Professional Documents
Culture Documents
G3 Project Cost Managment Group Assiment
G3 Project Cost Managment Group Assiment
June, 2023
Table of Contents
1. Project Overview............................................................................................................................1
2. Cost Planning.................................................................................................................................5
3. Cost Management...........................................................................................................................5
3. Reference......................................................................................................................................12
i
ii
1. Project Overview
The project owner Muger Cement Factory is located about 90kms North West of the capital city.
The factory has three production lines with production capacity of 5000 tons of clinker per day.
The first, second and third lines started operation in 1984, 1990 and 2011 respectively.
The (HFO to Coal Conversion Project) contract agreement made between Chemical Industries
Corporation Mugher Cement Factory and the contractor, CNBM International Engineering Co.,
Ltd, subsidiaries of China National Building Materials & Equipment Import & Export Co., Ltd,
with the total cost of USD 38,357,963 by 12th Jan, 2014.
The project was expected to be completed within 13 months but after 16 months delay it was
commissioned in November 2016 .
The main expenditure of the Factory is energy expense for HFO (Heavy Furnace Oil). It is about
60% of the production cost. Except Mugher cement enterprise all other similar factories were using
coal as their energy source for calcination.
The project objective is to convert energy consumption of HFO to Coal and to reduce the
production cost by more than 40%. The project is realized as per objective was set.
The Project was had its Master Schedule that can be used to manage Time, Cost and Scope of the project.
The purpose of project cost management plan is to measure Cost and time by looking the variance seen
between what is set and what actually is. The effectiveness of the project will be looked based on the
actual time consumed, the total cost at the end of the project and whether the project meets its
target or not. MCF was planned to complete the project in cost of USD 38,357,963 within 13 months.
But completed, after 29 months.
Accrual accounting involves tracking income and expenses as they are incurred (when an invoice is
present or a bill (Payment Request) received) instead of when money actually changes hands.
1
1.3 Project Scope
Scope refers to the quality and quantity of project deliverables specific to a particular project. In this
project the Contractor CNBM sells, erects and commissions and the Owner takes over after final
acceptance a Coal Handling, Storage (30+20=50t),Grinding System(30t/hr) and Conveying System to
convey coal as fuel for the three existing operating lines at MCF , on turnkey basis (Design, Supply,
Construction, Erection, Commissioning and Training ) to be installed at Mugher Cement Plant.
Fig1. HFO to Coal Conversion Project with first, second and third production line
2
Remark:
FOB means Free On Board and is when the seller (Contractor) takes care of all shipping documentation
and delivers the goods to the ship. Once aboard, the transportation risk passes from the seller to the buyer.
The buyer then pay for the freight to get to its destination, but the seller pays for the export customs
clearance.
Cost planning and cost management (Control) is the estimation of costs, the setting of an
agreed budget, and management of actual and forecast costs against that budget.
CIC
Corporate Audit
MCF
Project Manager
TURNKEY
TURNKEY Site Supervision and Consultant
Contractor
Contractor (CNBM)
(CNBM) Monitoring Team Lead (HOLTEC
by Site Manager
Site Engineers
Coordinator
3
General Role and Responsibility of the Project Structure
Role and Responsibility of the Chemical Industry Corporation
• Approves the budget that availed by the Agreement of CBE long term loan;
• Examines and approves the plan for project implementation;
• Provides support and monitoring according to the implementation plan prepared for the implementation
of the project.
Role and Responsibility of Corporate Project and Operation Division
• Develops the overall organization of the project;
• Monitors, and supports the overall project process;
• Completes and provides the budget, manpower and other resources required for the project;
Role and Responsibility of MCF
Owner of the project,
Assist the project manager in ensuring successful implementation,
Control and evaluate the overall progress of project as per CIC decision.
Role and responsibility of project manager
• Accountability will be for the MCF;
Creating the project plan and schedule
4
Notice; A turnkey project is a delivery method in which a contractor works with a project owner under a
single contract to complete all project stages from detail engineering through construction.
Project Supervision and Monitoring Team:
Identified, constructed from different discipline (Civil, Mechanical, Electrical and Process
Engineering) and lead by the Site Manager and Project Manager,
They are responsible for contributing to the overall objectives of the project and the specific team
deliverables
Perform the project tasks and activities that have been assigned to them,
2. Cost Planning
Cost Base Line:- Approved HFO Coal conversion project budget was 38,357,963 USD. or (38,357,963
*19.27=739,157,947.01Birr
About 70% of 38,357,963 (USD 26, 551,831) is paid in foreign currency and the rest USD 11,806,132in
local currency. 11,806,132*19.27 = 227,504,163.64birr (@ starting of the project) but due to delay as
exchange rate rise to 739,157,947.01 to 951,491,196.00
Due to delay on the project MCF withhold a 5% Contract Price as a liquidated damage which is 1.5
million American Dollar. Liquidated damage is a contractually agreed upon sum of money that one party
to a contract must pay the other party if they breach the contract. This sum is intended to provide the non-
breaching party with compensation for any losses or damages they incur as a result of the breach.
