Introduction to Elsalam Engineering Contractors - EEC, History & current Projects

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 38

Introduction for Elsalam

Engineering Contractors ‐ EEC,


History & Current Projects
APRIL 2015
Outline
• EEC in Brief

• EEC Documents

• EEC Operations

• EEC History (Main Clients/Projects & Consultants)


• EEC History (Aerodyne HVAC Acc.)

• EEC Ongoing projects


• EEC Certificates
• Organization Chart
• Appendix ‐1 ( Policies & Procedures )
EEC in Brief
• Products & Services

• Sheet metal forming (ductwork), piping & pipelines


forming, supplying of acoustic & thermal insulations
& the corresponding claddings.
Industry HVAC – Heating
Ventilation & Air
• Onsite installations of the above mentioned conditioning
products according to the international standards Founded Cairo, Egypt (1997)
(e.g.: ASHREA, SMACNA & NFBA) and executing the Founder Eng. Sami Salem
corresponding shop‐drawings. Area Served Egypt & Saudi
Arabia
• TAB (Test & Balance) including air & water networks No. of Employees 50 (2014)

testing, adjusting & balancing. Subsidiaries Aerodyne (Duct


work Accessories
& Air Outlets)
• Ductwork accessories & air‐outlets under the
AERODYNE brand name that EEC introduced to the
market on the year 2010.
EEC Documents

Commercial registration
EEC Documents

Commercial registration
EEC Documents

Taxes Id
EEC Documents

Taxes Id
EEC Documents

Sales Taxes Registration


EEC Documents

Import Registration
EEC Operations
• Production capabilities

• Sheet metal forming/ductwork: 20 ton per month.


• Air‐outlets & ductwork accessories: 1 ton of aluminum
profiles per month.
• Onsite installations schedules/rates is done strictly
according to the projects execution plans & timeframes (i.e.:
manpower & working hours can be increased to reach
projects timeframes).

Live photo Wrapped for Aerodyne


Live Photo for EEC Installed Ductwork with Insulation
aluminium air diffusers ready for delivery
Project: Elab, Alameria gas station, Alexandria, Egypt (Petrojet)
EEC Operations
• List of Machines (Production) • List of Instruments (Test & Balance)
No. Machine Count No. Instrument Count
1 Hydraulic shear 2 Ml 1 1 Water balance meter 1
2 Mechanical shear 2 Ml 1 2 Inclined manometer 1
3 Bender machine 2 Ml 2 3 Temperature & Humidity meter 1
4 Lockformer machine 2 4 Pressure gauge 2
5 Rolling machine 1Ml 2 5 Airflow measuring hood 1
6 Beading machine 3 6 Tachometer 2
7 Standing round seam machine 1 7 Van anemometer 4
8 Steel angle manual cutter 1 8 Sound meter 1
9 Spot welding machine 2
10 Welding machine 4
11 Threading piping machine 2
12 Aluminum saw 2
13 Electrical press 2
14 Manual press 4
15 Electricity generator 86K 1
16 Electricity generator 6K 4
Note: This list only includes the heavy machines and is excluding all Example of a sheet metal bending machine Example of an air flow measuring hood
tools & hardware that is used in production & onsite installations
EEC History (Main Clients/Projects & Consultants)
• Client: Washington Group international
• Consultant: US Army Corps of Engineers
• Projects: Air conditioning and ventilation systems of the Egyptian Air
Force Facilities (e.g.: Cairo West, Cairo East, Ainshas, Abu Suair, Beni
Suif, Borg Elarab, Elkhanka, Kom Oshim & Abu Hamad air bases)
• Scope of work:
• D‐EX units supply & installation
• DDC control systems supply & installation
• Copper piping supply & installation Washington Group Int. Logo

• Exhaust fans supply & installation


• Duct work, insulations & aluminum claddings production, supply
& installation
• Duct works accessories & air outlets installation
• Test & balance
• Timeframe: 1999 to 2014
• Client: Contrack International Inc. US Army Corps of Engineers Logo
• Consultant: US Army Corps of Engineers
• Projects:
• Cairo West Military Air Base PV‐7 (Phase 1)
• Scope of work: Contrack International Inc. Logo
• Duct work, insulations & aluminum claddings production, supply & Installation
• Duct works accessories & air outlets installation
• Timeframe: 2012 to 2013
EEC History (Main Clients/Projects & Consultants)
• Client: Orascom Construction Industries ‐ OCI
• Consultant: Shaker Consultancy Group & ECG
• Projects: OCI Logo
• Ain Sukhna & Paloza Power Stations
• Nile City admin & housing tower
Raya Holding Logo
• Eastern Company (Tobacco) factory
Shaker Consultancy Group Logo
• Raya Holding headquarters building (160
Ref. ton chilled water)
• Alaa Mubarak private villa at Cairo, Egypt
(40 Ref. ton chilled water) ECG Logo
• Gizera Sheraton 433*room renovation
• Marrasi Villas PK‐13 (23*villa concealed
FCUs) (Note: Owned by Emaar Misr) Emaar Misr Logo

