Performance Appraisal Report (PAR) for Group A and B officers of Govt.

of Odisha
Transmission Record
_____________________________________________________________________________________________
( To be filled in by Appraisee )

Financial Year : 2023-24 (for the period from 30-AUG-2023 to 31-DEC-2023)

Name & Designation of the Officer Reported Upon SHRI AKSHAY KUMAR SAHOO

GENERAL MANAGER(CIVIL),ODISHA BRIDGE AND


CONSTRUCTION CORPORATION (OBCC)

Service and Group (A/B) to which the Officer ODISHA ENGINEERING SERVICE
belongs
Group - A
_____________________________________________________________________________________________

Details of Transmission / Movement of PAR


( To be filled in at the time of transmission by respective officer / staff)

Transmission by Transmitted to whom (Name, Designation & Address)


Appraisee
Reporting 1. SHRI PURNA CHANDRA MOHAPATRA (CHIEF ENGINEER, ODISHA BRIDGE AND
Authority CONSTRUCTION CORPORATION (OBCC))
(From:30-AUG-2023 To:31-DEC-2023)

2. SHRI JAYA KRISHNA DAS (ENGINEER IN CHIEF-CUM-MANAGING DIRECTOR,ODISHA


BRIDGE AND CONSTRUCTION CORPORATION (OBCC),null)
(From:30-AUG-2023 To:31-DEC-2023)
Reviewing 1. SHRI JAYA KRISHNA DAS (ENGINEER IN CHIEF-CUM-MANAGING DIRECTOR,ODISHA
Authority BRIDGE AND CONSTRUCTION CORPORATION (OBCC),null)
(From:30-AUG-2023 To:31-DEC-2023)
Accepting 1. SHRI VIR VIKRAM YADAV (PRINCIPAL SECRETARY, WORKS
Authority DEPARTMENT,GOVERNMENT OF ODISHA, ODISHA)
(From:30-SEP-2023 To:31-DEC-2023)
PERFORMANCE APPRAISAL REPORT
for
Group A and Group B Officers of Govt. of Odisha.
Report for the financial year 2023-24

( Period from 30-AUG-2023 to 31-DEC-2023 )

PERSONAL DATA
PART-I (To be filled in by the Appraisee )

1. Full Name of the Officer: SHRI AKSHAY KUMAR SAHOO

2. Date of Birth: 02-JUL-1980

3. Service to which the Officer belongs: ODISHA ENGINEERING SERVICE

4. Group to which the Officer belongs(A or B): A

5. Designation during the period of Report: GENERAL MANAGER(CIVIL),ODISHA BRIDGE AND


CONSTRUCTION CORPORATION (OBCC)

6. Office to which posted with Head Quarters: ODISHA BRIDGE AND CONSTRUCTION CORPORATION
(OBCC),Bhubaneswar

7. Period(s) of absence (on leave, training etc., Nil


if 30 days or more).Please mention date(s):

8. Name & Designation of the Reporting Authority 1. SHRI PURNA CHANDRA MOHAPATRA (CHIEF ENGINEER,
and period worked under him/her: ODISHA BRIDGE AND CONSTRUCTION CORPORATION (OBCC))
(From:30-AUG-2023 To:31-DEC-2023)

2. SHRI JAYA KRISHNA DAS (ENGINEER IN CHIEF-CUM-


MANAGING DIRECTOR,ODISHA BRIDGE AND CONSTRUCTION
CORPORATION (OBCC),null)
(From:30-AUG-2023 To:31-DEC-2023)
_______________________________________________

9. Name & Designation of the Reviewing Authority 1. SHRI JAYA KRISHNA DAS (ENGINEER IN CHIEF-CUM-
and period worked under him/her: MANAGING DIRECTOR,ODISHA BRIDGE AND CONSTRUCTION
CORPORATION (OBCC),null)
(From:30-AUG-2023 To:31-DEC-2023)
_______________________________________________

10. Name & Designation of the Accepting Authority 1. SHRI VIR VIKRAM YADAV (PRINCIPAL SECRETARY, WORKS
and period worked under him/her: DEPARTMENT,GOVERNMENT OF ODISHA, ODISHA)
(From:30-SEP-2023 To:31-DEC-2023)
_______________________________________________

