Professional Documents
Culture Documents
REAR SE, G+6 Mixed Use Abera Lisanu Building-Model
REAR SE, G+6 Mixed Use Abera Lisanu Building-Model
3 2 1 REVISION
M
LEVEL
CT PLC.
LA
+24.70 S
SE
LOCATION;
ROOF CEILING
+23.70 +23.70
+11.75
G+6 MIXED USE
HCB Wall Plastered and
+10.90 +10.90
Painted
HCB Wall
4 mm Clear Glass
With
Steel Framing
curtain wall Plastered and Painted +10.90
BUILDING
HCB Wall
THIRD
FLOOR LEVEL
+10.35 +10.35 +10.35 Project Status
+ 9.90 +9.80 +9.80 +9.80
New Modification As-Built
+9.20 +9.20
+8.70 +8.70
4 mm Clear Glass
+5.50 +5.50
OWNER
Plastered and Painted 4 mm Clear Glass
With
HCB Wall Steel Framing
curtain wall
SCALE.1:100 Des.Team
ZEKARIAS TESFAYE.....
Drwn.by
BEREKET BARKLIGN.....GE ARCH/0033
NOTE - Internal wall of all wet cores is cladded with 2mm ceramic to a height of 200cm.
Color and pattern of ceramic will be decided by the Architect Drawing No SCALE
- All Architectural drawings shall be seen compatible to other engineering designs
- All dimensions are in cm unless specified
like structural, electrical and sanitary. 1:100
- All accessories shall be of the best quality and to be approved by the engineer/architect!
- Dimensions shall be read from drawings and not be measured. - Door openings direction shall be as shown on floor plans.
- All doors and door window combinationsdo have a threshold of 30cm wide and
3cm thick in white Wolega marble.
- Actual measurement of door & window should be taken on site.
- All hinges, locks, springs, lashes shall be ASSA type complying to ASTM standards & approved by
10/12 AR
- Use plastic door stoppers fixed to the floor at proper location approved by the engineer. the Architect prior to fixing.