WEEKLY SITE VISIT

TANK CLEANING
OF
FPSO FRONT PUFFIN,
WEST AFRICA EXPLORATION AND PRODUCTION COMPANY LIMITED

Date & 06th June., 2023


Subject: WEEKLY PROGRESS REVIEW
Time: 9:00 – 3:30 hours
FPSO FRONT PUFFIN
Notes Engr. Mathias
Minute No: 05 Venue SHI-MCI YARD,
LADOL-TAKWA-BAY Taken by: Onosemuode

Attendees: Distribution
WAEP SESL SWDA All Attendees
1. Mathias Onosemuode (CM) 1. Izontimi Timi (PM) 1. Miracle (Project Engineer)
2. Stephen Ogundele (HSE Lead) 2. Ndenwa Victor (PE)
3. Kehinde Mustapha (Production Engineer) 3. Shehu Ringim (Trainee)
4. Oluwabusola Sipeolu (Trainee) 4. Clarence Ataha (Prod. Supt)
5. Tamunosini Daniel (Trainee)
6. Vikran Singu

Regrets
Nil

Agenda:
1. Work through of the FPSO accommodation and production facilities
2. Inspection of tank cleaning equipment and personnell
3. Progress review for tank cleaning operations
4. HSE review for tank cleaning operations
5. Status report on NORM

WAEP SESL SWDA

Reviewed and Approved By: Reviewed and Approved By: Reviewed and Approved By:

Name: Mr Gibson Lawrence Name: Huang Jian bo

Page 1 of 2
WEEKLY SITE MEETING
AG, UG SHOP FABRICATION
FOR
MHC, MS-BLOCK AND RFCC,
DANGOTE REFINERY AND PETROCHEMICAL PROJECT

Ref Description Action Party Target


Date

1.0 Objective:
To improve productivity, quality and material availability. Info

2.0 Highlights of Discussions:

➢ Current Work Front to be updated to reflect recently issued MIVs CC-7 30/10/2019

➢ Any list of shortage materials to be sent to Mathias for a follow-up CC-7 30/10/2019

➢ 32 Tie-in spools to be check if fabricated and ready for installation. CC-7, DORC 30/10/2019

➢ Numbers of welders to be increase to 15 no. for shop fabrication, and 6 CC-7 A.S.A.P
no. for field fabrication