Professional Documents
Culture Documents
CHECK LISTS PREPARATION
CHECK LISTS PREPARATION
Check List :
Check List :
1. Consultant’s approved drawings / specifications for materials and pumps / work order.
2. Ensure the provision of valve and NRV, PRV
3. Position of delivery pipes, air vent pipes, over flow pipes, wash out drain pipes.
4. Joining and alignment of pipes near overhead tank.
5. Installation of water pumps of required capacity its Earthing and Electrical connection.
6. If auto control system is provided, then ensure
a) Quality of the sensors of the system.
b) Display panel for water tank.
c) Cabling used for system.
d) Protection for dry run.
7. Proper clamping for pipes.
8. Adopt telescopic arrangement in down take pipe lines and check the plumb and
alignment.
9. Pressure of water to each floor.
10. Identification marks on pipes PMC / wash water supply.
PRAVINYA GUTTA
FOURTH YEAR
BUILDING DRAINAGE SYSTEM UPTO
THE VERTICAL STACK CL – 27
Check List :
1. Check sequence of waterproofing before starting work.
2. Procurement of material as per approved drawing and changes in outlet of sanitary
wares.
3. Ensure the provision for bends, branch pieces etc.
4. Ensure the verticality of the stack before joining internal branches
5. Ensure leak proof joints
6. Ensure sufficient slope to horizontal drain pipes.
7. Introduce plug socket for cleaning.
8. Ensure inspection eye provided wherever necessary.
9. Ensure the position, levels of sanitary ware from the floor levels.
10. Ensure provision of anti siphon age pipes and elongated length of vent pipe above the
roof level.
11. Clamping the pipes rigidly to maintain verticality, plumb, line level, and slopes.
12. Ensure the free flow of drainage for the desired discharge by testing all the lines.
13. Do not mix rain water outlets in to sewage or sullage drains.
14. Rain water outlets to connect to rainwater harvesting system.
Records : Consumption Statement
Check List :
SEPTIC TANK CL – 30
Check List :
1. Approved drawing
2. Invert level of incoming sewer.
3. Record initial ground level.
4. Record final excavated ground level.
5. PCC / RCC, BBM, Water-proofing to be done as per respective check list.
6. Inlet – Outlet levels of tank.
7. Free board.
8. All the documents, Size of the compartments and the baffle walls.
9. Filler media materials and filling procedure.
10. Water tightness of septic tank.
11. Vents are provided.
12. Connected effluent to sock pit or nearest drain or STP
Check List :
Check List :
COLOUR PURPOSE
Red, Yellow, Blue Phase Wires
Black Neutral
Green Earthing
Check List :
1. Civil instrument work of LT room and transformer yard based on approved layout of
M.S.E.D.C.L. and electrical inspector and detailing by Architects and RCC consultants.
2. M.S.E.D.C.L. approved layout of transformer, four pole structure, LT / HT panels,
earthing provision switchgear, feeder pillars, cable layout from transformer to meter
board including sizing.
3. Work order for transformer, LT / HT panels, switchgear, cables, steel structure, feeder
pillar and all accessories required.
4. Electrical contractors scope of work, his work order, installation schedule.
5. Approvals from M.S.E.D.C.L. and electrical inspector after erection.
6. M.S.E.D.C.L. supply from outside mains for charging transformer, testing and
commissioning of the total system.
Material Consumption
EXTERNAL ELECTRICAL GENERATOR SUPPLY CL – 34
Check List :
Check List :
1. The capacity of U.G.W.T. and O.H.W.T. with provision in that for fire fighting storage.
2. Other requirement as per municipal authorities in provisional N.O.C.
3. Authorized agency for fire fighting installation work.
4. Quality of material supplied by the contractor refers work order.
5. Civil work like excavation, making holes to the bricks, wall, concrete and refinishing of
the same is done properly as per the requirements of working agency.
6. Scaffolding fixed in such a way that no work in fire fighting is disturbed.
7. Testing done before inspection by Municipal authorities.
8. All G.I. / M.S. pipe line for straightness, level plumb, etc for perfect ness.
9. G.I. / M.S. line painted in red colour.
10. Check all required electrical connections are provided and are in working condition.
11. Check that all fire extinguishers are working and installed at proper location.
12. Fire hydrant located is easily accessible.
COLLECTION AND DISPOSAL OF DRY GARBAGE / WET GARBAGE CL - 51
Check List :
1. For 100 kg wet garbage per day (approximately half kg / family / day), construct 7
bins of size 8’ x 4’ x 2’6” (plastering is optional) over ground level along suitable part
of the compound wall.
2. Bins should be marked “Monday, Tuesday,…..” for efficient disposal.
3. Spread broken piece of bricks evenly at bottom of bins.
4. On the layer of bricks spread coconut fiber, dry leaves.
5. Instruct every flat owner to collect wet and dry garbage in separate bags or buckets.
6. Ensure that the person is appointed for collecting wastage from every house.
7. Ensure that the person collects wet and dry garbage separately.
8. Spread wet garbage inside bin (of respective day)
9. Sprinkle rock-dust on it.
10. On these layers sprinkle vermi ++ Biosanitizer (Biosanitizer is an enzyme used to
process biodegradable waste in simple and efficient manner).
11. Cover it with thin layer of garden waste.
12. Sprinkle ‘Sujala Biosanitizer’ water with a watering can evenly over entire bins. (Packet
of ‘Sujala Biosanitizer’ to be left in watering can permanently)
13. Repeat the process in the next bin for next day.
14. Spread the waste wet in every day in the respective bin only, but every day sprinkle
‘Sujala Biosanitizer’ water in all bins.
15. Ensure that the dry wastage is separate like paper and plastic for recycling and
remaining garbage dump into the PMC separate dust bin for dry garbage.
16. Ensure that the PMC container comes and collects all the wastage and dump into the
depot everyday.
17. A.M.C. may be given to approved agency.
Records : Waste Collecting Register.
Check List :
1. Ensure that OHWT capacity 10,000 liters serve for fire fighting.
2. Ensure that UGWT capacity 50,000 liters serve for fire fighting if applicable.
3. Ensure that 4” dia pipeline for each building in each one main valve & NRV at OHWT &
3 HP with back up pump is connected to the line. Hydrant valve with lugs for every
floor to attach delivery hose & branch pipe fire alarm system with control panel pill box
& siren at ground floor.
4. Ensure that the oiling to lungs assembly, Female coupling hydrant Spindles, Gate
Valves Spindle & pump checking for inner gaskets of hydrant valve & coupling.
5. Ensure that the Portable extinguisher for each building servicing fire extinguisher
quarterly done and yearly refilling and demonstration before refilling.
6. Ensure that Fire Drill System is done quarterly.