• National Hospital
• Scope of work:
• Copper piping supply & installation
• Chilled water networks, insulation &
aluminum claddings production, supply &
Installation
• Duct work, insulations & aluminum
claddings production, supply & Installation
Nile City & Fairmont Towers
• Timeframe: 2000 to 2008 Gezira Sheraton
Tower
EEC History (Main Clients/Projects & Consultants)
• Client: Fabricom (Axima) (Belgian contractor)
• Consultant: Orascom Construction Industries ‐ OCI
• Projects:
• Ain Sukhna & Paloza Power Stations
• Scope of work: Axima Logo Kahromika
• Duct work, insulations & aluminum claddings Logo

production & supply


• Timeframe: 2002
• Client: Kahromika – Egyptian Company for Mechanical and Electrical
Projects
• Consultant: PGESCO
• Project:
• Giza North 1500MW Power Plant.
• Scope of work:
• Duct work production, supply & Installation
• Timeframe: 2013 to 2014
Note: AinShukhna & Paloza projects are repeated under the two
clients; OCI & Axima and this is because the Production and supply
contract was with Axima and the installation contract was with OCI. Live photo for EEC installed Ductwork
Project: Giza North1500MW Power Plant, Giza, Egypt
EEC History (Main Clients/Projects & Consultants)
• Client: PetroJet
• Consultant: Engineering for The Petroleum & Process Industries ‐
Enppi
• Projects:
• UGDC Gas Station at Portsaied, Egypt (480 Ref. Ton
D‐EX)
• ELAB at Alamyria Gas Station, Alexandria, Egypt
(360 Ref. ton D‐EX, 240 Ref. ton chilled water)
• KJO Offshore control platform at Khafji, Saudi
Arabia (22 Ref. ton D‐EX) Live photos for EEC installed Ductwork
• Emethanex methanol factory at Damietta, Egypt Project: Offshore Control Room , Khafji, Saudi Arabia
(680 Ref. ton D‐EX)
• Scope of work:
• D‐EX units installation
• DDC Control systems supply & installation
• Copper piping supply & installation
• Exhaust fans supply & installation
• Duct work, insulations & aluminum claddings
production, supply & Installation
• Duct Accessories & air outlets supply & installation
Petrojet Logo & Live photos for EEC installed Ductwork
• Test & balance Project: Emethanex methanol Factory Damietta, Egypt
• Timeframe: 2003 to 2010
EEC History (Main Clients/Projects & Consultants)
• Client & Consultant: Engineering for The Petroleum & Process Industries ‐
Enppi
• Projects:
• Enppi Headquarters Air conditioning system renovations
• Obayied Gas Field at Marsa Matrouh, Egypt (250 Ref. ton D‐EX)
• GASCO project at Alexandria, Egypt (360 Ref. ton D‐EX)
• NOSPCO Gas Station at North Sinai, Egypt (430 Ref. ton D‐EX) Enppi Logo
• Offshore control platform for GUBCO Red Sea, Egypt (20 Ref. ton D‐EX)
• SODCO company Suez, Egypt (40 Ref. ton D‐EX)
• Alamal Petroleum Plant Red Sea, Egypt (220 Ref. ton D‐EX)
• Scope of work:
• HVAC Redesign
• Cooling tower, condensing water pumps, AHU & D‐EX units installation
• DDC Control Systems supply & installation
• Copper piping supply & installation
• Exhaust fans supply & installation
• Duct work, insulations & claddings production, supply & installation
• Duct Accessories & air outlets supply & installation EEC Execution Progress at GASCO Project

