Professional Documents
Culture Documents
ALBERT ONYANGO OWINO'S PROJECT
ALBERT ONYANGO OWINO'S PROJECT
7371010458
1
Contents
DECLARATION ............................................................................................................................................... 3
DEDICATION .................................................................................................................................................. 4
ACKNOWLEDGEMENT ................................................................................................................................... 5
ABSTRACT...................................................................................................................................................... 6
CHAPTER ONE ........................................................................................................................................... 9
SURVEYING AND SOIL INVESTIGATION ......................................................................................................... 9
CHAPTER 2 .............................................................................................................................................. 15
BUILDING TECHNOLOGY ............................................................................................................................. 15
Task 3: Schedules .................................................................................................................................... 20
Door schedule And Window schedule ................................................................................................ 20
CHAPTER 3 .............................................................................................................................................. 21
STRUCTURES ............................................................................................................................................... 21
CHAPTER FOUR ....................................................................................................................................... 24
MEASUREMENT ESTIMATION AND COSTING ............................................................................................. 24
ESTIMATION AND COSTING.............................................................................................................. 37
CHAPTER FIVE ......................................................................................................................................... 44
MANAGEMENT............................................................................................................................................ 44
2
DECLARATION
STUDENT
I Albert onyango, I declare that this project is the work of my own hand
and hasn't been presented to the Kenya National Examination Council
for any award.
7371010458
Sign....................................
Date....................................
SUPERVISOR
I declare that the work done by the candidate was done under my
supervision.
DESIGNITION........................................................
Sign........................
Date...........................
3
DEDICATION
My dedication goes to the Almighty God for giving me the gift of life
and wisdom to do my own work with much confidence. Second
dedication goes to my supervisor who took his time to help me succeed
this far.
4
ACKNOWLEDGEMENT
I give my sincere gratitude's to my project supervisor Mr. Tom Ondiek for his tireless efforts and
guidance during the preparation of this project. I would also like to acknowledge my friends, relatives
who supported me and eventually,it's a pleasure to thank the entire Ramogi Institute of Advanced
Technology fraternity for offering a cool environment for this work to reach at the end and also financial
institutions none other than National Bank of Kenya for more support.
5
ABSTRACT
It was proposed that at Ramogi Institute of Advanced Technology,a modern men’s hostel should be
constructed, this is due to the rising number of trainees being admitted yearly in the facility. The
completion and execution of the entire project will depend on how all the finance team members of
Ramogi Institute of Advanced Technology administration in collaboration with with the county
government of Kisumu and how issues will be managed during the process of construction.
The project comprises of one framed structure a two-storey building that will follow the American
standard is aimed to create more rooms for students. The project construction will be based on the
knowledge from chapters like structures, survey, measurements, estimation and costing, management
and building drawing.
SOIL SAMPLE
Soil samples were taken from the chosen marked place for the site and taken to the lab to determine
the soil moisture content and its ability to hold the structure. Soil sample was done through proctor test
for soil and also a CBR test was done, these tests were done at ministry of transport and infrastructure
in Kisumu public works.
6
building plan to give the builder project owners and trade works a sense of how the entire project will
look like on completion.
STRUCTURAL DRAWINGS
This shows the plan and details for how a building or structure will be built. After all the drawings are
done, structural calculations of members are done to ensure safety.
Economical and efficiency are considered hence structural drawings are presented. From here is where
various laboratory tests of the building materials are confirmed before the work
Commences, soil test, concrete test and slump test among other tests structural drawing helps to check
whether the structure is safe for construction.
SPREED SHEET
A strict structural calculations, analysis and assumptions for columns, beam, slab, and staircase were
conducted to establish if the ground and the building will be able to with stand live load, dead load and
natural calamities.
7
ESTIMATION AND COSTING
Estimation, costs and measurements were carried out to establish suitable capital that the project will
require. The estimates are done lined with the market rate to avoid the project inconvenience.
Measurement involves the transformation of drawn information into description and quantities to be
undertake.
MANAGEMENT
Project management helps every part of the business to run smoothly and efficiently.
Since it’s a big project different peroneal i.e. Architecture, surveyors (land and quantity), contractors,
foreman, casual labourers prepared an organization chart identify the site personnel and cutting their
daily responsibilities and weekly duties and also the activities of the project to identify the critical path.
This helps in time managing and ensuring projects succeed through proper planning, monitoring and
controlling.
OBJECTIVES
The main objective of the project to build a modern hostel that will fit and meet the needs of the
students. Since its modern some few features were including such as gym, assembly hall, and study area.
