Project name Assets Preservation and General Maintenance Services

Contract No. EFP-10-10200(1)(Phase 1)

Contractor: Miraj Projects Company FZE DAILY PROGRESS REPORT Date: Friday 28-06-2024

Report No. 10200-00-F-RA-1230-D28062024-B1 Weather Sunny Temp. (Max) 46 ºC (Min) 35 ºC Location Open yard- Phase 1 (SPA)

DOCUMENT NO: 10200-00-F-RA-1230-D28062024-B1

DOCUMENT TITLE: DAILY PROGRESS REPORT 28-06-2024

PROJECT TITLE: ASSETS PRESERVATION AND GENERAL MAINTENANCE SERVICES

EMPLOYER: BASRAH OIL COMPANY

CONTRACT NO.: EFP-10-10200(1) (Phase-1)

Issue Rev. Date Revision Description By Checked Approved Employer Approval

B1 05-07-2024 Issued for Approval MZ AM YH

Page 1 of 17
Project name Assets Preservation and General Maintenance Services

Contract No. EFP-10-10200(1)(Phase 1)

Contractor: Miraj Projects Company FZE DAILY PROGRESS REPORT Date: Friday 28-06-2024

Report No. 10200-00-F-RA-1230-D28062024-B1 Weather Sunny Temp. (Max) 46 ºC (Min) 35 ºC Location Open yard- Phase 1 (SPA)

TABLE OF CONTENTS

1. OPEN YARD - PHASE 1 (SPA)………………….……........…………03

2. WAREHOUSE LV-19 C & D…….............……….…....………..….…12

3. SUMMARY OF OPEN YARD & WAREHOUSE MAN-HOURS....…16

Page 2 of 17
Project name Assets Preservation and General Maintenance Services

Contract No. EFP-10-10200(1)(Phase 1)

Contractor: Miraj Projects Company FZE DAILY PROGRESS REPORT Date: Friday 28-06-2024

Report No. 10200-00-F-RA-1230-D28062024-B1 Weather Sunny Temp. (Max) 46 ºC (Min) 35 ºC Location Open yard- Phase 1 (SPA)

1. OPEN YARD - PHASE 1 (SPA)

Page 3 of 17
Project name Assets Preservation and General Maintenance Services

Contract No. EFP-10-10200(1)(Phase 1)

Contractor: Miraj Projects Company FZE DAILY PROGRESS REPORT Date: Friday 28-06-2024

Report No. 10200-00-F-RA-1230-D28062024-B1 Weather Sunny Temp. (Max) 46 ºC (Min) 35 ºC Location Open yard- Phase 1 (SPA)

Activity type Quantity Completed Performed by Time (Hrs)


Activity
ITP's Activity ID Activities Equipment Remarks
status
D/W/M/3M Planned Actual Y/N Code Planned Actual

DAY SHIFT

ELECTRICAL & INSTRUMENTATION ACTIVITIES

DAILY ACTIVITIES

*Legend: - Completed, × - Not completed


J-5001.01  Visual Inspection for Battery In DC system.
J-5001.08  HVAC system/Alarm/Trip status checks.
ABOT Control room D 1 1 Y MSI 2 2 -------
J-5001.09  Measuring of Battery charging Voltage & current,
Healthiness.

J-5001.10  Room temperature measuring and humidity checks in


all room locations.

E-5001.01  Visual Inspection for Battery In DC system.

E-5001.08  Measuring of Battery charging Voltage & current,


Healthiness. ABOT Electrical building D 1 1 Y MSI 2 2 -------

E-5001.09  Room temperature measuring and humidity checks in


all room locations.

J-6001.01  Visual Inspection for Battery In DC system.

J-6001.08  HVAC system/Alarm/Trip status checks.

KAAOT Control room D 1 1 Y MSI 1 1 -------


J-6001.09  Measuring of Battery charging Voltage & current,
Healthiness.

J-6001.10  Room temperature measuring and humidity checks in


all room locations.

E-6001.01  Visual Inspection for Battery In DC system.

E-6001.08  Measuring of Battery charging Voltage & current,


Healthiness. KAAOT Electrical building D 1 1 Y MSI 1 1 -------

E-6001.09  Room temperature measuring and humidity checks in


all room locations.

