Professional Documents
Culture Documents
Roofing the Dubai Int'l. Airport
Roofing the Dubai Int'l. Airport
By
1
INTRODUCTION
Today’s Architects are becoming aware of and using more complex double curvature
geometry in the buildings that they create.
They also are experimenting with new materials and from a Roof Designers and
Contractor’s point of view, constructing a project of the size of the Dubai International
Air Terminal is a major undertaking. For a project of this magnitude and complexity a
considerable number of professionals are involved in the disciplines of:-
• Structural Engineering
• Hydraulics
• Thermal/Condensation Control
• Acoustics
Also in remote locations the Roof Designer has to consider the quality of labour, and the
likely expertise of the construction personnel.
2
1. PREAMBLE
THE ROOF DESIGNER/CONSULTANT CHECK LIST
Before going into the details relating to the Dubai Project I would like to cover what I
regard as some of the basic concepts in roof design.
All personnel involved in the designed of roofing will no doubt have their own “check
list” which covers a wide range of considerations from which recommendations are made
and details developed. (The “check list” takes a considerable amount of time and
experience to develop and generally is based on the individuals’ experience).
In my experience there are probably 10 major areas to consider and which in many
instances are influenced by the Architect’s requirements in relation to materials,
aesthetics and performance etc.
The development of a roof design, the type of materials we use, the research and
experience we draw upon has developed over a considerable time, but primarily we all
are trying to develop a system that will provide satisfactory shelter and consider the
ultimate required performance from the structure.
The check list that I have developed from my 50 years+ in the industry generally covers
the following:-
Note that the order and importance of this review will vary from project to project.
3
1.1 Architectural Requirement
This normally has a major bearing on the aesthetics of the building and most
architects have very definite thoughts on the roofs appearance. At this stage,
although it will be considered in more detail later, the geometry (shape), of the
building and roof will obviously have an influence on further considerations
regarding material and construction.
4
Figure 2. Singapore Expo Railway Station
The roof geometry is toroid and is covered with a full welded
titanium roof sheeting (double curvature geometry)
5
Figure 4. Khalsa Heritage Complex, Punjab, India
To satisfy architectural geometry, roof sheets are both curved and
tapered.
1.2 Weatherproofness
In my opinion this should be the first consideration of any Roof Designer and this
would involve a detailed study of rainfall intensity and other items such as the
probability of hail, snow and even possibly sand build-up on the roof’s surface.
A hydraulic review is also of extreme importance and at this stage decisions are
made for such questions as:-
6
Figure 5.
7
1.3 Materials
Both the Architect and the Roof Consultant have a wealth of alternatives
available to them and a review of manufacturer’s data and application details may
cause more confusion than providing appropriate answers. For the material
review (apart from the architectural requirements) we had to consider:-
• Zinc
• Stainless steel
• Galvanised steel
• Pre-coated steel
• Aluminium
• Pre-coated aluminium
• Titanium
• Copper
• Lead
8
Figure 7. Singapore Expo Railway Station (curved & tapered titanium).
The selection, quite often, will depend on geographic availability, costing and in
remote locations, available methods of transportation.
1.4 Structural
9
selection obviously will dictate spans of sub framing and the overall structural
lay-out.
1.5 Acoustics
With the current trends to lightness of building construction and the possible use
of a building as say an Auditorium, Lecture Theatre or Classroom, sound
transmission loss through the roof system should be a major consideration for the
Designer.
Satisfactory solutions have been developed and are able to provide, within
lightweight systems, acceptable transmission loss values to satisfy the project
Acoustician’s requirements.
This aspect of the design may also influence materials as, with a sheet metal roof,
heavy rain or hail can generate very high sound levels which do not necessarily
occur with membrane type construction. (Particularly with gravel or trafficable
surfacing).
High transmission loss systems, whilst still relatively low in dead load, can have a
direct influence on the design of the structural support components.
• Panel Resonance
• Acoustic decoupling from the main structure
• Flanking Paths
The author, many years ago, held an Australian Patent for an acoustic decoupling
system. However, costs for the system were high and building owners appeared
to be prepared to take the risk.
