Professional Documents
Culture Documents
Production of Morning Meeting Summary for 24-11-2023-1
Production of Morning Meeting Summary for 24-11-2023-1
Production of Morning Meeting Summary for 24-11-2023-1
年累计发电量
月累计发电量 Annual 发电气耗率the gas
日发电量daily Monthly 厂用电率Auxiliary power
cumulative consumption per KWH Running hours
机组 power generation generating rate Net Efficiency
power (BTU/KWh)
Date Unit capacity
generation
(MWh) (MWh) (MWh) (HHV) (LHV) MWh (%) HHV % LHV % (hh:mm)
No Content
• Activity 3.11, Sr#226 Clean the interior of the 400V circuit breaker and apply conductive paste on the terminals in PEECC 3
(Completed)
• Activity 3.11, Sr#225 Cleaning & dust removal of Batteries sets in PEECC 3.(Completed)
• PTW# 4159 Cooling Tower MCC Bus-B new transducer installed.
2 E • PTW#4159 GT-1 MCC Bus-A new transducer installed. No Observation
• HRSG-3 Ground floor 5 lights replaced of 250 W and, 4 lights replaced of 150W.
• HRSG-1 HP main steam drain MOV limit adjustment performed.
• 3.11.236 & 237: GT-1,2,3 instruments calibration for transmitters & switches; GT-2 calibration at Auxiliary compartment is in progress
• GT -03 Turbine compartment hazardous sensor 45HT-iR-5B fault is normalized
3 I No Observations
• Activity 3.11, Sr#224 Cleaning & dust removal of 02 charger in PEECC 1 to 3 .(PTW required)
• Activity 3.11, Sr#234 Activity test of GT battery
E
•3.11.236 & 237: GT-1,2,3 instruments calibration for transmitters & switches; GT-2 calibration. (Work in progress).
I
Plant Defects
No Content Reason
• HRSG-1,2,3: Bypass control valve passing (Shut down Job) (TR#6557)
• Compressor Room: Instrument & Service air comp-A&B, Suction filters choked. (Spares required)
• HRSG-1: HP Drum to Super heater sampling line leakage. (Complex Shutdown required)
• ST: Vacuum pump-A &B, heat exchanger water leakage. (Complex Shutdown required)
• ST: LP G.V control valve differential filter oil seepage. (Complex Shutdown required)
Mechanical • ST: Condenser rear side –A drain valve yoke found damaged. (Complex shutdown required) Spares/(S/D)
• ST: CEP-C, Thrust bearing lube oil level sight glass not available. (Spares required)
• Cooling Towers: CTF No.2, gear box lube oil level sight glass damaged. (Spares required)
•TR # 9756, GT01, UAT oil temperature wrong reading is showing. Winding temperature gauge BWY 804 is required
• TR # 16886, ECR, UPS 2 Alarm Short circuit @ high DC, spare required.
• TR # 16872, GT01, MW & MVAR transducer malfunctioning.
• TR # 13156, UPS output frequency not showing on DCS. Spare required.
• TR # 7066, ST Main T/F winding temperature fluctuating. Winding temperature gauge BWR 804 is required.
Electrical Spares
• TR # 3476, Bay control unit#03 device#02 display not showing reading, spare required.
• TR # 16568, GT Hall, Roof fan not working. Access issue.