J-0002.1  Visual Inspection of the CPFOC/FOC Cable drums for


tarpaulin tightness and placement. CPFOC Cable and Instrument
D 20 20 Y MSI 1 1 -------
Cable.
J-0002.2  Visual Inspection of the Instrument Cable drums for
tarpaulin tightness and placement.

E-0001.2  Visual Inspection of the Power Cable drums for


tarpaulin tightness and placement.
Power cable drums D 70 70 Y MSI 1 1 ---------

Sub Total 8

MECHANICAL & STRUCTURAL ACTIVITIES

MONTHLY ACTIVITIES

In progress
COMPARTMENT NO. 6,
SPM4- CALM BUOY COMPARTMENTS
HYDRAULIC
ACCUMULATOR UNIT
1. Oil leakage observed from
the Tie-In connection of
TP3A belongs to A-M5401.
(Refer to photo 1.1)
2. Oil leakage observed from
the Tie-In connection of
TP5A belongs to A-M5401.
(Refer to photo 1.2).
Manual valves except the surge relief valve in
3. Oil leakage observed
M4401.10  compartment #4 (surge piping) shall be operated
(open/close) to check proper functioning, Grease
from the tube fitting of TP4B
belongs to A-M5403.
gearboxes.
4. Oil leakage observed from
the tube fitting of TP6B
belongs to A-M5404.
5. Oil leakage observed from
the tube fittings of TP5B
belongs to A-M5404.
(Refer to photo 1.3).
General:
1. Internal corrosion is
evident in the sounding
pipe, metal corroded and
flakes off, the corrosion
debris accumulated at the
floor of compartment.(Refer
M4401.11  Visually inspect the piping SPM4 M 1 1 N
BG,AK,
KP,SH
35 35
to photo 1.4).
2. Plain washer (one)
number of Enlarged
Manhole was found missing
(Not available) (Refer to
photo 1.5).
3. Paint deterioration was
noted on both Equipment
and Enlarged manholes
(Refer to photo 1.6)
Compartment#4 :
1. One set of hexagon bolt
and plain washer of Access
Enlarged Manhole were
found missing/unavailable
and not stored separately
(Refer to Photo 1.7).
2. The Access Equipment
Manhole rubber gasket has
been degraded due to
deterioration caused by
Check each compartment for water ingress via aging (Refer to Photo 1.8).
M4401.12  sounding plugs. Any water presents should be
removed, and all seals re-instated.
3. Paint/Coating of Access
Enlarged Manhole cover was
deteriorated and general
corrosion observed due to
aging (Refer to Photo 1.9).

Page 4 of 17
Project name Assets Preservation and General Maintenance Services

Contract No. EFP-10-10200(1)(Phase 1)

Contractor: Miraj Projects Company FZE DAILY PROGRESS REPORT Date: Friday 28-06-2024

Report No. 10200-00-F-RA-1230-D28062024-B1 Weather Sunny Temp. (Max) 46 ºC (Min) 35 ºC Location Open yard- Phase 1 (SPA)

Activity type Quantity Completed Performed by Time (Hrs)


Activity
ITP's Activity ID Activities Equipment Remarks
status
D/W/M/3M Planned Actual Y/N Code Planned Actual

SPM4- CALM BUOY-NAVAIDS (Navigation


light, foghorn, fog detector, RACON, wind
generator)

Solar panels shall be disconnected by switching off


M4401.24  their isolator. They shall be covered with an opaque
cover.

Check batteries voltage and top up to compensate for


M4401.25  self-discharge if it is under 23.6V (yard to inform SBM
about charger brand and model before use). SPM4 M 1 1 Y MNA,MD,FH 26 26 (Refer to photo: 2)

Visual inspection If storage is beyond three months all


M4401.26  battery banks shall be removed with all batteries inside
in a full charged state. The banks shall be kept in a
warehouse under air conditioning at around 30C.

M4401.27  Annual: reinstall all the equipment, recharge the


batteries and test all navaids functions.

VS1 Subsea Spools, Bends and Concrete


Coated Pipes

L5505.21  Detailed Visual inspection of VS1 Subsea Spools,


Bends and Concrete Coated Pipes.

