Professional Documents
Culture Documents
Procurement Strategy and Outcomes of New Universities Project
Procurement Strategy and Outcomes of New Universities Project
www.emeraldinsight.com/0969-9988.htm
ECAM
26,9 Procurement strategy and
outcomes of a new universities
project in South Africa
2060 Samuel Laryea
School of Construction Economics and Management,
Received 10 April 2018
Revised 17 September 2018 University of the Witwatersrand, Johannesburg, South Africa
24 February 2019
Accepted 5 March 2019
Abstract
Purpose – Construction project management outcomes in the literature typically portray significant
deviations from expected outcomes. Various theories from studies that focus superficially on causes of project
cost and time overruns rather than root causes have not addressed this problem. The need is for a better
understanding of how procurement strategy provides a fundamental means to address this problem. The
purpose of this paper is to examine the procurement strategy used to deliver a new universities project in
South Africa within budget and to ascertain its influence on the outcomes.
Design/methodology/approach – A case study was designed to provide a comprehensive and intensive
methodology to identify and examine the construction procurement strategy and its influence on the project
outcomes. Document analyses and semi-structured interviews were used to collect data on the construction
procurement strategy and outcomes from the client team.
Findings – The evidence brought forward demonstrates that the successful outcome was largely a
consequence of the client team, procurement strategy and systems of delivery. However, the collaborative
procurement strategy formed the basis of the successful project delivery and outcomes. A general observation
from the data is that an appropriate construction procurement strategy developed by an experienced client
team and proactively implemented by an integrated delivery team working collaboratively is likely to achieve
the intended project outcomes.
Practical implications – The findings show three critical keys to achieving intended outcomes – people,
procurement strategy and systems of delivery at the governance, portfolio, programme and project
management levels.
Originality/value – The value of this paper lies in using a comprehensive methodology to study the
relationship between procurement strategy and outcomes. The findings can be applied by client teams to
achieve better outcomes and value for money in infrastructure projects.
Keywords Integration, Case study, Project management, Strategic management
Paper type Case study
1. Introduction
Project management outcomes reported in the construction management literature typically
portray significant deviations from intended outcomes, which places value for money for a
project at risk. This phenomenon is a common occurrence in the construction industry and
various theories arising from several studies on causes of project cost and time overruns have
proved insufficient to address this perennial problem over time. One reason for this may be
due to the observation that a majority of the studies on this phenomenon have tended to focus
superficially on the symptoms rather than root causes (see Flyvbjerg et al., 2018).
The current study examines the procurement strategy as a root cause of deviations
between expected and achieved outcomes in projects. Limited literature on the subject of
construction procurement strategy is mainly experiential in nature and shows that the
purpose of a procurement strategy is to identify the best way to achieve the objectives of a
project and value for money (OGC, 2003; ISO 10845, Watermeyer, 2012). It is argued in the
Engineering, Construction and
Architectural Management current study that if this strategic exercise is well crafted and implemented, then the gap
Vol. 26 No. 9, 2019
pp. 2060-2083
between expected and actual outcomes should be as close as possible (see Laryea and
© Emerald Publishing Limited
0969-9988
Watermeyer, 2014). However, clients continue to experience the problem of poor outcomes and
DOI 10.1108/ECAM-04-2018-0154 there is a need for a better understanding the empirical relationship between procurement
strategy and outcomes which will inform a more successful approach to the delivery of New
infrastructure projects. universities
The case of Phase I of a new universities project in South Africa is examined to probe project in
deeply into the procurement strategy used to achieve its delivery within budget; and its
influence on the project outcomes. The value and main contribution of this research lies in South Africa
using a comprehensive and intensive methodology to examine the relationship between the
procurement strategy and outcomes of a new universities project. This is currently a gap in 2061
the literature relating to this subject which the findings of this study help to illuminate.
The starting point for this paper was the observation that an R1.5bn ($100,000) project had
been delivered within budget using alternative delivery approaches that had been adopted in
the procurement strategy for the project. This phenomenon is not the norm in South African
where significant deviations from expected outcomes are often reported on projects especially
large public sector infrastructure projects (see, e.g. publications by Nkado, 2010; Thomas,
2013; Public Protector, 2014; Fombad, 2015 which examine significant cost overruns in
projects such as the 2010 FIFA World Cup Stadia, Gautrain project, Nkandla project).
However, also in the context of the wider construction management literature, many academic
researchers have reported on poor outcomes in infrastructure projects (see demonstrated in
the literature review section). Hence, the phenomenon of poor project outcomes extends
beyond the South African environment into other international jurisdictions. Therefore,
research was needed to investigate how this particular project was delivered within budget;
and then attempt to theorise from it a general statement on practices which contributed to the
successful project outcomes.
A preliminary enquiry showed that the procurement strategy adopted by the client’s
team was one of the fundamental keys to the successful project outcome. Hence, the purpose
of this study was to examine the nature of the procurement strategy underpinning the
successful delivery of the project and its influence on the project outcomes.