10
It cannot be over emphasised that rain on metal deck roofing can and has
produced acoustic disasters. For example in Sydney, in a television production
building, production could not take place during heavy rain simply as a result of
the generated noise levels.
The author has spent a considerable amount of time (and money) in testing a
variety of systems, profiles and rainfall intensities and this is a complex subject
on its own.
11
Figure 9. Adelaide Convention Centre – Tested results for Sound
Transmission Loss
12
Figure 10. Typical Acoustic Roof System as used on the Adelaide Convention
Centre
13
1.6 Condensation
As with curtain walling and any cladding system (roof or walls), a condensation
review is important and quite often, depending on the external and internal
ambient conditions, double vapour barriers may be required.
In some instances it is necessary that the vapour barrier has the characteristics of
a balloon for the total building area, as minor leaks (very small holes) through the
vapour barrier (within the roof system) can render the system useless.
Most of the work that we design in the Middle East requires double vapour
barriers (external and internal face), as temperature variations are considerable
with possible ranges being:-
Ambient
14
Figure 11. Dubai International Air Terminal
Extracts of a Condensation Report
15
Figure 12. Dubai International Air Terminal
Extracts of a Condensation Report
16
1.7 Buildability
The author has had project involvement where on-site manufacture is far more
preferable to using the normal factory produced products and shipping/trucking
onto the site.
The total roof was assembled into pre-fabricated modules, each of 25ft. x 30ft.
and these were craned into position as a complete unit (weight approx 5 ton/unit).
It was not possible to factory fabricate components off-site because of the poor
condition of the road system adjacent to the airport.
Figure 13. The rear building (100,000 sq. ft) is the on-site factory at
Bangkok Airport, Thailand. This was a temporary
structure and demolished at the conclusion of the roof
production.
17
Figure 14. Chadwick’s On-site Bangkok Air Terminal Factory
Production of Sun Louvres that formed part of the roof
system.
This same system of on-site manufacturing has been used on roofing projects
including:-
18
Figure 15. Bangkok International Air Terminal, Thailand
Completed roof sections (25ft. x 30ft.) being craned into
position.
Building economists will suggest the economic life of a building and this should
have some influence on the product/materials we propose and specify. An
example of what not to do, is on an unnamed project where the architect required
titanium cladding on a building with a maximum economic life of 40 years.
Costs could have been substantially reduced and still maintain material with
acceptable durability (and appearance).
1.9 Insulation
Today, with requirements for energy conversation, greenhouse gas omissions and
other manufacturing hazards together with the physical safety of the installer we
19
have to closely review all of the characteristics of the insulation we are
recommending.
As with other materials in the roof construction, the type of insulation, quite
often, will depend on the geographic location of the manufacturing plant in
relation to the installation location.
The correct selection of insulation can also assist with certain of the previous
noted item including:-
• Condensation Control
• Sound Transmission Loss
A balance has to be made regarding the cost and likely performance requirements
for all of these items.
20
Figure 16. Rashidiya Metro Depot, Dubai
50metre length of roofing being carried from an elevated
production roll former.
(Very much an important decision in relation to buildability).
Summary
The above list is by no means complete but forms a good starting point for the review of
possible systems.
21
2. DUBAI INTERNATIONAL AIR TERMINAL
CONCOURSE II
The remainder of this paper will review the roof construction of the Dubai
International Air Terminal Concourse.
All of the general considerations previously noted received some consideration in the
development of the final system for the Dubai International Terminal. I propose to
comment on several aspects of the design, manufacture and construction.
This is a most exceptional building and is a kilometre long (.63 mile). With ancillary
facilities the total cost is approximately 4 billion US.
The building provides 26 Aircraft loading bridges (with several being capable of
handling the new A380 Air Bus) and also includes two international hotels, massive
lounges and duty free shopping together with immigration, customs and baggage
services.
22
Figure 18. Dubai International Air Terminal – Building Plan
Figure 19. Dubai International Air Terminal – Elliptical Part Cross Section
23
Figure 20. Dubai International Air Terminal – Interior at Departure Level.