5
2.3 Confirmation/Adjustment of Current Year Spending Plan
3. Cost Management
3.1 Expenditure Tracking
Expenditure tracking is a recording of all expenditures to have a clear and detailed understanding of
the budget.
MCF agreed to borrow construction material like rebar (210t) for the contractor CNBM because of
the delay on the port. CNBM replace it when the material arrived. (Notice Ethiopia is port less).
Time extension agreement for design modification (E.g increasing Concrete car parking area and
other additional works.
Cost adjustment agreement made in both side for those additional works.
All disputes resolved with mutual agreement harmoniously, that is the good side of the
project..
6
Fig 3 Project Minute on Liquidated Damage & its Settlement
7
3.3. Expenditure Reports and Metrics
951,491,196.00 617,911,674.00
951,491,196.00 612,911,674.00
8
Cumulative
Through
2016 30-Jun-16 2015
Ethiopian Birr Ethiopian Birr Ethiopian Birr
3. DEFFERED EXPINDITURE
Testing production before 137,186,984.0 137,186,984.
Commissioning 0 00
9,115,839.0
Bank charge 0 50,792,596.00 41,676,757.00
40,098,736.0
Loan Interest 0 48,177,143.00 8,078,407.00
6,378,582.0
Consultancy fees 0 11,917,039.00 5,538,457.00
1,357,792.0
Salaries and benefits 0 4,338,744.00 2,980,952.00
229,400.0
Supplies 0 943,770.00 714,370.00
316,824.0
Entertainment 0 906,279.00 589,455.00
281,537.0
Cost of tickets 0 804,454.00 522,917.00
271,656.0
Communication 0 635,281.00 362,625.00
259,494.0
Audit fee 0 319,494.00 60,000.00
71,599.0
Insurance 0 169,315.00 97,716.00
25,000.0
Miscellaneous 0 406,347.00 381,348.00
195,593,443.0
0 256,597,446.00 61,003,004.00
9
Balance at 30 June 2015
Net Transaction carried out by MCFon
behalf of the project 127,071,816.00
Additional withdrawals from the Loan
account 206,507,706.00
945,919,613.00
Actual cost of the project or actual cost work performed (ACWP) will be birr 951,491,196.00
Cost Variance (CV) = [Budgeted cost of work performed (BCWP)] – [Actual cost of work performed
(ACWP)]
CV=EV-AC
CPI =EV/AC =0.78 CPI less than 1 that shows our actual cost is greater than planned.
1. Delay of the project as a result rise exchange rate (19.27 to 24) due to agreement made.
2. Additional payment for the consultancy fee due to first amended agreement (USD 101,745) on
client side.
Schedule Variance
10
Project Schedule
The contract is signed here in Ethiopia on 12th Jan, 2014 and planned to complete by February 2015 but
The project delay over 16 months totally takes over 29 (13+16) months to complete.
1. Incompetent subcontractors that failed to deliver its obligations in due time because of inadequate
man power, resource shortage (equipment and machinery)
11
3. Late delivery of materials and equipment as result of Ethiopia shipping line and Port clearance
delay
4. Contractors occasional strikes by its employees due to delay in paying out their wages.
5. The 2016 civil unrest in the country has major contribution to the delay of the project.
Delay is one of the biggest problems often experienced on construction project sites. Delays can brings
negative effects such as increased costs, loss of productivity and revenue, even can lead to contract
termination.
Due to the delay occurred in this project (16 months), Mugher cement Factory , based on its annual HFO
consumption rate, lose 392 million birr.
From the Contractor side the consequence is very high, Additional payment to its staff, covering
additional fee to the consultant for extended period and 5% USD 1.5million about (34,500,000 million
birr ) liquidated damage payment to the client(MCF).
Certain types of delays are highly predictable (i.e. late delivery from outside sources), and should have
been factored into the schedule before project work begins.
The client should have been tolerant and consider the contractor‘s additional project duration instead of
sticking its own proposal.
The employer should allow the contractor to use any carrier to import equipment. Allowing searching and
use sea carrier fasten the importation and avoid delay due to transportation caused by ESL.
12
4. Reference
Chemical Industry Corporation(CIC). (2017). Chemical Industry Corporation Mugher Cement Factory
HFO to Coal Conversion Project Progress and Exit report.
Chemical Industry Corporation HFO to Coal Conversion Project. (2016). Independent Auditor Report and
Financial Statement.
Henok Eshetu W/Senbet. (2017). Assessment on The Effectiveness of Mugher Cement Enterprise Coal Conversion
Project
13