The specific objectives were to:
• examine the nature of the procurement strategy developed by the client team to
achieve the intended outcomes of the project;
• analyse the project outcomes as a means to assess the efficacy of the procurement
strategy for the project; and
• discuss any empirical observations on the relationship between procurement
strategy and outcomes.
The scope of this paper is limited to the construction works delivery. The procurement of
professional services and goods will be dealt with in another paper.
2. Literature review
The international standard for construction procurement (ISO, 2010) defines construction
procurement as the process through which contracts are created, managed and fulfilled.
This process entails establishing what is to be procured; deciding on procurement strategy;
soliciting tender offers; evaluating tender offers; contract award; and administering
contracts and confirming compliance with requirements.
The academic literature generally does not portray the construction industry as one
where the majority of projects are delivered according to the expected time, cost and quality
specifications. Studies by Frimpong et al. (2003), Koushki et al. (2005), Lee (2008), Ameh et al.
(2010), Bhargava et al. (2010), Nkado (2010), Memon et al. (2010), Pourrostam and Ismail
(2011), Memon et al. (2011), Love et al. (2012), Thomas (2013), Sweis et al. (2013), Doloi (2013),
Shrestha et al. (2013), Ismail et al. (2014), Shehu et al. (2014), Rajan et al. (2014), Cheng (2014)
and Fombad (2015) show evidence of significant deviations between expected and actual
ECAM outcomes in infrastructure projects in, for example, Australia, China, Ghana, Iran, Jordan,
26,9 Kuwait, Malaysia, Nigeria, South Africa, South Korea and the USA.
Several theories have been put forward by academic researchers to explain reasons for
the perennial wide deviations clients experience between expected and actual outcomes in
infrastructure projects. The majority of such theories are found in studies on causes of
project cost and time overruns. These include poor cost estimation, lack of information in
2062 the early stages, design changes and scope creep, technical difficulties, optimism bias,
managerial incompetence, strategic misrepresentation, inability to accurately identify and
quantify risks, lesser reliance on data mining, heavy reliance on contractors’s performance
alone for cost performance (see Frimpong et al., 2003; Ahiaga-Dagbui and Smith, 2014).
A paper by Flyvbjerg et al. (2018) stated that psychological and political bias are the
underlying reasons for cost overruns in projects. However, Love and Ahiaga-Dagbui
(2018) counter argued that cost overruns are largely a result of errors caused by scope
changes and complexity.
Procurement strategy has not been comprehensively examined by academic researchers
as a root cause of poor outcomes in infrastructure projects – although some practitioners
have (see, for example, a paper by Watermeyer, 2012 on “Changing the construction
procurement culture to improve project outcomes”). The World Bank (2016) also appears to
have identified this key issue and now requires a project procurement strategy for all its
funded projects since publishing its new procurement guidelines in 2016. The World Bank
(2016) prucurement guidelines describes this as “the overall design of ‘fit for purpose’
procurement to award contracts that deliver the project development objectives and value
for money. This includes the procurement arrangements, procurement risk management,
contract strategy, market engagement, requirements drafting and contract management
(where appropriate)”.
This paper argues that cost and time overruns are largely symptoms of a more
underlying root cause which this paper argues to be procurement strategy, that is, either a
lack of procurement strategy or an inappropriate/inadequate procurement strategy. A
construction procurement strategy identifies the best way to achieve intended outcomes and
value for money (OGC, 2003; ISO, 2010). If this strategic exercise is competently designed
and executed, the gap between intended and actual outcomes should be as close as possible.
However, other root causes have been argued by other researchers. For example, in
specific relation to the root cause of cost overruns in infrastructure projects, Flyvbjerg et al.
(2018, p. 10) argued as follows: “Your biggest risk is you, according to behavioural science.
The root cause of cost overrun is human bias, psychological and political. Scope changes,
complexity, geology, archaeology, bad weather, business cycles, etc. are causes, but not root
causes. If you don’t solve the problem of cost overrun at the root, you will not end overrun”.
The current study agrees that dealing with causes or symptoms will not necessarily
address the root cause(s). However, assuming that the human bias variable was properly
addressed in a project, an appropriate construction procurement strategy is still required to
set the basis to achieve intended project outcomes. A private sector infrastructure project
may not be fraught with the problem of psychological and political bias but still experience
deviations from expected outcomes due to a lack of (or inadequate) appropriate procurement
strategy. It should be clarified here that a procurement strategy is not the same as
procurement method or route which relates more to the systems of organisation of
contractual roles and responsibilities for infrastructure project delivery (see Hughes et al.,
2015). According to OGC (2003), “the procurement route delivers the procurement strategy.
It includes the contract strategy that will best meet the client’s needs”. The choice of
procurement method or route will therefore fall under one of the five components of a
construction procurment strategy (see explained in ISO, 2010). The rest of this section looks
at some key literature on the procurement strategy.