• Test & balance


• Timeframe: 1998 to 2009
EEC History (Main Clients/Projects & Consultants)
• Client & Consultant: Al Amal Hospital
• Project:
• Patients, operations rooms & ICU renovations & extensions
• Scope of work:
• Duct work, insulations & aluminum claddings production, supply &
Installation
Al Amal Hospital Logo
• Duct works accessories & air outlets supply & installation (Including
HEPA & laminar flow terminals)
• Test & balance Timeframe: 2013 to 2014
• Client: Besix Orascom J.V.
• Consultant: Shaker Consultancy Group
• Project: Chiller Connection Besix Logo
• Fairmont hotel 700*rooms at Nile City Complex
• Scope of work:
• Chilled water networks, insulation & aluminum
claddings production, supply & Installation
• Duct work, insulations & aluminum claddings
production, supply & Installation Pump Room Fairmont Nile City Logo
• Timeframe: 2007 to 2009
EEC History (Main Clients/Projects & Consultants)
• Client: Golden Pyramids Plaza (City Stars)
• Consultant: Shaker Consultancy Group
• Project:
• Smoke evacuation system for Intercontinental Hotel City Stars, Cairo, Egypt
• Scope of work:
• Duct work, smoke exhaust fans supply & Installation
• Timeframe: 2004
Intercontinental Cairo City Stars
• Client & Consultant: Gulf Egypt for Hotels & Tourism ‐ GEHT
• Projects:
• Modifications & HVAC System Extensions for Sheraton Heliopolis Hotel.
• GEHT Head Office in Cairo, Egypt (60 Ref. Ton chilled water)
• Scope of work:
• Chilled water networks, insulation & aluminum claddings production, supply & Installation
• Duct work, insulations & aluminum claddings production, supply & Installation
Sheraton Hotels & Resorts Logo
• Test & balance
• Timeframe: 1997 to 2000
• Client: Four Seasons Nile Plaza Hotel
• Consultant: Shaker Consultancy Group
• Project:
• Smoke evacuation system for Four Seasons Nile Plaza Hotel, Cairo, Egypt
• Scope of work:
Four Seasons Nile Plaza logo
• Duct work, smoke exhaust fans supply & Installation
• Timeframe: 2005
EEC History (Main Clients/Projects & Consultants)
• Client & Consultant: SAMSUNG
• Projects:
• Phase 1 & 2 of Samsung factory in beni‐suif, Egypt (The first Samsung Factory in
the Middle East region)
• Scope of work:
• Duct work, insulations & aluminum claddings production, supply & Installation Samsung Logo
• Duct works accessories & air outlets supply & installation
• Test & balance with HVAC system startup
• Timeframe: 2013 to 2014
• Client & Consultant: EDAFCO (The Egyptian sister of SAFCO of Saudi Arabia)
• Projects:
• EDAFCO Food & Dairy factory at 10th of Ramadan City, Egypt (110 Ref. ton chilled
water)
• Scope of work:
SADAFCO Logo
• Duct work, insulations & aluminum claddings production, supply & Installation
• Timeframe: 1999 to 2000
• Client ABB SUSA Inc.
• Consultant: US Army Corps of Engineers
• Projects:
• Ventilation system for a military workshop at Hikstep, Cairo, Egypt
• Scope of work:
ABB Logo
• Duct work, insulations & aluminum claddings production, supply & Installation
• Timeframe: 2001 to 2002
EEC History (Main Clients/Projects & Consultants)
• Client & Consultant: Sigma Pharmaceutical Industries
• Project:
• Sigma factory a Kwesna industrial zone, Monoffia, Egypt (220 Ref. ton D‐EX & chilled
water)
• Scope of work:
• Chilled water networks, insulation & aluminum claddings production, supply & Installation
• Duct work, insulations & aluminum claddings production, supply & Installation
• Timeframe: 2007 to 2011
• Client & Consultant: Mina Pharm Pharmaceuticals
Sigma Pharmaceutical industries Logo
• Project:
• Mina Pharm factory continues renovations
• Mina Pharm factory extension at 10th of Ramadan City, Egypt (360 Ref. ton D‐EX &
chilled water)
• Scope of work:
• Chilled water networks, insulation & aluminum claddings production, supply &
Installation Mina Pharm pharmaceuticals Logo
• Duct work, insulations & aluminum claddings production, supply & Installation
• Timeframe: 1998 to Present time (Continuous renovations)
• Client & Consultant: Egyptian Group for Pharmaceutical Industries
• Project:
• EGPI Factory at Elobour City, Cairo, Egypt
• Scope of work:
• Chilled water networks, insulation & aluminum claddings production, supply & Installation
• Duct work, insulations & aluminum claddings production, supply & Installation Egyptian Group for
Pharmaceutical Industries
• Timeframe: 2005 to 2007
EEC History (Main Clients/Projects & Consultants)
• Client & Consultant: GB Ghabour Auto
• Project:
• Hyundai factory extension (Main contractor: TC &TUS (Korean
Companies)
• Scope of work:
• Duct work, insulations & aluminum claddings production, supply
& Installation
• Timeframe: 2010 to 2011

• Client & Consultant: Bavarian Auto Group (BMW Egypt)


• Project: Live photo for EEC installed Ductwork & FF
• BMW factory paint shop air‐conditioning & ventilation System Project: Hyundai Factory, Cairo, Egypt
• Scope of work:
• Duct work, insulations & aluminum claddings production, supply
& Installation
• AHUs & exhaust fans supply & installation
• Timeframe: 2004

