Work Order Details Report Date 7/12/24 9:20 PM


Page 1 of 3

Work Order D2-69819 Asset FRA008D21B


Scheduled Start Date 7/17/24 9:00 PM Scheduled Completion Date 7/17/24 9:15 PM
Project Number Task Number

Work Order Information


Work Order Description Auto Framing DVM Asset Description Auto Framing - DVM 1B
(V2): General
Work Order Type Preventive Released Date 7/12/24 4:37 AM
Work Order Subtype Production Maintenance Completed Date
Work Order Status Released Resequencing Operations During Execution No

Work Definition Details


Work Definition Name NA00001884: Auto Framing
DVM(V2): General
Work Definition Version 1
Work Definition Version Date 7/14/24 9:00 PM
Time Zone (UTC-04:00) Eastern Time
Work Order Details Report Date 7/12/24 9:20 PM
Page 2 of 3

Work Order D2-69819 Asset FRA008D21B


Scheduled Start Date 7/17/24 9:00 PM Scheduled Completion Date 7/17/24 9:15 PM
Project Number Task Number

Work Order Operations


Operation Operation Execution Operation Operation Allow Work Scheduled Scheduled Scheduled Actual Actual Quantity
Sequence Code Sequence Name Type Resequence Center Start Date Completion Quantity Start Date Completion
Date Date Ready Completed
10 See DCC IN_HOUSE No DMT2R 7/17/24 9:00 7/17/24 9:15 PM 1
Attachment ESOURC PM
ES

Operation Materials
Material Description Date Required Issued Open Available On Unit Of Supply Supply Sub Supply
Required Quantity Quantity Quantity Hand Measure Type Inventory Locator

60028924 PUNCH, TIP, 7/17/24 9:00 3 3 0 Each Push SHOPFLOOR


GI040-1011- PM
X0453,
GREATECH

Operation Resources
Resource Resource Type Basis Activity Job Equipment Usage Unit Of Required Issued Open Start Completion
Sequence Profile Profile Rate or Measure Quantity Quantity Quantity Date Date
Amount
1 MTC MECH Labor Variable 0.25 Hours 0.25 0.25 7/17/24 7/17/24 9:15 PM
9:00
PM

Attachments
Time Zone (UTC-04:00) Eastern Time
Work Order Details Report Date 7/12/24 9:20 PM
Page 3 of 3

Work Order D2-69819 Asset FRA008D21B


Scheduled Start Date 7/17/24 9:00 PM Scheduled Completion Date 7/17/24 9:15 PM