S.no Description Unit Quantity Price Amount
1 Open Excavation m3 1750.0 432 756000
2 Open Excavation in Rock m3 350.0 610 213500
3 100mm thick PCC M10 m3 10.0 7179 71790
4 Concrete M25 m3 300.0 12126 3637800
5 Concrete M30 m3 10.0 14780 147800
6 Reinforcement steel MT 25.0 90876 2271900
7 Random backfill m3 1930.0 1500 2895000
8 Stone pitching m3 5.0 1600 8000
9 Non-Embedded metal works MT 1.0 123500 123500
10 water stop 230mm RM 27.0 8670 234090
11 Pebble flushing pipe 1000mm dia RM 230.0 7500 1725000
12 Dewatering Kwh
68
TOTAL 12084380
Feeder Tunnel
Total length of Feeder Tunnel mtrs. 476
Class Class II Class III Class IV Class V
Class Percentage in Tunnel 10% 40% 40% 10%
Tunnel Length (Class wise) 47.60 190.40 190.40 47.60
Note:
1. Steel is Excluding in Precast lagging & Concrete lining; cost of steel shall be paid
extra.
2. Shuttering and DE shuttering work is not mentioned in the boq it shall be charged
extra.
3. All rates are excluding GST which shall be paid extra on total billed amount.