Vanguard Risk and Safety Asia

Past QRA and Safety Case Project Experience (2018 - 2024)

Year Project Status Region Industry Description


2023 TPSC QRA and Safety Case Intervention Ongoing Singapore Petrochemical
QRA and Safety Case support to closeout IP/ RP items from MHD.
Plan (IP) Closeout
2023 STMicroelectronics Safety Case Completed Singapore Semiconductor
Safety Case support to closeout IP/ RP items from MHD.
Intervention Plan (IP) Closeout
2022 LTA CR3006 H&S Buffer Assessment Completed Singapore Infrastructure H&S Buffer Assessment for a major infrastructure project in Singapore to ensure societal risk is managed and kept to ALARP.

2022 Singapore Integrated Waste Management Ongoing Singapore Power Generation Safety and Risk support (HAZOP, SIL and FMEA) to Keppel for the Singapore Integrated Waste Management and Power Plant Facility (SIWMF).
Facility (SIWMF)
2021 Drew Marine QRA Completed Singapore Petrochemical Development of a QRA for a chemical production facility in accordance the Singapore QRA guidelines.

2021 AECOM GE QRA Tender Support Completed Singapore Power Generation / Oil and Development of a Preliminary QRA of a power generation facility in accordance the Singapore QRA guidelines for tender support.
Gas (Onshore)
2020 PT Cargill Project Zulu Jetty Operations Completed Singapore, Indonesia Terminalling Development of a QRA to establish a Marine Exclusion Zone for Jetty operations for PT Cargill in Indonesia.
QRA
2020 - 2021 STMicroelectronics Safety Case Completed Singapore Semiconductor Development of the Safety Case for a semiconductor facility in accordance the Singapore MHI Safety Case Regulations.

2020 BW Offshore Safety Case Support Completed Singapore, Norway Oil and Gas (Offshore) Safety Case support for BW Offshore's entire FPSO Fleet in accordance to BWO internal requirements and international regulations.

2020 MODEC Barrosa and Bacalhau Safety Case Completed Singapore, Australia, Oil and Gas (Offshore) Safety Case support for MODEC's FPSO Projects (Barrosa and Bacalhau) in accordance to MODEC internal requirements and international regulations.
Support Norway
2020 SOITEC Singapore QRA - Phase 3 Completed Singapore Semiconductor Development of a QRA for a semiconductor facility in accordance the Singapore QRA guidelines. Project carried out by current staff (Wei Liang) in other company.

2019 - 2020 Siltronic Singapore QRA and Safety Case Completed Singapore Semiconductor Development of QRA and Safety Case for a semiconductor facility in accordance the Singapore QRA and MHI Safety Case Regulations respectively. Project carried
out by current staff (Wei Liang) in other company.
2019 - 2020 Sharjah National Oil Company (SNOC) QRA Completed UAE Oil and Gas (Onshore) Development of a QRA for an LPG terminal with import / export facilities.

2019 TPSC Singapore QRA and Safety Case Completed Singapore Petrochemical Development of QRA and Safety Case for a petrochemical facility in accordance the Singapore QRA and MHI Safety Case Regulations respectively.

2019 MODEC MV24 FPSO Fire Risk Analysis Completed Brazil Oil and Gas (Offshore) Development of a FRA for MODEC's MV24 FPSO.
(FRA)
2019 Versum Materials QRA Completed Singapore Warehousing Development of a QRA for a specialty gas / chemical warehouse facility in accordance the Singapore QRA guidelines. Project carried out by current staff (Wei Liang)
in other company.
2019 SOITEC Singapore QRA - Phase 2 Completed Singapore Semiconductor Development of a QRA for a semiconductor facility in accordance the Singapore QRA guidelines. Project carried out by current staff (Wei Liang) in other company.

2019 SSMC Singapore QRA Completed Singapore Semiconductor Development of a QRA for a semiconductor facility in accordance the Singapore QRA guidelines. Project carried out by current staff (Wei Liang) in other company.

2019 INPEX Ichthys Safety Case Support Completed Australia Oil and Gas (Offshore) Safety Case support for INPEX's Ichthys FPSO.

2018 - 2019 SOITEC Singapore QRA - Phase 1 Completed Singapore Semiconductor Development of a QRA for a semiconductor facility in accordance the Singapore QRA guidelines. Project carried out by current staff (Wei Liang) in other company.

2018 - 2019 Sembcorp Industries QRA and Safety Case Completed Singapore Power Generation / Oil and Development of QRA and Safety Case for a power generation and terminalling facility located in Jurong Island in accordance the Singapore QRA and MHI Safety Case
Gas (Onshore) Regulations respectively. Project carried out by current staff (Wei Liang) in other company.
2018 - 2019 Murakami Screen Singapore QRA Completed Singapore Warehousing and Development of a QRA for a warehouse and manufacturing facility in accordance the Singapore QRA guidelines. Project carried out by current staff (Wei Liang) in
Manufacturing other company.
2018 - 2019 Horizon Terminals Singapore Safety Case Completed Singapore Oil and Gas (Onshore) Development of the Safety Case for an oil terminal facility located in Jurong Island in accordance the Singapore MHI Safety Case Regulations. Project carried out by
current staff (Wei Liang) in other company.
2018 - 2019 Huntsman Singapore Safety Case Completed Singapore Petrochemical Development of the Safety Case for a specialty petrochemical facility located in Juron Island in accordance the Singapore MHI Safety Case Regulations. Project
carried out by current staff (Wei Liang) in other company.
2018 Globalfoundries Silane Bunker QRA Completed Singapore Semiconductor Development of a QRA for a semiconductor facility in accordance the Singapore QRA guidelines. Project carried out by current staff (Wei Liang) in other company.

Project List last updated on 10/06/2024