2.1 Procurement strategy New
There is a fairly well-developed body of knowledge on the concept of procurement strategy universities
generally in the context of commercial transactions and specifically in the construction project in
industry context. The existing body of knowledge on procurement strategy can substantially
be found in 184 articles published between 1978 and 2018 (as found through a systematic South Africa
search in Scopus conducted in September 2018). Each of the 184 articles has the phrase
“procurement strategy” in the article title. The articles can be found in a wide range of sources 2063
relating to different academic fields and industrial sectors such as aerospace, commerce,
defence, engineering, information technology, production and public procurement.
This paper is focused on construction procurement strategy and in this regard, 8 of the 184
articles relate to procurement strategy in the construction industry context. This literature
review here covers a general overview of meaning and principles from the broader concept of
procurement strategy and then focuses specifically on the research studies and current extent
of knowledge on the subject of procurement strategy in the construction industry.
The 184 articles indicate that a procurement strategy generally refers to the strategic
approach designed to obtain required works, goods and/or services in the most appropriate way,
taking into consideration several factors and values of the client such as the time, funding and
budget, risks and opportunities, among others. In a construction industry-specific context,
procurement is the process through which contracts are created, managed and fulfilled
(ISO, 2010). Therefore, a construction procurement strategy relates to the overall strategic
approach developed by the client’s project leadership team to achieve intended objectives and
best value. Three publications connected with the literature on construction management
provide definitions of a construction procurement strategy: ISO, 2010; BSI, 2011 and OGC, 2003.
OGC (2003) publication on Procurement and Contract Strategies (Achieving Excellence in
Construction Procurement Guide 6) explains that a procurement strategy “identifies the best
way of achieving the objectives of the project and value for money, taking account of the
risks and constraints, leading to decisions about the funding mechanism and asset
ownership for the project. The aim is to achieve the optimum balance of risk, control and
funding for a particular project”. The guide goes on to explain the relationship between the
procurement strategy, procurement route and contract strategy. The procurement strategy
determines the most appropriate procurement route, including the contract strategy, to fit
the project objectives and current circumstances. The procurement route delivers the
procurement strategy. It includes the contract strategy that will best meet the client’s needs.
An integrated procurement route ensures that design, construction, operation and
maintenance are considered as a whole; it also ensures that the delivery team works together
as an integrated project team. The contract strategy determines the level of integration of
design, construction and ongoing maintenance for a given project, and should support the
main project objectives in terms of risk allocation, delivery and incentivisation.
It seems clear that the contracting strategy may be influenced or limited by the specific
standard form of contract employed in the project delivery. That is one reason why the choice of
a standard form contract should be carefully approached (Fitzgerald and Hodgson, 2010. In
South Africa, the Construction Industry Development Board’s (CIDB) endorses the use of two
international forms of contract (FIDIC suite of contracts and NEC family of contracts) and two
local forms of contract (SAICE’s General Conditions of Contract for Construction Works (GCC)
and the JBCC suite of contracts)). The Construction Indusry Development Board (CIDB) (2016)
survey of construction industry indicators in South Africa shows that while all four forms of
contracts are significantly used by clients, the JBCC form of contract is typically used for
building projects while the rest are typically used for civil engineering and local government
projects. This is probably influenced by traditional perceptions or categoration of contracts into
building contracts and civil engineering contracts. However, there is an increasing use of NEC
contracts in South Africa (see Laryea and Watermeyer, 2014, 2018).
ECAM According to the ISO (2010) family of standards for construction procurement, “a
26,9 procurement strategy consists of the selected packaging, contracting, pricing and targeting
strategy, and procurement procedure for a particular procurement”. ISO (2010) outlines five
key components of a construction procurement strategy as packaging (organisation of work
packages into contracts), contracting (nature of the relationship between the parties), pricing
(how to secure financial offers, build up tender prices, and remunerate contractors), targeting
2064 (procedures for promoting secondary procurement objectives) and procurement procedure
(how tender offers are solicited). Various options available for dealing with each of the
components of a construction procurement strategy are outlined in ISO (2010) and also
explained in an experiential-based paper by Watermeyer (2012) in which a framework for
developing a construction procurement strategy was presented. The paper by Watermeyer
(2012) explains that procurement strategy is about the choices made in determining what is to
be delivered through a particular contract, the procurement and contracting arrangements
and how secondary procurement objectives are to be promoted. As such, a construction
procurement strategy comprises of the strategies relating to packaging, contracting, pricing,
targeting and procurement procedure for projects. The purpose is to satisfy the client’s
functional needs in the most appropriate way.
The British Standard on Construction Procurement (BSI, 2011) defines a construction
procurement strategy as a “plan of action for funding, organisation, management, selection
and payment of supply chains for the design, fabrication and which may include the
operation of constructed facilities to achieve a desired objective”. BS 8534 notes that the
choices made in relation to funding, selection method, price basis, responsibility for design,
responsibility for management and supply chain integration informs the strategic
procurement approach and project outcomes.
Client/Sponsor
Department of Higher Education
and Training (DHET)
Implementing agent
Wits governance and oversight
Wits Director of Campus Planning
and Development
2068
Table I.