Check all associated Spools, Bends and Concrete


L5505.22  Coated Pipes for any Concrete coatings physical
damage.

All open ends of Subsea Spools and Bends (except


Concrete Coated Pipes) to be fitted with plastic.
Flanged ends to have plywood cover. Flanges raised
L5505.23  face shall be greased and fully covered. Each Flange
face making contact with a ring joint type gasket shall
be greased to restrict corrosion. (if not covered, shall
be reported with photos).

Weld joint portion of concrete coated pipe having a


L5505.24  ring joint type gasket, shall check condition of stacked
pipe, also to check inside areas of any dirt’s, any
physical damage and inspected quarterly.
During the routine inspection, it
has been observed that external
L5505.25  Check inside areas of any dirt's. 3LPE coated 02 pipe spools and
05 QTY of Pipes are being
Pipe spools M 1 Lot 1 Lot Y BG 5 5 stacked/stored by LO above the
Check the spool supports stool /dunnage (if concrete pipes and directly
L5505.26  applicable), Stored condition on wooden dunnage of
spools with a minimum of 150mm clearance.
exposed to sunlight leading to
degradation of the coating.

Check all spools are stored safely and properly (if not (Refer to photo: 3)
L5505.27  stored properly as required, shall be reported with
photos).

Subsea spools that have 3LPE coating are to be


L5505.28  stored under an elevated tarpaulin allowing for the free
flow of air and preventing direct sun light on them.

Check. If significant corrosion is found for metal parts


L5505.29  of subsea spools, bends and concrete coated pipes it
shall be reported immediately with BOC/PMC site
representative for corrective action if required.

Thickness measurement for the metal parts for


L5505.30  indication of corrosion level in the spools, report with
photos any thickness reduction as a corrosion level
before taking any corrective action.

L5505.31  Check all spools are stored safely and properly (if not
stored properly, shall be reported with photos).

Sub Total 66

Page 5 of 17
Project name Assets Preservation and General Maintenance Services

Contract No. EFP-10-10200(1)(Phase 1)

Contractor: Miraj Projects Company FZE DAILY PROGRESS REPORT Date: Friday 28-06-2024

Report No. 10200-00-F-RA-1230-D28062024-B1 Weather Sunny Temp. (Max) 46 ºC (Min) 35 ºC Location Open yard- Phase 1 (SPA)

Activity type Quantity Completed Performed by Time (Hrs)


Activity
ITP's Activity ID Activities Equipment Remarks
status
D/W/M/3M Planned Actual Y/N Code Planned Actual

NIGHT SHIFT
J-5001.08  HVAC system/Alarm/Trip status checks.

J-5001.09  Measuring of Battery charging Voltage & current,


Healthiness. ABOT Control room D 1 1 Y MM 2 2 -------

J-5001.10  Room temperature measuring and humidity checks in


all room locations.

E-5001.08  Measuring of Battery charging Voltage & current,


Healthiness.
ABOT Electrical building D 1 1 Y MM 3 3 -------
E-5001.09  Room temperature measuring and humidity checks in
all room locations.

J-6001.08  HVAC system/Alarm/Trip status checks.

J-6001.09  Measuring of Battery charging Voltage & current,


Healthiness. KAAOT Control room D 1 1 Y MM 3 3 -------

J-6001.10  Room temperature measuring and humidity checks in


all room locations.

E-6001.08  Measuring of Battery charging Voltage & current,


Healthiness.
KAAOT Electrical building D 1 1 Y MM 3 3 -------
E-6001.09  Room temperature measuring and humidity checks in
all room locations.