The construction took over 4 years and the building became operational in October, 2008
(without any major difficulties).
The geometry of the building is also extremely unusual being partly cigar shaped with
double curvature geometry throughout and the cross section being an ellipse.
As both a Designer and Contractor the items I wish to now cover include:-
• Pricing
• Staffing
• On-Site & Off-Site production
• Building Geometry
• Roof construction Build-Up
• Design Development
• Testing
• Building Maintenance Unit
• Workforce
24
2.1.1 Pricing
Excluding minor fixing items there was probably 10 major material cost
centres involved in the construction. These included:-
Material Location
Galvanised Steel Structural Deck
Colour coated Steel Metal Roof Sheeting
EPDM Membrane Vapour Barrier/Sarking
Rockwool Insulation General Insulation
Glass reinforced Plasterboard Mass Layer – Acoustics
Extruded Aluminium External Tile Support
Composite Aluminium Panels External Cladding
Stainless Steel for Flashings & Concealed Gutters & Flashings
Trims
Secondary structural steelwork for Skylight Supports
support items.
Structural stainless steel BMU Rails
components.
Particularly with the metal components, price and supply volatility creates
a major risk factor for the Contractor on a fixed price contract.
The main part of the construction of the Dubai Concourse took place
during a very volatile construction period in Dubai. This also created a
shortage of many standard materials with subsequent price increases.
25
In pricing such a project “preliminaries” and in particular Management
and Supervisory staff are a very substantial cost. Also when considering
all of the add-ons which occur including items such as motor vehicles,
accommodation, air travel, school fees, medical insurance etc. the
Management component deserves major consideration.
2.1.2 Staffing
26
All of the senior staff including Management, Engineering, Material
Procurement, Supervision, Factory Management, were long term
employees in the roofing industry and had very acceptable CVs in relation
to airport construction having worked on projects such as:-
• Safety Officer
• Quality Assurance Officer
• Materials Handling Supervisor
• Factory Manager (on-site production was our selected alternative)
Our Design & Engineering Director, Engineers and Supervisors were also
responsible for the development of “Work Method Statements” which are
required for every activity and had to be submitted to the Client’s
representative before each section of the work could progress.
27
Figure 22 – 27. Quality Assurance (Extract)
28
Figure 23.
29
Figure 24.
30
Figure 25.
31
Figure 26.
32
Figure 27. Quality Assurance (Extract)
33
Figure 28. Safety Plan
34
Figure 29. Safety Plan
35
2.1.3 On-Site, Off-Site Production
a) Transportation
• 2 Roll-formers
• 2 Purpose built curving machines
• Brake press
• Guillotine
• General sheet metal equipment
• Welding equipment
36
structural decking (3 inches deep) and the roof sheet profile (2.5
inches rib height).
The major advantage was that product was always available on-
site and with variable length material, sizing could be transferred
directly from site to factory in a short time span.
During the course of production for the Dubai Terminal the factory
handled in excess of 1,000 ton of coiled material.
37
2.1.4 Plant & Equipment
All roofing products were craned into position using a 200 ton extended
reach cranes (mobile). As with all projects on an active airport,
considerable care had to be exercised in relation to the height and location
of the jib and also the location of on-site transport equipment on the active
side of the airport.
Crane lifts were not heavy. Reaching the correct locations was the
important requirement. Maximum weight of each lift would be no more
than 2 tons.
38
Figure 32. Crane lifting secondary components to the roof level.
Special on roof support platforms were required.
39
Figure 34. Roof profile rollforming Machine (material entry end).
40
2.1.5 Building Geometry
41
Figure 37. Shows co-ordination of the geometry and cladding.
The overall geometry was made more difficult as the tear drop shaped
skylight transoms also were required to align with the tapering
longitudinal joints in the external cladding system.
The program used for the development of the outer cladding panel size
was undertaken by a programmer with previous experience in the
development of programs for the tailoring of sailing spinnakers.
42
2.1.6 Design Development
43
A short comment will be made on each of these components in relation to design and or
function.
i) Structural Decking
The structural deck was fabricated from 1.2mm (18 gauge) thick
(galvanised) material.
44
ii) Secondary Z Spacers
iii) Insulation
45
Figure 42. Insulation being applied over the structural
deck.
46
Figure 43. The black material to the right of the skylight is the
EPDM vapour barrier.
v) Vapour Barrier
47
vi) Metal Profiled Roofing
48
The outer tiles are 6mm “composite” aluminium panels with an
external fluorocarbon coating. These panels are reinforced to
allow for foot traffic and the detail and engineering data to allow
for the reinforcement is shown in Figures 45 to 48.
This component acts as a screen and has open joints. There have
been some interesting debates in relation to wind pressure on open
screen construction (relating to what pressure should be
considered.
49
Figure 46. Engineering Calculations
50
Figure 47. Engineering Calculations
51
Figure 48. Engineering Calculations & Data
52
2.1.7 Testing
53
Figure 50. Sketch of tested Area (2)
54
Figure 52. Dubai International Air Terminal
Roof Mock-Up under construction.
55
Figure 54. Dubai International Air Terminal (Mock Up)
Note: The extent of secondary steelwork and pre-cast concrete walls.
56
Figure 56. Dubai International Air Terminal
Testing for water penetration using aircraft engine
57
Figure 58. Dubai International Air Terminal
Insulation and plasterboard mass layer visible.
58
Figure 59. CSIRO Structural, Weather, and other Performance
Tests on Performance Mock Up Unit – 1
59
Figure 60. CSIRO Structural, Weather, and other Performance
Tests on Performance Mock Up Unit – 1
60
Figure 61. CSIRO Structural, Weather, and other Performance
Tests on Performance Mock Up Unit – 1
61
Figure 62. Dubai International Air Terminal
CSIRO Structural, Weather, and other Performance Tests
on Performance Mock Up Unit – 1
62
Secondary testing was also undertaken by Factory Mutual Inc in the USA,
and they had a joint role of both a testing authority and insurance advisor
for the Dubai International Terminal.
63
Figure 65. Progressive construction of test specimen (structural
decking) – Factory Mutual, Boston, USA
64
Figure 67. Final roof sheeting being applied to test specimen –
Factory Mutual, Boston, USA
The bulk of the roof area is accessible for cleaning from a Building
Maintenance Unit (B.M.U) which runs on stainless steel rails which are
incorporated within the roof construction. Refer to Figure 68 which
shows the BMU rail construction.
65
Figure 69. BMU
Elliptical BMU rails positioned during roof
construction.
66
Figure 71. Building Maintenance Unit in position.
The spacing of the rails is approximately 9metres (30 ft.) and the BMU
spans between rails and has both on-board water and power outlets. As
can be imagined, the rails also are required to be of an elliptical shape and
with a heavy stainless steel box section (150x150x8mm) rolling the
appropriate elliptical shape required considerable innovation in
developing a variable program for roller wheel adjustment to achieve the
ellipse.
67
mid summer working day would commence at 4.00am and finish at 12
noon.
During the summer months and considering the previously stated ambient
temperature it is possible that exposed components may be 20-30 C°
hotter than the ambient condition.
Sandstorms are far more frequent than rain, and gutter and drainage
systems have to be maintained to ensure that sand build up does not
restrict water flow during the rare occasions when rain occurs.
• Engineering (Structural)
• Engineering (Mechanical – Condensation)
• Engineering (Acoustics)
68
• Engineering (Metallurgical review)
• Manufacturing
• Risk Evaluation
• Financial & Cash Flow Planning
• Documentation Preparation including:-
• Construction Expertise
• Control of heavy Plant & Equipment
• Supervision
• Workmen Quality/Training
Conclusion
Both from a design and construction viewpoint the Dubai International Air
Terminal was one of the most difficult projects that the author has been involved
with in his 50 years+ experience in the Roofing and Cladding industry.
Fortunately the overall final results are self evident, with the completion of a very
successful building.
In relation to the roof construction, this work has now received several awards
including:-
69