5-2.Monthly Itemized Fund Execution Plan 월별 항목별 자금집행계획서 (1)
5-2.Monthly Itemized Fund Execution Plan 월별 항목별 자금집행계획서 (1)
Contract Progress
Monthly Execution Amount (Draft) Total Payout
No. Description Amount Period Remarks
(USD)
(USD) (Months) 1 2 3 4 5 6 7 8 9 10 11 12
1 Land Purchase 토지구매 2,518,200 2,518,200 2,518,200
3-1 Architecture(general)+Civil Work 건축(일반)+토목 5,928,978 6 1,185,796 790,530 790,530 790,530 790,530 790,530 790,532 5,928,978
3-2 Factory-Steel Structure (QEB) 공장 철구조물(QEB) 813,541 3 244,062 325,416 244,062 813,541
C
3-5 EPS Molding M/C 1,335,815 3 667,908 534,326 133,582 1,335,815
3-7 Roll Forming M/C(Zinc Plate) 526,154 1 263,077 210,462 52,615 526,154
3-9 Roll Forming M/C(Deck Plate) 544,615 1 272,308 217,846 54,462 544,615
En
3-12 C-Channel 100x50x2.0T 276,923 1 138,462 110,769 27,692 276,923
3-15 Wood Board & Composited Panel 850,000 2 425,000 425,000 850,000
9
Completion Ceremony 준공식
Mass production of building materials and construction work in
progress 건축자재 양산 및 건설업 진행
합계
2,184,534
33,097,128
12
H 182,044
2,950,244
182,044
7,455,343
182,044
972,574
182,044
2,885,189
182,044
3,355,765
182,044
2,441,628
182,044
4,333,331
182,044
4,633,991
182,044
1,345,782
182,044
2,190,910
182,044
350,320
182,049
182,049
0
2,184,534
33,097,128
M
The monthly execution amount is (월별 집행 금액은)
* January + February amount: US$ 10,405,588 - Used as land purchase amount, down payment for construction and machinery manufacturing companies.
* March + August amount: US$ 18,622,479 - Used for construction and machine manufacturing companies' intermediate payments and balances, packaging, transportation, transportation costs, machine installation, test runs, labor costs for mass production preparation, and other expenses.
3월+8월 금액: US$ 18,622,479 - 공사 및 기계 제작 업체의 중도금 및 잔금, 포장, 수송, 운반비, 기계 설치, 시운전, 양산준비를 위한 인건비, 기타경비 등으로 사용.
* September + December amount: US$ 4,069,061 used for safety devices, purchase of transportation equipment, test runs, labor costs for mass production preparation, and other expenses.
9월+12월 금액: US$ 4,069,061은 안전장치, 운반장비 구입, 시운전, 양산 준비를 위한 인건비, 기타경비 등으로 사용.