Sub Total 11

GENERAL ACTIVITIES

1  Cleaning and covering of assets at A1, B2, B6 area. General General 1 Lot 1 Lot N
MN,DK,AB,
SA,KH
30 30
In progress
(Refer to photo: 4)

2  Cleaning and tarpaulin covering on end face of pipe


spools.
General General 3 3 Y
MN,DK,AB,
SA,KH
20 20 (Refer to photo: 5)

3  Sprikling of Water for cooling of Phase-1 CPFOC


cable
General General -- -- Y MD,FH 4 4 (Refer to photo: 6)

4  Site Housekeeping. General General -- -- Y AF,SM 20 20 -------

Sub Total 74

SUB CONTRACTOR/SUPPORT SERVICE


General
1  Sewage removal. (Sub contractor/Support
service)
General 5000 Gal 5000 Gal Y -- 10 10 1 person × 10 hour

Sub Total 10

GENERAL ACTIVITIES FOR MIRAJ TEMPORARY EQUIPMENTS


1  Visual inspection. 400V Switchboards D 2 2 Y MSI 1 1 -------

2  Switching generator (Day shift).


Generator
MRJ-5278 (2)
D 1 1 Y MNA 2 2 -------

3  Switching generator (Night shift).


Generator
MRJ-506852 (3)
D 1 1 Y MM 1 1 -------

Generator
4  Running hours, current consumption reading, fuel
consumption.
MRJ-5278 (2)
MRJ-506852 (3)
D 2 2 Y MSI 1 1 -------

Sub Total 5
ASSET PRESERVATION AND GENERAL MAINTENANCE - SUMMARY OF OPEN YARD MAN-HOURS
S/N Technical Activities Manhours
1 Electrical & Instrumentation - Daily Activities 8

2 Electrical & Instrumentation - Weekly Activities 0

3 Electrical & Instrumentation - Monthly Activities 0

4 Electrical & Instrumentation - Three monthly Activities 0

5 Mechanical & Structural - Weekly Activities 0

6 Mechanical & Structural - Monthly Activities 66

7 Mechanical & Structural - Three-Monthly Activities 0

8 Night Shift 11

9 General Activities 74

10 General Activities for MIRAJ temporary equipments 5

Sub Total 164

Support Activities

11 Sub Contractor - Open yard ( 1 Persons x 10 hours) 10

12 Support Activities ( 5 Persons x 10 hours and 4 Persons × 12 hours) 98

Sub Total 108

POTENTIAL VARIATION WORKS - SUMMARY OF NON-PRODUCTIVE MAN-HOURS FOR PRE-EMPTIVE ACTIVITIES


S/N Technical Activities Manhours

1 Category 2 & 3 Assets exportation Activities 0

Sub Total 0

Support Activities

2 Sub Contractor - Category 2 & 3 0

Sub Total 0

Page 6 of 17
Project name Assets Preservation and General Maintenance Services

Contract No. EFP-10-10200(1)(Phase 1)

Contractor: Miraj Projects Company FZE DAILY PROGRESS REPORT Date: Friday 28-06-2024

Report No. 10200-00-F-RA-1230-D28062024-B1 Weather Sunny Temp. (Max) 46 ºC (Min) 35 ºC Location Open yard- Phase 1 (SPA)

Activity type Quantity Completed Performed by Time (Hrs)


Activity
ITP's Activity ID Activities Equipment Remarks
status
D/W/M/3M Planned Actual Y/N Code Planned Actual

Hours
S/N Owned/Hired Equipment No. S/N Personnel Code Discipline
(each)
1 Generator 200KVA (DAY SHIFT) MRJ-5278 (2) 1 16 Technical Man-Hours Hrs

2 Generator 60KVA (NIGHT SHIFT) MRJ-506852 (3) 1 8 1 Deepak DK 10 Mech/Struc Eng/Insp

3 SUV/MUV four wheel drive 1 12 2 Bhavinkumar Govindbhai Patel BG 10 Mech/Struc Eng/Insp

4 Mini bus 1 12 3 Mohamed Nasreldin Ali MNA 12 Mechanical technician

Total 48 4 Ajil Kochanian AK 10 Mechanical technician

5 MD Shakir Irfani MSI 10 E & I Engineer

6 Mohammed Mumtaz MM 12 E & I Technician

7 Mohammad Shadab MH AL E & I Technician

8 Muthuraman N MN 10 Material control

9 Mohammad Faishul FH 10 Helper

10 Mohammed Dilshad MD 10 Helper

11 Abu Faijan AF 10 Helper

12 Kuldeep KP 10 Helper

13 Sachin Kumar SH 10 Helper

14 Abid Ali AB 10 Helper

15 Khalid KH 10 Helper

16 Sarwar Haidar Malik SM 10 Helper

17 Md Shazad Alam SA 10 Helper

Total 164

Support Man-Hours

18 Yasir Hussein YH 10 Project Manager

19 Murthy Arumugam MA 10 Technical manager

20 Mohammed Sahal MS 10 HSE Manager / Officer

21 Jayaganesh D JD 10 DCC

22 Mohammed Zubair MZ 10 Planning Engineer

S/N Manhour 23 Noorkhad NK 12 Driver

24 Sulphi Abdul Azeez SA 12 Driver

25 Man Bahadur Jarka Thapa G4S 12 Security


1 Total hours / Technical Activities Open yard 164 164
26 Himal Man G4S 12 Security

Total 98
Open yard
98
(S)

2 Total hours / Support Activities 108

Sub Contractor
10
(C)

3 Total 272

NON PRODUCTIVE MAN-HOURS FOR POTENTIAL VARIATION WORKS

S/N Personnel Code Discipline


S/N Manhour
Technical Man-Hours Hrs

Open yard
1 Total hours / Technical Activities 0
Category 2&3

0
Open yard
Category 2&3
2 Total hours / Support Activities 0
Sub Contractor
(C)

3 Total 0 Total 0

Support Man-Hours

Open yard Category 2&3 Sub Contractor ( C ) - 0 Sub Contractor

Total 0

*Legend: WO - Weekly Off, SL- Sick Leave, AL- Annual Leave, EH - Eid Holiday, PH - Public Holiday, L - Leave,
A - Absent

S/N Additional Notes (important items started or completed, major equipment received, visitors, etc)

Page 7 of 17
Project name Assets Preservation and General Maintenance Services

Contract No. EFP-10-10200(1)(Phase 1)

Contractor: Miraj Projects Company FZE DAILY PROGRESS REPORT Date: Friday 28-06-2024

Report No. 10200-00-F-RA-1230-D28062024-B1 Weather Sunny Temp. (Max) 46 ºC (Min) 35 ºC Location Open yard- Phase 1 (SPA)

Activity type Quantity Completed Performed by Time (Hrs)


Activity
ITP's Activity ID Activities Equipment Remarks
status
D/W/M/3M Planned Actual Y/N Code Planned Actual

PHOTOS
1. Monthly maintenance of SPM4.

1.1 1.2

Oil leakage observed from


the Tie In of TP3A.

Oil leakage observed from the


Tie In of TP5A.

1.3 1.4

Internal corrosion is evident in the


sounding pipe, metal corroded
and flakes off, the corrosion
debris accumulated at the floor of
compartment.

Oil leakage observed


from the Tie In of
TP5B.

1.5 1.6

Paint deterioration was


noted on both
Equipment and
Enlarged manholes.
Plain washer (one) number
of Enlarged Manhole was
found missing (Not
available).

Page 8 of 17
Project name Assets Preservation and General Maintenance Services

Contract No. EFP-10-10200(1)(Phase 1)

Contractor: Miraj Projects Company FZE DAILY PROGRESS REPORT Date: Friday 28-06-2024

Report No. 10200-00-F-RA-1230-D28062024-B1 Weather Sunny Temp. (Max) 46 ºC (Min) 35 ºC Location Open yard- Phase 1 (SPA)

Activity type Quantity Completed Performed by Time (Hrs)


Activity
ITP's Activity ID Activities Equipment Remarks
status
D/W/M/3M Planned Actual Y/N Code Planned Actual

2. Monthly maintenance of SPM4.

1.7 1.8
One set of hexagon bolt and
plain washer of Access Paint deterioration
Enlarged Manhole were was noted on both
found missing/unavailable Equipment and
and not stored separately. Enlarged manholes.

Paint/Coating of Access
Enlarged Manhole cover was
1.9 deteriorated and general
corrosion observed due to
aging.