ECAM
contract strategies
SPU procurement and
Time Control Price
variance budget variance Targeting
(% (agreed target (% Design Contract strategies (LPG
Planned Actual increase price when Final increase allocations and (a); B-BBEE SG
Description of Start completion completion or order was account or (responsibility pricing Procurement (b); LDEG (c);
Project works date date date decrease) issued) price decrease) for design) strategy procedure SDG (d))
Framework contract for the services of a management contractor for the refurbishment, extension or alteration of existing buildings on the Sol Plaatje University precincts –
HSH Construction (Pty) Ltd
Renovation of 2013 – 2016 – R86.5 R86.1 m −0.4 DBE ECC-F FC-Open a
existing tender FC-
buildings and Negotiated
upgrading works
(17 Package
Orders)
Framework contract for upgrading of infrastructure – Roburn Construction Trust 2
Upgrading of 2013 – 2016 – – R16.49 – DBE ECC-SC FC-Open a
infrastructure (5 m tender FC-
Package Orders) Negotiated
Framework contract for the construction of buildings on the Sol Plaatje University’s precincts in Kimberley – Murray and Dickson Construction, Trencon Construction,
Qualicon Construction
C001 New build 13 15 Jan 2016 2 Mar 2016 +10 R218 m R210 m −4 DBE(e) ECC-C FC-Open a, b, c, d
(residential, retail, Oct (460 days) (508 days) tender
laundry) 2014
C002 New build (mixed 13 15 Jan 2016 5 Jul 2016 +31 R244 m R232 m −5 DBE(e) ECC-C FC-Open a, b, c, d
use – residence, Oct (460 days) (602 days) tender
teaching venue, 2014
offices, retail)
C003 New build (mixed 13 15 Jan 2016 8 Apr 2016 +18 R174 m R172 m −1 DBE(e) ECC-C FC-Open a, b, c, d
use – residence, Oct (460 days) (544 days) tender
classrooms, 2014
auditorium,
offices)
(continued )
Time Control Price
variance budget variance Targeting
(% (agreed target (% Design Contract strategies (LPG
Planned Actual increase price when Final increase allocations and (a); B-BBEE SG
Description of Start completion completion or order was account or (responsibility pricing Procurement (b); LDEG (c);
Project works date date date decrease) issued) price decrease) for design) strategy procedure SDG (d))
CX01 New build (site 27 15 Jan 2016 20 May +49 R90 m R82 −9 DBE(e) ECC-C FC- a, b, c, d
infrastructure for Apr (264 days) 2016 (390 Negotiated
C001, C002, C003) 2015 days)
R812.5 m R782.1 −3.74
m
Notes: SPU, Sol Plaatje University. The control budget includes construction cost, a provision for price adjustment for inflation, a contingency amount of 5 per cent,
VAT, and a professional fee estimate based on the tendered fees. The final account price is based on actual costs. Contract and pricing strategy: ECC – NEC3 Engineering
and Construction contract; ECC-C – Main Option C (Target contract with activity schedule); ECC-B – Main Option B (Target contract with bill of quantities); ECC-F –
Management contract; SC – NEC3 Supply contract; ECC-SC – NEC3 ECC Short Contract; Design allocations (Responsibility for design): DBE – Works designed by the
employer; and DBE(e) – Works designed by the employer with early contractor involvement. Packaging strategy: FC – Framework contract; FC-Call off – Call off from
framework contract; FC-Negotiated – Negotiated target; Targeting strategies: LPG, local participation goal; B-BBEE SG, broad-based black economic empowerment
spend goal; LDEG, local direct employment goal; SDG, skills development goal
Table I.
universities
2069
South Africa
project in
New
26,9
2070
strategies
Table II.
ECAM
and contract
UMP procurement
Time Control Price Targeting
variance budget variance strategies
(% (agreed (% Design Contract (LPG (a); B-
Planned Actual increase target price Final increase allocations and BBEE SG (b);
Description of completion completion or when order account or (responsibility pricing Procurement LDEG (c);
Project works Start date date date decrease) was issued) price decrease) for design) strategy procedure SDG (d))
Framework contract for the services of a management contractor for the refurbishment, extension or alteration of existing buildings on the University of Mpumalanga
precincts – Norse Projects (Pty) Ltd
Total Renovation of – 2013-2015 – – R28.7 R26.74 −6.97 DBE ECC-F FC-Open a
of MCs existing m tender
buildings (8
POs)
Construction of orchard and water course – Norse Projects (Pty) Ltd
Orchard 2013 – – – R2.2 m – DBE ECC-SC Open tender
campuses
Renovation and expansion works by framework contractors – Siyabuswa Campus – Murray and Dickson (Pty) Ltd
Phase Refurbishment – 2012/2013 – – R19 m R19 m – DBE ECC-D FC-Open a
I of three tender
residential
units and other
upgrades work
Phase Refurb of – 2013/2014 – – R40 m R40 m – DBE ECC-D FC- a
II remaining negotiated
residences plus
upgrade of
classrooms/
dining halls
Phase Additional – 2014/2015 – – R80 m R80 m – DBE ECC-D FC- a
III residences negotiated
(continued )
Time Control Price Targeting
variance budget variance strategies
(% (agreed (% Design Contract (LPG (a); B-
Planned Actual increase target price Final increase allocations and BBEE SG (b);
Description of completion completion or when order account or (responsibility pricing Procurement LDEG (c);
Project works Start date date date decrease) was issued) price decrease) for design) strategy procedure SDG (d))
2071
South Africa
project in
New
Table II.