Also is to provide more space and rooms for future trainees to enable them feel comfortable due to the
building conducive environment also to create a good learning environment.
CONCLUSION
I decided to choose this field of building construction to be part of my area of study in order to be able
to meet the needs of clients in the society, economically and efficiently in order to do away with the
frequent cases of disasters for example by eliminating all problems that have been affecting the
construction industry, like the collapse of already build structures due to improper management and
Negligence.
8
CHAPTER ONE
it saw found that the nature of the site comprises of vegetation of small trees, shrubs, grass and
rocks.
TOOLS USED
Ranging rod -Alignment points on the same line on the straight line
Field book -Data was recorded obtained from the readings on site
Tripod stand- Used for entering the instrument of correct and convenient height
Theodolite- Readings were taken at different levels on site
The instrument to be used will be a dumpy level, since adjustments can be made as per the
required type of ground, it’s easy to use, has a high optical power and the level readings are
accurate.
9
LEVEL TRANSFER FROM TEMPORARY BENCHMARK TO PERMANENT
RISE AND FALL METHOD
B. S I.S F. S RISE FALL RL
2.220 18.60
10
SOIL MATERIAL
Soil is the layer of the land/ground that is unconsolidated which consists of organic matter, water,
air, materials, and red rocks. Soil material are tested to determine their nature, this include
shrinkage test, plastic limit test, sieve analysis
For foundation; shear test, oedometer, particle cell and USC (for rocks) strength was carried out.
SOIL TEST
. This is done by digging out a simple within the marked are for construction work. The taken to
the lab for testing. It was archive through proctor test for soil. And also, The C.B.R test.
The soil was sampled through a sieve of 20mm, the sampled soil was then divided I to four parts
to get the finer contest of the soil. The remain sample on the sieve was not to pass 5% of the total
sample.
The collected sample was done by 2.5kg o the weighing machine. After weighing soil sampling
was done by use of cube of 950mm (American unit). While the soil is mixed water is added until
wet then added in the mould in 3layes while compacting each layer with 25strikes by use of steel
hammer of 4.5kg
11
Soil sample analysis
12
13
14
CHAPTER 2
BUILDING TECHNOLOGY
Architectural drawings and designs
This are the most important aspect for the project, the drawings are done through computers
installed with drawing softwires (AutoCAD and ArchiCAD) using a suitable scale that will fit
the project. 3D drawings will be produced to show how the proposed building project will look
like upon finishing. Sets off paper work are produced that establishes the legal information for
the foundation of the project. The paper work entails the building contract, detail specification
sheets, working drawings for construction and the order of building process according to each
plan and the elevation views of the whole project which gives a sense on the look of the project
Paper work; working drawings, Schedules, Plot plans, Title and Legend sheets, Foundation
15
ARCHITECTURAL DRAWINGS
GROUND FLOOR
FIRST FLOOR
16
FRONT ELEVATION
REAR ELEVATION
17
SECTION
18
RIGHT ELEVATION
LEFT ELEVATION
19
Task 3: Schedules
Door schedule And Window schedule
DOOR SCHEDULE
S NO SIZE (B X H) QTY TYPE
WINDOW SCHED
ULE
S NO SIZE (B X H) QTY TYPE
20
CHAPTER 3
STRUCTURES
Structural drawings and designs
Before the commence of the project analysations were made for the architectural drawings and a
keen structural calculation of the building done. The main purpose for the structural drawing is to
ensure safety of load bearing (both dead load and live load) capacity, efficiency and flexibility of
the building when in use. Also, some laboratory tests were carried out to ensure standard
complied; soil tests, concrete test (cube test and slump test), steel test, rock test
assumptions for the design of foundation, Columns, beams, Staircase, slab and Suspended floor
were made.
Structural drawings
21
22
23
CHAPTER FOUR
Measurement involves the transformation of drawn information into description and quantities to be
undertake.
MEASUREMENT: TAKING OFF OF SUB STRUCTURE WORKS FOR THE GRUND FLOOR/LEVEL
DROWING NO;1
24
25
26
27
28
29
30
MEASUREMENT; TAKING OFF OF SUB STRUCTURE WORKS FOR THE STAIRCASE
31
DROWING NO:2
32
33
34
35
36
ESTIMATION AND COSTING
This is the best way of determining the cost of the project to know the estimated value of the
building.
37
AMOUNT
M DESCRIPTION UNIT QTY RATE
(Kshs)
ELEMENT NO. 1
PROPOSSED
MORDER MENS
HOSTEL AT RIAT
COLLEGE
SUBSTRUCTURES
(ALL PROVISIONAL)
Excavations
Clear site of all
vegetation and
bushes, grub their
A SM 2196 30 65,880.00
roots
and burn all the
arising.
