NOTES:

FIELD ADMIN & CONTROL ROOM BUILDING SWITCHGEAR BUILDING

GATE HOUSE - A

FENCE

LEGEND ABBREVIATIONS

GATE HOUSE - B

INTO-PLANE AREA

DUTY OFFICE

GATE HOUSE - 2
WORK STATION
REFERENCE DRAWING

INTO-PLANE AREA WAREHOUSE

SECURITY CABIN
F1 14/07/21 IFA ISSUED FOR ACKNOWLEDGE MSD JPJ PISANU R.

F0 21/06/21 IFA ISSUED FOR ACKNOWLEDGE MSD JPJ PISANU R.

SECURITY CABIN A 27/10/20 IFR ISSUED FOR REVIEW MSD JPJ PISANU R.

REV. DATE STATUS REVISION RECORD ISSUED BY CHECKED BY APPROVED BY

DESIGN OF FUEL SUPPLY PROJECT IN NPPIA CONSULTANT

COMPANY Electronic Filename


SHEET of SCALE
A1 PAPER
Comment Response Sheet (CRS)

Contract No. Owner TOTAL / CNAF / PTTOR


Project No. 20218 Prepared by PENSPEN Date 14-JUL-2021
Document Number 80-1-20218-CAM-001 Rev. No. of Commented F0 Sheet 1 of 1
Document Title OVERALL TELECOMMUNICATION SYSTEM ARCHITECTURE

Section
No. Comment Response By Date Remark
/Page
Note added: "At detailed engineering
PENSPEN 14-07-2021
stage EPC contractor to verified the
FOC from Airport Why we need to connect with the CCTV integration with Airport with Client
1 1
Airport and CAIC" as mentioned during PP &
Client meeting / discussion on 30th June
2021

Additional Notes (if any) Attachment: