TSE Network for Green Riyadh Program - Group 3

ITP NO. APPROVED DATE


INSPECTION & TEST PLAN FOR GROUNDING AND BOUNDING OF ELECTRICAL SYSTEM.
PROJECT TITLE & NUMBER: TYPE OF ITP CONTRACTOR/SUBCONTRACTOR:

GROUP THREE & 12021-G3 Vendor Fabrication Shop Site AL - SAYEGH

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & SPECIFICATION/ ACCEPTANCE QUALITY ASSIGNMENTS
TASK / ACTIVITY FREQUENCY Remarks
NO. ACTIVITY CODE DRAWING CRITERIA RECORD SUB THIRD CONSULTANT
CONTRACTOR
CONT. PARTY /CLIENT
DOCUMENT
1.0
REVIEW

1.1 Work Permit N/A N/A N/A N/A N/A N/A H N/A R

GROUNDING AND BONDING FOR


ITP for Grounding & ELECTRICAL SYSTEMS (26 05
1.2 REVIEW 26) / TSE-00-3-PM-1600-FKEC-D-
Bounding EL-GEA-00001 / TSE-00-3-PM-
1600-FKEC-D-EL-DRW-00002

MOS for Grounding


1.3 REVIEW
& Bounding

Material
1.4 Submittal/specificatio REVIEW
ns

1.5 FAT Report REVIEW

1.6 IFC/Shop Drawings REVIEW

2.0 EXECUTION

2.1

3.0 TESTS

3.1

PRE-
4.0
COMMISSIONING

4.1

GENERAL NOTES
The five Inspection or testing activity listed require 100 % participation by Consultant/Client. After this period, Consultant/Client may adjust the levels of Consultant/Client participation based upon the Contractor’s
1
performance.
2 Surveillance: Client representative to monitor work in progress without notice from Construction Organization

3 Witness: Client representative shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC client representative is not present.

4 Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC client representative in attendance.

LEGEND
H 100% Hold Point for QC Inspection or Test R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection/Test
TSE Network for Green Riyadh
Program Group XX
INSPECTION CHECKLIST Checklist Number Date Approved Discipline

Project Title/Number WIR Number ITP Number

Area Location Equipment Number

Layout Drawing No Activity Number EC / PMCC / MCC NO.

ITEM
Check Points Pass Fail N/A Remarks
No.

A1

A2

A3

A4

A5

A6

A7

A8

REMARKS:

Signature Register Sub-Cont. XXX Consturction XXX QC Consultant/RCRC

Name
Signature

Date