TARGET DAILY SISA PEKERJAAN INSTALASI MEKANIKAL KONSTRUKSI

Durasi 13-19
NO ITEM PEKERJAAN
(Hari) 13 14 15 16 17 18
MECHANICAL STRUCTURE
1 Conveyor
CV01_JIS750x 31ML 2
CV01A_JIS750x 14ML 2
CV02_JIS900x 10ML 1
CV03_JIS900x 42ML 6
CV04_JIS1050x 43ML 3
CV05_JIS600x 14ML 5
CV06_JIS600x 34ML 5
CV07_JIS1200x 23ML 2
CV08A_JIS600x 20ML 3
CV08B_JIS600x 20ML 3
CV08C_JIS750x 21ML 3
CV09_JIS600x 22ML 3
CV10_JIS600x 24ML 3
CV11_JIS750x 25ML 3
CV12_JIS750x 50ML 2
CV13_JIS900x 9ML 2
CV14_JIS900x 43ML 2
CV15_JIS600x 30ML 4
CV16_JIS600x 30ML 4
CV17_JIS600x 24ML 3
CV18_JIS600x 15ML 3
2 Cone NH.600 & NH.40 2
3 Screen :
BMI_706 Screen 3YK 3
BMI_707 Screen AD3 3
BMI_715_CTS.1024 Ma 5
4 Vacum Filter & Dewatering :
BMI_716 Vacum Filte 4
BMI_717 Dewatering 4
BMI_718 Dewatering 5
BMI_719 Slurry Pipe 5

Keterangan :
Schedule pekerjaan ini dengan catatan :
1. Alat bantu kerja (Alat Berat) mencukupi, sesuai dengan yang dibutuhkan dilapangan
2. Kondisi cuaca mendukung untuk bekerja
20-26 27-31
19 20 21 22 23 24 25 26 27 28
27-31
29 30 31