ECAM Themes Summary of key texts from interview transcripts
26,9
Procurement strategy Procurement strategy is driven by the client. You need a strong client
Procurement strategy is demand driven. A lot of it is driven by your time, cost
conundrum and your demand management – how much budget have you got and
how do you achieve?
Procurement strategy also involves your portfolio, programme and project
2072 management strategies
Set procurement strategy to match your strategic intents. What are we building,
What are the skills we need – Should be procured at competitive and
market-related prices
Our strategy was to go collaborative
We changed principal agents to project managers
In many places, there is no procurement strategy in place. Anytime you ask about
options, there are no options. It is a one size fits all approach
Packaging strategy Packaging strategy is whether you want individual contracts or package in a
framework. Too many relationships to manage if you have too many individual
contracts to manage
Packaging was the long-term relationship to achieve value. We really wanted long-
term relationships with collaborative working
We went for framework contracts – subject to satisfactory performance, more work
is given to the same contractor
Framework contracts because we did not have the time and space to procure
everything as a single project – and there was opportunity for contractor to
participate in everything provided he meets the performance criteria
Contracting strategy We wanted to have a culture of collaboration towards shared goals
The main question here was: How do we bring the contractors on board?
Risk sharing with the contractor was a key thing that helped to deal with cost
overruns and all of those issues. It is a partnership. What we bought in the
framework contract was a relationship. Builder became part of the project
Framework contracts gave us the ability to have early contractor involvement (ECI)
in the design development
The main thing here was early contractor involvement and integration of the design
and contractor teams – in the context of a design by employer contracting strategy
We wanted to test the design consultants from a buildability point of view. ECI was
about bringing the specialist to the table. The real value comes from the
construction partner. The value engineering you can only do from a practical
perspective. There is a level of skills and expertise your contractor has which has to
come to the table. The New Engineering Contract (NEC) contract provided a tool to
bring these things to the table and have a discussion between everyone. Under
traditional contracts, the contractor is not welcome at the design table and gets
blamed for everything
Pricing strategy We set a very strict control budget. Setting the control budget is an iterative
process. Control budget as opposed to a budget. That will be way before tendering –
you go to the market only once you know what your control budget is – when we
tender for a purchase order, we tender against an estimate
Build up realistic project budgets with appropriate contingencies
The main pricing strategy we have used is NEC Option A and C. We have gone
according to what the NEC offers. The pricing strategy is linked with the
sophistication of the market that you are going to engage with
We wanted collaboration and shared risk. We went for target cost because of the
partnership we wanted to establish. There has to be joint responsibility. With target
cost, you get a good understanding of the cost make-up. Target cost helps to take
the risk out of the pricing. You pay for actual costs here
Part of the pricing strategy is to price things upfront and find a way of managing
Table III. it – finding a way to deliver within your budget
Summary of key texts
from interview
transcripts (continued )
Themes Summary of key texts from interview transcripts
New
universities
Construction is all about information flow – provide sufficient information to price project in
The pricing strategy affects risk allocation between parties. We use the NEC six options –
choose your main options and then your secondary option. Our risk tool is working South Africa
through NEC options. The question is who is at risk for design, quantities, rates, etc.
Targeting strategy Targeting strategy is first of all – the socio-economic. We used targeted
procurement procedures – BEE, small business, women-owned business, bursaries, 2073
participation of local enterprises, skills development, etc.
Tendering/selection Competitive negotiation procedure. For first framework contract – we used
procedures expression of interest
Open tenders
Good screening/eligibility criteria. And we did framework from that. You do not
just use contractor gradings – use turnover, show us three jobs you have done of x
amount, etc. Table III.
demonstrated in the successful delivery of the Wits capital projects programme. This expertise
included programme management, project management, procurement and spatial planning. The
core team was then expanded to include academic, institutional and development expertise,
some of whom were identified by the DHET.
6. Discussion of results
The research aim was to examine nature of the procurement strategy used to deliver the
new universities project and its influence on the project outcomes. The data presented in
ECAM Tables I and II summarise the procurement strategy and project outcomes in terms of time
26,9 and cost performance. Three points are brought forward for discussion.
7. Conclusions
The research aim was to examine the procurement strategy for the new universities project
and its influence on the project outcomes. Key conclusions on the three research objectives
are as follows.
First, the data summarised in Tables I and II show a collaborative procurement strategy
where contractors were mostly appointed on framework contracts in line with the long-term,
value-based collaborative approach the client wanted. Refurbishment projects in the initial
ECAM stage of the project were based on management contracts (NEC Option F). Capital works
26,9 projects were mostly procured using target cost contracts (NEC Option C) which is an
incentive contract with an element of joint responsibility for financial risk. Alternative
strategies were used in a few projects where other strategies were more appropriate. This
“horse for courses” approach reflects procurement strategy which is different from the “one
size fits all” approach that tends to prevail in South Africa.
