVALENT.
7. PREPARATION OF STAND-OFF AND DOUBLER PLATE TO BE DONE BY JACKET FABRICATOR.
8. ANODES SHALL BE LOCATED SO THAT THEY ARE VERTICALLY IN LINE WITH BRACING WHEN JACKET IS
PLACED.
FIGURE 17 : WELDING PROCEDURE
FIGURE 18 : CERTIFICATE OF TEST