Live photo for EEC installed Ductwork


Bavarian Auto Group Logo GB Ghabour Auto Logo Fire Pump Project: Hyundai Factory, Cairo, Egypt
EEC History (Main Clients/Projects & Consultants)
• Client & Consultant: Embassy of the US in Cairo, Egypt
• Project:
• Modification for the HVAC systems of the embassy main building and the
staff housing buildings
• Scope of work:
• Fan coil units with hock up & ductwork supply and installation
• Duct works accessories & air outlets supply & installation
• Timeframe: 2002 to 2013 (continuous renovations)
• Client & Consultant: US Agency for International Development ‐ USAID
• Project:
Embassy of the US Logo
• Modification for the HVAC systems of the USAID admin. buildings and the
staff housing buildings
• Scope of work:
• Fan coil units with hock up & ductwork supply and installation
• Duct works accessories & air outlets supply & installation
• Timeframe: 2008 to 2010 US Agency for International Development

• Client & Consultant: Embassy of Canada to Egypt


• Project:
• Renovation of the embassy building Mechanical Room. (24 Ref. ton D‐EX)
• Scope of work:
• Chilled water networks, insulation & aluminum claddings production,
supply & Installation
• Duct work, insulations & aluminum claddings production, supply &
Installation Canada Flag
• Timeframe: 2005
EEC History (Aerodyne HVAC Acc.)
• Despite the recession allover the Egyptian market due to the unstable political situation since
the year 2011 Aerodyne has found its way to the reputable customers & consultants thanks to its
strategy which was based on introducing the technical and quality requirements of the market
with a highly competitive price
• Aerodyne products:
• Square & round ceiling diffusers.
• Jet diffusers.
• Linear slots diffusers.
• Swirl diffusers.
• Double & single deflection grilles.
• Linear grilles.
• Door grilles.
• Valve desk.
• Louvers.
• Round & square volume control dampers.
• Shutter Fire dampers.
• Smoke Damper.
Examples of Aerodyne Brochures Covers
• Pre‐filters.
EEC History (Aerodyne HVAC Acc.)
• Aerodyne main customers/projects:
• Nissan Auto Egypt (Nissan Motors Egypt)
• Egyptian International Pharmaceutical industry Co. ‐
EIPICO
• Elgalaa Hospital (Owned by the Egyptian Army) (Note:
Including HEPA terminals)
• Alamal Gas Station in Ras Gharib, Egypt
• Alamal Hospital (Note: Including HEPA terminals)
• Kaliob Hospital (Note: Including HEPA terminals)
• Eden Food & Beverage Complex in 6 of October city, Egypt Live photo forgrillaninAerodyne installed stainless steel
an operations room
• Elmasah Elbahary Hospital (Port Said) Project: Elgalaa Hospital, Cairo, Egypt

• British Embassy
• Samsung Complex
• Mina Farm

Live photo for Aerodyne Round Volume Live photo for Aerodyne Live photo for Aerodyne Wrapped aluminium Volume
Control Damper (Radial Damper) Square Ceiling Diffusr Control Dampers ready for delivery
EEC Ongoing projects
• The previous slides only showed a part of the extended history of EEC represented in
the main customers and this in addition to other reputable customers & projects

• The Year 2014 is full of achievements that was added to EEC resume that represented
in successfully handing over the following project:

• Cairo West Military Airbase


• Giza North 1500MW Power Plant.
• Phase 2 of Samsung factory in beni‐suif, Egypt

• And executing the following ongoing projects:

• Al Amal Hospital patients, operations rooms & ICU renovations & extensions
• Mina Pharm factory extension at 10th of Ramadan City, Egypt
• Eden Food & Beverage complex, Sheikh Zayied City, Egypt
EEC Certificates

ABCE Certificate ‐ 1
EEC Certificates

ABCE Certificate ‐ 2
EEC Certificates

BUE Certificate
EEC Certificates

Orascom & Besix Certificates


EEC Certificates

Contrack Certificate
EEC Certificates

Contrack & WO Certificates


EEC Certificates

Samsung Certificate
EEC Certificates

Kahromika & COE U.S. Certificates


Organization Chart
CHAIRMAN
ENG. SAMY SALM

MANAGING DIRECTOR
ENG. MOHAMED SAMY

ADMINISTRATION

PROJECTS
MANAGERS ESTIMATION
DEPARTMENT

ACCOUNTS
DEPARTMENT
MECHANICAL PROJECT ESTIMATION SAFETY
ENGINEERS ENGINEERS OFFICERS

ENGINEERING
DEPARTMENT

PLUMBERS DUCTMEN
PLUMBING SUPERVISORS
PIPE FITTERS AC TECHNICIANS

HVAC SUPERVISORS
WELDERS DRIVERS

Organization Chart
Address