2080 Second, the project outcomes achieved through the procurement strategy were analysed
and summarised in Tables I and II. The data show a portfolio of 33 package orders or
individual projects successfully delivered within a control budget of R1.5bn.
Third, a precise measurement of the impact of procurement strategy alone on the
end outcomes is complex and this one case provides limited knowledge on this complex
relationship. A stated primary objective was to “deliver the new universities within a
control budget”. The conscious effort and choices made to put together an appropriate
collaborative procurement strategy which “could best help to achieve the intended
objectives” shows a relationship between procurement strategy and outcomes. Successful
delivery of the project outcomes demonstrates that the procurement strategy was fit for
purpose. Based on the evidence in the case examined, a general observation or statement on
the relationship between procurement strategy and outcomes is that: an appropriate
construction procurement strategy developed by an experienced client team and proactively
implemented by an integrated delivery team working collaboratively is likely to achieve
intended project outcomes.
Acknowledgement
Gratitude is due to the Wits University Campus Planning and Development Office and the
New Universities Project Management Team for the significant asistance which made this
study possible. The author also wishes to thank the anonymous reviewers whose comments
greatly helped to improve this paper. This work is based on the research supported in part
by the National Research Foundation of South Africa (NRF). The grant holder
acknowledges that the opinions, findings and conclusions or recommendations expressed
in any publication generated by NRF-supported research are that of the authors and that the
NRF accepts no liability whatsoever in this regard.
References
Ahiaga-Dagbui, D.D. and Smith, S.D. (2014), “Rethinking construction cost overruns: cognition,
learning and estimation”, Journal of Financial Management of Property and Construction, Vol. 19
No. 1, pp. 38-54, available at: https://doi.org/10.1108/JFMPC-06-2013-0027
Ameh, O.J., Soyingbe, A.A. and Odusami, K.T. (2010), “Significant factors causing cost overruns in
telecommunication projects in Nigeria”, Journal of Construction in Developing Contries, Vol. 15,
pp. 49-67.
Bengtsson, M. (2016), “How to plan and perform a qualitative study using content analysis”,
Nursing Plus Open, Vol. 2, pp. 8-14.
Bhargava, A., Anastasopoulos, P.C., Labi, S., Sinha, K.C. and Mannering, F.L. (2010), “Three-stage least-
squares analysis of time and cost overruns in construction contracts”, Journal of Construction
Engineering and Management, Vol. 136 No. 11, pp. 1207-1218.
Bowen, G.A. (2009), “Document analysis as a qualitative research method”, Qualitative Research
Journal, Vol. 9 No. 2, pp. 27-40, available at: https://doi.org/10.3316/QRJ0902027
BSI (2011), BS 8534:2011: Construction Procurement Policies, Strategies and Procedures: Code of
Practice, BSI, London.
Cheng, Y.M. (2014), “An exploration into cost-influencing factors on construction projects”,
International Journal of Project Management, Vol. 32 No. 5, pp. 850-860.
Construction Industry Development Board (CIDB) (2016), Construction Industry Indicators (CIIs) Report, CIDB, New
Pretoria, available at: www.cidb.org.za/publications/Pages/Construction-Industry-Indicators.aspx universities
Construction Industry Institute (2002), BMM2002-10 – Measuring the Impacts of the Delivery System project in
on Project Performance – Design-Build and Design-Bid-Build, Publication BMM2002-10,
Construction Industry Institute, Austin, TX. South Africa
Doloi, H. (2013), “Cost overruns and failure in project management: understanding the roles of key
stakeholders in construction projects”, Journal of Construction Engineering and Management, 2081
Vol. 139 No. 3, pp. 267-279.
Fitzgerald, P. and Hodgson, S. (2010), “Funding higher education infrastructure investment: the case of
Wits University, South African Regional Universities Association (SARUA)”, Leadership
Dialogue Series, Vol. 2 No. 2, pp. 28-42.
Flyvbjerg, B., Ansar, A., Budzier, A., Buhl, S., Cantarelli, C., Garbuio, M., Glenting, C., Holm, M.S.,
Lovallo, D., Lunn, D., Molin, E., Rønnest, A., Stewart, A. and van Wee, B. (2018), “Five things you
should know about cost overrun”, Transportation Research Part A Policy and Practice, Vol. 118,
December, pp. 174-190, available at: https://doi.org/10.1016/j.tra.2018.07.013
Fombad, M.C. (2015), “Governance in public–private partnerships in South Africa: some lessons from
the Gautrain”, Journal of Southern African Studies, Vol. 41 No. 6, pp. 1199-1217, doi: 10.1080/
03057070.2015.1117240.
Frimpong, Y., Oluwoye, J. and Crawford, L. (2003), “Causes of delay and cost overruns in construction
of groundwater projects in a developing countries: Ghana as a case study”, International Journal
of Project Management, Vol. 21 No. 5, pp. 321-326.