Excavate oversite
to reduce levels
average 150mm
B CM 330 250 82,500.00
deep
and cart the soil
away from site
Excavate for strip
foundation
commencing from
C CM 146 250 36,500.00
reduced
level not exceeding
1.50m deep
Excavate for
columns pits
commencing from
D CM 150 250 37,500.00
reduced level
and not exceeding
1.50m deep
Extra over for
excavation in rock.
E Disposal of CM 35 1,000 35,000.00
excavated
materials
Return fill and ram
selected excavated
F CM 61 250 15,250.00
materials around
foundations.
Remove excavated
materials from site
G as directed. CM 75 250 18,750.00
Collection 291380
38
AMOUNT
ITEM DESCRIPTION UNIT QTY RATE
(Kshs)
Planking
and water
exclusion
Allow for planking and
strutting to uphold sides
A Item 3,000 3,000.00 90,000
of
excavation
Ditto but keeping all
excavations free from
running or
B Item 3,000 3,000.00 90,000
underground water by
pumping or bailing
Approved Hardcore
Approved hardcore
compacted and watered
C CM 275 1,200 330,000.00
in Layers of
150mm
50mm thick stone dust
D or murram blinding SM 275 100 27,500.00
Anti-termite Treatment
Chemical anti-termite
treatment as "Thermidor
EC 25" to
E build surfaces SM 350 120 42,000.00
THERMAL AND
MOISTURE
PROTECTION
100-gauge polythene
damp proof membrane
F under floor SM 1500 100 150,000.00
bed with 150mm side
and ends laps
Damp- proof course B.S
743, Type A, Bitumen
hessian
base Horizontal 200mm
G wide LM 250 100 25,000.00
Concrete works
Mass concrete class
10 (1:4:8) mix as
described in;
50mm thick building
H SM 162 500 81,000.00
under strip footing
Ditto column bases 500
I SM 162 81,000.00
39
ITEM DESCRIPTION UNIT QTY RATE AMOUNT (Kshs)
In-situ vibrated
reinforced concrete
(class 25/20mm
(mix 1:2: 4) as
before described
in;
Assorted Reinforcement
bars of various sizes
Mesh fabric
F reinforcement to B.S KG 100 150 15,000.00
4483 set in concrete
with 300mm
side end slabs
40
41
ITEM DESCRIPTION UNIT QTY RATE AMOUNT (Kshs)
Foundation Walling
Load bearing natural
stone walling bedded
and jointed in cement
sand (1:4) mortar
including 25mm × 20-
gauge hoop iron
reinforcement
at every alternate course
COLLECTION PAGE
B Brought forward from 291,380.00
page 1
TOTAL FOR
SUBSTRUCTURE
6,458,338.0
CARRIED TO
SUMMARY
42
ITEM DESCRIPTION QTY UNIT RATE SH CTS
FITTINGS
WINDOWS AND DOORS
Supply and fix the following ex-shop
purpose mad casement windows made
from 25mm Z and I section, complete
with all necessary iron monger.
43
CHAPTER FIVE
MANAGEMENT
In a Project, management helps every part of the business to run smoothly and efficiently.
Since it’s a big project different peroneal i.e. Architecture, surveyors (land and quantity), contractors,
foreman, casual labourers prepared an organization chart identify the site personnel and cutting their
daily responsibilities and weekly duties and also the activities of the project to identify the critical path.
This helps in time managing and ensuring projects succeed through proper planning, monitoring and
controlling.
It will also assist to know when the project is to be completed. Planning is done to ensure that the
payments of specialist, the skilled and the unskilled is met plus for the entire project
Monitoring will be done by the engineer, contractor with the help of the supervisor and the foreman
44
ORGANIZATION CHART
Critical Path
Critical Path is the sequence of activities with the longest duration, a delay in any of these
activities will result in a delay for the whole project.
This is the latest time when an activity may be finished without delaying the completion of the
project.
It is defined as the latest time when an activity may be started without delaying the completion
time of the project.
Float in activities
The float indicates the range within which the start and finish time of an activity may vary
without affecting the completion time of the project.
Total float
This is the maximum time by which an activity can be delayed without delaying the completion
time of the project.