SHRI AKSHAY KUMAR SAHOO


Signature of the Appraisee
PART-II SELF-APPRAISAL
(To be filled in by the Appraisee )

1. Brief description of duties/tasks entrusted.(in about 200 words)

_____________________________________________________________________________________________
2. Physical / Financial Targets & Achievements
_____________________________________________________________________________________________
SL. Task Target Achievement Qualitative % of % of Achievement
No Achievement
1 Execution of Turnkey Worked in Major activities of 100 100
Contracts - Nilamadhab accordance with ChandanPond,
Kantilo Temple Development Turnkey Contract - Temple Garden ,
Complex Reviewed Project Temple Khandolite
components, , Toilet blocks, Lift
Drawings issued Lobby portion
for execution ,
Visited Sites more
than 7 times during
4 months tenure
,monitored Civil,
MEP works of
Contractor and
Consultants . Paid
4th and 5th RA Bill
after
recommendations
by the Engineer .
2 Execution of Turnkey Worked in Efforts given in 100 100
Contracts - Ugratara Temple accordance with conductance of
Development Complex Turnkey Contract - Survey and
Reviewed Project Planning Works ,
components, Geotechnical
Architectural exploration
Drawings Visited Clearance / NOC
Sites more than 4
times during 4
months tenure
,monitored site
clearance and
topographical
survey works of
Contractor and
Consultants
.Coordinate with
District
Administration for
clearance from
State Endowment
Commission.
3 Ekamra Kshetra Proposed Land Retaining Wall and 100 100
Development Project schedule in Road Works
consultation with started at
BMC , Coordinated Kotiteerth-
with ASI, Taleswar new
Bhubaneswar Road Link, Toilet
officials towards Block Foundation
NMA Clearance for works completed at
construction within Lingaraj Plaza ,
prohibited zone, North Parking
Surveyed Drain Sand filling works
No-7 with line and levelling were
departments , accomplished
facilitating setting
up of site camp
office of Agency ,
Labour Licence
etc. Filling up of
works at North
Patrking area ,
Utility shifting ,
New road link
Taleswar-
Kotiteerth junction ,
Toilet Nlocks at
Lingaraj Plaza ,
interacted with
GAIL India, District
Administration
Officials, BMC
Officials for further
scope of works,
WATCO, TPCODL
Authorities
4 Swimming Pools -6 Nos Reviewed available During my tenure 100 100
under Turnkey Contract Design Drawings, Swimming Pools at
Scope and Niladrivihar ,
Specification , Jharsuguda,
Method of Balasore have
workmanship and been started
testing of materials physically at sites,
, Input given for Tamando was at
approval of advanced stage
Revised Payment though behind
Schedule for schedule due to
smooth fund flow delay in certain
of the work done approvals of
by the agency , drawings by
Paid 1st and 2nd Engineer and
Running Account OBCC level
Bills , Monitored
workmen engaged
by Engineer and
Contractors at site
5 Bhagabati Temple complex Reviewed and site As instructed and 100 100
development visit conducted by entrusted by
self and with Sr OBCC
CGM, CGM-II ,
EIC-cum-MD ,
OBCC for feasible
of immediate start
of works on priority
basis . Initiation
has been taken for
State Endowment
Clearance and
Land demarcation
for taking up of
construction works
.
6 Processing towards EOT and Processed EOT As entrusted 100 100
Deviation approval of application post-
Turnkey Contract facto for Dhauli
Project executed
7 Payment of Salary, Vehicle As entrusted by Satisfactorily 100 100
and Miscallaneous Supply OB&CC as
and Consultancy Bills Division Head,
salary , vehicle and
other Office
expenditure bills
have been
processed timely
for payment to the
beneficiaries for
the works /
services rendered
by them , in
observance of
Codal/ OM
Guidelines on
vogue .
Consultancy
Payment for
previously certified
works have also
been made ,
pending as
admissible after
obtaining approval
from Finance wind
of OBCC Ltd.
_____________________________________________________________________________________________
3.(i) Significant work, if any, done

(ii) Work Done For Implementation of 5TS (Transparency,Teamwork,Technology,Transformation and Time):


4. Hindrance

SHRI AKSHAY KUMAR SAHOO


Place: BHUBANESWAR PAR Submitted on: 30-JAN-2024 Signature of Appraisee