Hughes, W. (2001), “What makes a good research paper?”, ARCOM Newsletter, Vol. 16 No. 3,
pp. 1-4, available at: www.arcom.ac.uk/newsletters.php
Hughes, W., Champion, R. and Murdoch, J. (2015), Construction Contracts – Law and Management,
5th ed., Routledge, London.
ICE (2009), Client Best Practice Guide, Thomas Telford Limited, London, ISBN: 978-0-7277 3650-5.
ICE (2017), From Transactions to Enterprises, A New Approach to Delivering High Performing
Infrastructure, Infrastructure Client Group, London.
Ismail, I., Memon, A.H. and Rahman, I.R. (2014), “Expert opinion on risk level for factors affecting time
and cost overrun along the project lifecycle in Malaysian construction projects Int”, Journal of
Construction Technology Management, Vol. 1, pp. 10-15.
ISO (2010), ISO 10845-1:2010: Construction Procurement – Part 1: Processes, Methods and Procedures.
ISO, Geneva.
Koushki, P.A., Rashid, K. and Kartam, N. (2005), “Delays and cost increases in the construction of
private residential projects in Kuwait Constr”, Management Economics, Vol. 23, pp. 285-294.
Laryea, S. (2017), “Impact of tendering procedure on price formation in construction contracts: case study
of the competitive negotiation procedure”, in Laryea, S. and Ibem, E. (Eds), Procs 7th West Africa
Built Environment Research (WABER) Conference, 16-18 August, Accra, Ghana, pp. 853-869.
Laryea, S. and Murray, A. (2017), “Tendering and administering activity schedule-based NEC3
contracts”, Civil Engineering, Vol. 25 No. 1, pp. 43-48.
Laryea, S. and Watermeyer, R. (2014), “Innovative construction procurement at Wits University”,
Proceedings of the ICE - Management, Procurement and Law, Vol. 167 No. 5, pp. 220-231.
Laryea, S. and Watermeyer, R. (2016), “Early contractor involvement in framework contracts”, Proceedings
of the Institution of Civil Engineers – Management, Procurement and Law, Vol. 169 No. 1, pp. 4-16.
Laryea, S. and Watermeyer, R. (2018), “Comparison of two infrastructure project implementation models
in a developing country”, Proceedings of the Institution of Civil Engineers – Management,
Procurement and Law, Vol. 171 No. 1, pp. 3-17, available at: https://doi.org/10.1680/jmapl.16.00029
Lee, J.K. (2008), “Cost overrun and cause in Korean social overhead capital projects: roads, rails,
airports, and ports”, Journal of Urban Planning and Development, Vol. 134, pp. 59-62.
ECAM Love, P. and Ahiaga-Dagbui, D. (2018), “Debunking fake news in a post-truth era: the plausible untruths
26,9 of cost underestimation in transport infrastructure projects”, Transportation Research Part A:
Policy and Practice, Vol. 113, pp. 357-368, available at: https://doi.org/10.1016/j.tra.2018.04.019
Love, P.E.D., Wang, X., Sing, C. and Tiong, R.L.K. (2012), “Determining the probability of project cost
overruns”, Journal of Construction Engineering Management, Vol. 139, pp. 321-330.
Memon, A.H., Rahman, I.R., Abdullah, M.R. and Azis, A.A.A. (2010), “Factors affecting construction cost
2082 performance in project management projects perspective of project management consultant”,
International Journal of Sustainable Construction Engineering Technology, Vol. 1, pp. 30-35.
Memon, A.H., Rahman, I.R., Asmi, A. and Azis, A.A.A. (2011), “Preliminary study on causative factors
leading to construction cost overrun”, International Journal of Sustainable Construction
Engineering Technology, Vol. 2, pp. 57-71.
Mintzberg, H. (1973), The Nature of Managerial Work, Harper and Row, New York, NY.
Naoum, S.G. (1994), “Critical analysis of time and cost of management and traditional contracts”,
Journal of Construction Engineering and Management ASCE, Vol. 120 No. 4,
pp. 687-705, doi: 10.1061/(ASCE)0733-9364 (1994)120:4(687).
New Universities Project Management Team (NUPMT) (2018), “Close out report of the new universities
project management team on the development of new universities in Mpumalanga and the Northern
Cape”, 1 November 2011–31 July 2017, available at: www.wits.ac.za/ipdm/guides/close-out-report/
Nkado, R.N. (2010), “Cost escalation of major infrastructure projects: a case study of Soccer City
Stadium in Johannesburg”, in Laryea, S., Leiringer, R. and Hughes, W. (Eds), Proceedings of West
Africa Built Environment Research (WABER) Conference, Accra, Ghana, WABER Conference/
University of Reading, Reading, pp. 265-270.
OGC (2003), Procurement and Contract Strategies: Achieving Excellence in Construction Procurement
Guide 6, OGC, Norwich.