45
Free Float
This is the difference between Early Starting Time of the succeeding activity and Earliest Finish
Time of the activity under consideration. It is the float available for a activity without affecting
the total float of the succeeding activity. It mostly based on the assumptions that all events occur
at their earliest event times
c.p =A>C>E>F>H>Y>O>Q
46
SITE PERSONELS
CLIENT
47
Assist in the exploitation construction services
Prescribe the qualification for registration under the government act
Promote and stimulate, improve and expansion of construction industry
ARCHITECT
STRUCTURAL ENGINEER
Concern with the strength and stability and economy of the project
Prepare structural working drawing for the project
QUANTITY SURVEYOR
CLERK OF WORKS
48
CONRACTOR/BUILDER
Interprets plan and ensure the construction project is done as architect requirements
Ensure all payments is done to the operatives
Handed over the key to the client upon completion of the construction project
SUPPLIER
Vendors who contract to supply the material for the project within the projectspecification and
schedule.
SUB-CONTRACTOR
Specialty contractor who contracts with the prime contractor to conduct specific portionof the
project with the overall project schedule
TECHNICIAN
OPERATIVES
Skilled and unskilled labor that carry out different duties on site i.e. plumbers,electricians,
masons, carpenters and helpers.
The HSE officer pilots and implements the company’s health, safety, and security policy on the
construction site.
BUILDER:
Builders bring the vision of the structural (civil) engineer to reality. They are in charge of physical
activities.
49
ACTIVITY
NO.
JUNE
MAR
MAR
2024
2025
MAY
MAY
SEPT
JULY
NOV
AUG
OCT
APR
APR
JUN
DEC
JAN
JAN
FEB
FEB
Electrical Engineer:
Electrical engineers create electrical designs of structures, consisting of the layout of both the electrical
PROCUREMENT OFFICER:
They are in charge of the purchase of all materials needed on site. Their priority is to effectively control
the cost of purchase of needed materials, and the timely delivery to the site so as to not slow down the
MECHANICAL ENGINEER:
They create mechanical designs of structures, consisting of the layout of the plumbing piping and fittings.
MACHINE OPERATOR:
The machine operator like the name implies operates various machinery used in construction such as
ACCOUNTANT:
They work with the management arm of the operation to oversee and monitor the remuneration of all
personnel.
STORE KEEPER:
work with the Quantity Surveyors/Auditors and oversee the use of materials, quantities which they are
50
1. Site
preparation/fencing
and signs
2. Foundations excavation
3. Footings
4. Temporary electric
installation
5. Water and sewer tap
6. Blinding and column
bases
7. Foundation walling
8. Hardcore placing
9. Murram filing mesh,
dpm placing, anti pest
and slab sides
formwork
10. Ground floor slab
casting
11. Slab curing
12. Preparing
reinforcement and
casting of ground floor
columns
13. Ground floor walling
14. Preparing
reinforcement bars and
formwork for beams
15. Formwork for first floor
slab
16. First floor slab casting
17. Curing
18. First floor columns
(reinforcement,
formwork and casting
of columns)
19. First floor walling and
beam casting
20. Roofing
21. Fittings
22. Finishes (plastering,
rendering and painting)
construction schedule bar chart.
51
APPENDIX
ac_dimension of cross section column. g- grams
Ab average lateral area of the punching pyramid. B.S – Back Site
Af_ area of footing. BS Code – British standard code
DITTO – Above
As area of steel.
Dmin – Minimum depth
ho_-effective depth of footing EXC – Excavation
Lx_-longer length FWK – Formwork
SSW – Sown softwood
Ly-_shorter length.
SMM – Standard method of measurement
N1=mf_load transmitted by the column to the I.S – Inter site
foundation R.L – Reduced Level
F.S – Fore site
g- grams
Lx – Longer length
H.O.I – Height of instrument Ly AsT – Area of stale
– Shorter length PL – Plastic Limit
PI – Plastic index
LIST OF REFERENCES
British standard code.
CP114
Standard method for measurements.
Bibliography=2.10÷0.228=9.21<14.3, short column_ from RCD1page 46
BIBLIOGRAPHY
BS: British Standard was published September 1st 1991 by Nelson Thornes Ltd. Author of the book is
British Standards Institutions.
Construction Technique was originally published in 1981 by Stephen J. Scaysbrook. Author of the
book is Roy Chudley.
SMN: Standard Method of Measurement for building works, GHANA LIBRARY AUTHORITY
INTERNATIONAL STANDARD BOOK NUMBER (ISBN). Published by university press, KNUT kumati, ISBN
978 – 2 – 6826 – 8. Authors of the book Gabriel Nani Kwodzo Agebert.
Strength of Materials Published by Laxmi Publication Ltd 113, Golden House. BK. Bansal
52
53