Professional Documents
Culture Documents
2_ARC1418_Week 4 Precast Floor System and Roof Slab
2_ARC1418_Week 4 Precast Floor System and Roof Slab
2_ARC1418_Week 4 Precast Floor System and Roof Slab
BUILDING TECHNOLOGY 5
Single Tee
A precast, prestressed concrete slab
having a broad T shaped section
• 30' to 120' (9 to 36 m) span range
• Rule of thumb for depth: span/30
SINGLE TEE
(Source: DK. Ching, 2019)
Double Tee
A precast, prestressed concrete slabs
having two stems and a broad cross
section resembling the capital letters T.
• 30' to 100' (9 to 30 m) span range
• Rule of thumb for depth: span/28
• Double tees do not require
temporary support against tipping.
DOUBLE TEE
(Source: DK. Ching, 2019)
PRE-CAST FLOOR AND ROOF SLAB
Beams
• 15' to 75' (4.5 to 22 m) span range
• Rule of thumb for depth: span/15
• Use the span ranges indicated for
preliminary sizing only. Consult
manufacturer for availability of sizes,
exact dimensions, connection details,
and span-load tables.
BEAMS
(Source: DK. Ching, 2019)
AASHTO GIRDER
• American Association of State Highway and
Transportation Officials
• Designed originally for bridge structures but
used sometimes in building construction.
• 36' to 60' (10 to 18 m) span range
AASHTO GIRDER
(Source: DK. Ching, 2019)
PRE-CAST FLOOR AND ROOF SLAB
Lift Slab
• Lift-slab construction is a technique of constructing multistory buildings in which all horizontal
slabs are cast at ground level and, when cured, are raised into position by hydraulic jacks.
• Lift-slab construction, used chiefly with two-way flat plate structures, virtually eliminates formwork.
The floor and roof slabs of a building are cast in a stack on the ground. Then hydraulic jacks are used
to lift the slabs up the columns to their final elevations, where they are welded in place using special
cast-in-place steel slab collars.
Flying form
• A large form that can be
moved by a crane, used
in constructing the
concrete floors and roofs
of a multistory building.
• For floor slabs that are
cast in place, flying
formwork is fabricated in
large sections that are
supported on deep metal
trusses. The sections are
moved from one floor to
the next by crane,
eliminating much of the
labor usually expended
on stripping and re- Flying Form
(Source: E. Allen, 2009)
erecting formwork.
PRE-CAST FLOOR AND ROOF SLAB
Slip forming
• It is useful for tall- walled structures such as elevator shafts, stair wells, and storage
silos. A ring of formwork is pulled steadily upward by jacks supported on the vertical
reinforcing bars, while workers add concrete and horizontal reinforcing in a continuous
process
BUILDING TECHNOLOGY 5
References:
• Allen, E. (2009). Fundamental of building construction: materials and method 5th
edition. New Jersey: John Wiley & Sons.
• Chudley, R. (2010). Building Construction Handbook 8th Edition. USA: Elsevier.
• Ching, F. (2014). Building Construction Illustrated 5th Edition. New Jersey: John
Wiley & Sons.