Pourrostam, T. and Ismail, A. (2011), “Significant factors causing and effects of delay in Iranian
construction projects”, Australian Journal of Basic and Applied Sciences, Vol. 5 No. 7, pp. 450-456.
Public Protector (2014), “Secure in comfort, report on an investigation into allegations of impropriety
and unethical conduct relating to the installation and implementation of security measures by
the Department of Public Works at and in respect of the private residence of President Jacob
Zuma at Nkandla in the KwaZulu-Natal province”, Report No: 25 2013/2014, March 2014, ISBN:
978-1-920692-15-5, Pretoria, available at: www.publicprotector.org
Rajan, T.A., Gopinath, G. and Behera, M. (2014), “PPPs and project overruns: evidence from road
projects in India”, Journal of Construction Engineering and Management, Vol. 140, pp. 1-10.
Saunders, M., Lewis, P. and Thornhill, A. (2016), Research Methods for Business Students, ISBN:
9781292016627, Pearson Education.
Shehu, Z., Endut, I.R., Akintoye, A. and Holt, G.D. (2014), “Cost overrun in the Malaysian construction
industry projects: a deeper insight”, International Journal of Project Management, Vol. 32 No. 8,
pp. 1471-1480.
Shrestha, P.P., Burns, L.A. and Shields, D.R. (2013), “Magnitude of construction cost and schedule
overruns in public work projects”, Journal of Construction Engineering, Vol. 20, pp. 1-9.
Sweis, G.J., Sweis, R., Rumman, M.A., Hussein, R.A. and Dahiya, S.E. (2013), “Cost overruns in public
construction projects: the case of Jordan”, Journal of American Science, Vol. 9 No. 7, pp. 134-141.
Thomas, D.P. (2013), “The Gautrain project in South Africa: a cautionary tale”, Journal of
Contemporary African Studies, Vol. 31 No. 1, pp. 77-94, doi: 10.1080/02589001.2013.747292.
Ward, S.C., Curtis, B. and Chapman, C.B. (1991), “Advantages of management contracting – critical
analysis”, Journal of Construction Engineering and Management, Vol. 117 No. 2, available at:
https://doi.org/10.1061/(ASCE)0733-9364(1991)117:2(195)
Watermeyer, R. (2012), “Changing the construction procurement culture to improve project outcomes,
keynote address: joint CIB W070, W092 and TG72 international conference on facilities
management”, Procurement Systems and Public Private Partnerships, Cape Town, 23-25 January.
Watermeyer, R. (2018), Client Guide for Improving Infrastructure Project Outcomes, Johannesburg: New
School of Construction Economics and Management and Engineers Against Poverty, 1st ed., universities
April, ISBN: 978-0-620-79292-9, School of Construction Economics and Management,
Wits University, Johannesburg. project in
Watermeyer, R.B. (2012), “A framework for developing construction procurement strategy”, South Africa
Proceedings of the Institution of Civil Engineers – Management, Procurement and Law,
Vol. 165 No. 4, pp. 223-237, available at: http://dx.doi.org/10.1680/mpal.11.00014
World Bank (2016), Project Procurement Strategy for Development, Long Form Detailed Guidance,
2083
1st ed., The World Bank, Washington, DC, available at: www.worldbank.org
Further reading
Abd El-Razek, M., Bassioni, H. and Mobarak, A. (2008), “Causes of delay in building construction projects
in Egypt”, Journal of Construction Engineering and Management, Vol. 134 No. 11, pp. 831-841.
Barnes, M. (2000), “Civil engineering management in the new millennium”, Proceedings of ICE, Civil
Engineering I38, pp. 73-78, Paper I 2 IO9.
Gill, J. and Johnson, P. (2010), Research Methods for Managers, 4th ed., Sage, London.
Guest, G., Namey, E.E. and Mitchell, M.L. (2013), Collecting Qualitative Data: A Field Manual for Applied
Research, Chapter 3, Participant Observation, Sage, London.
Hasanzadeh, S.M., Hosseinalipour, M. and Hafezi, M.R. (2014), “Collaborative procurement in
construction projects performance measures, case study: partnering in Iranian construction
industry”, Procedia – Social and Behavioral Sciences, Vol. 119, 19 March, pp. 811-818.
Joint Building Contracts Committee (2005), Principal Building Agreement, 4th ed., JBCC, Johannesburg.
Rahman, I.A., Memon, A.H. and Karim, A.T.A. (2013), “Significant factors causing cost overruns in
large construction projects in Malaysia”, Journal of Applied Science, Vol. 13, pp. 286-293.
Saunders, M., Lewis, P. and Thornhill, A. (2012), Research Methods for Business Students, 6th ed.,
Pearson, Harlow.
The New Engineering Contract (1993), “Done in the interview transcripts Table”, Thomas Telford Ltd,
London.
Corresponding author
Samuel Laryea can be contacted at: samuel.laryea@wits.ac.za
For instructions on how to order reprints of this article, please visit our website:
www.emeraldgrouppublishing.com/licensing/reprints.htm
Or contact us for further details: permissions@emeraldinsight.com