NO PHOTO

2. Monthly maintenance of SPM4 NAVAIDS.

Page 9 of 17
Project name Assets Preservation and General Maintenance Services

Contract No. EFP-10-10200(1)(Phase 1)

Contractor: Miraj Projects Company FZE DAILY PROGRESS REPORT Date: Friday 28-06-2024

Report No. 10200-00-F-RA-1230-D28062024-B1 Weather Sunny Temp. (Max) 46 ºC (Min) 35 ºC Location Open yard- Phase 1 (SPA)

Activity type Quantity Completed Performed by Time (Hrs)


Activity
ITP's Activity ID Activities Equipment Remarks
status
D/W/M/3M Planned Actual Y/N Code Planned Actual

2. Monthly maintenance of SPM4 NAVAIDS.

3. Monthly visual inspection of VS1 Subsea Spools, Bends and Concrete Coated Pipes.

3LPE coated 02 pipe spools and 05 QTY of Pipes are being


stacked/stored by LO above the concrete pipes and directly
exposed to sunlight leading to degradation of the coating.

Page 10 of 17
Project name Assets Preservation and General Maintenance Services

Contract No. EFP-10-10200(1)(Phase 1)

Contractor: Miraj Projects Company FZE DAILY PROGRESS REPORT Date: Friday 28-06-2024

Report No. 10200-00-F-RA-1230-D28062024-B1 Weather Sunny Temp. (Max) 46 ºC (Min) 35 ºC Location Open yard- Phase 1 (SPA)

Activity type Quantity Completed Performed by Time (Hrs)


Activity
ITP's Activity ID Activities Equipment Remarks
status
D/W/M/3M Planned Actual Y/N Code Planned Actual

4. Cleaning and covering of assets at A1, B2, B6 area.

5. Cleaning and tarpaulin covering on end face of pipe spools.

6. Sprikling of Water for cooling of Phase-1 CPFOC cable

Reviewed by Prepared & Checked by Approved for Issue

Title: Employer Representative Planning Engineer Project Manager

Name: James Murray Thomson Mohammed Zubair Yasir Hussein

Date: 05-07-2024 05-07-2024

Signature:

Page 11 of 17
Project name Assets Preservation and General Maintenance Services

Contract No. EFP-10-10200(1)(Phase 1)

Friday
Contractor: Miraj Projects Company FZE DAILY PROGRESS REPORT Date:
28-06-2024

Report No. 10200-00-F-RA-1230-D28062024-B1 Weather Sunny Temp. (Max) 46 ºC (Min) 36 ºC Location Warehouse LV-19 C & D

2. WAREHOUSE LV-19 C & D

Page 12 of 17
Project name Assets Preservation and General Maintenance Services

Contract No. EFP-10-10200(1)(Phase 1)


Friday
Contractor: Miraj Projects Company FZE DAILY PROGRESS REPORT Date:
28-06-2024

Report No. 10200-00-F-RA-1230-D28062024-B1 Weather Sunny Temp. (Max) 46 ºC (Min) 36 ºC Location Warehouse LV-19 C & D

Activity type Quantity Completed Performed by Time (Hrs)


TASK ID Activities Equipment Remarks
D/W/M/3M Planned Actual Y/N Code Planned Actual
Morning: 23 ºC
Warehouse LV-19 D
1 -- D 1 1 Y AA 2 2 Evening: 22 ºC
Temperature monitoring and maintaining.
(Refer to photo: 1)
Warehouse LV-19 C Morning: 20.7 ºC
2 Document storage room temperature -- D 1 1 Y AA 2 2 Evening: 20.8 ºC
monitoring and maintaining. (Refer to photo: 2)

3 Housekeeping. -- D 1 1 Y AA 6 6 (Refer to photo: 3)

Sub Total 10

SUMMARY OF WAREHOUSE MAN-HOURS


S/N Technical Activities Manhours

1 Warehouse 10

Sub Total 10
Support Activities
2 Support Activities ( 1 Person x 8 hours, 3 Persons x 10 hours and 1 Person x 12 hours ) 50

3 Sub Contractor 0

Sub Total 50

POTENTIAL VARIATION WORKS - SUMMARY OF NON-PRODUCTIVE MAN-HOURS FOR PRE-EMPTIVE ACTIVITIES

S/N Technical Activities Manhours

1 Category 2 & 3 Assets exportation Activities 0

Hours
S/N Owned/Hired Equipment No. S/N Personnel Code Discipline
(each)
1 SUV/MUV four wheel drive 2 12 Technical Man-Hours Hrs

Total 24 1 Amanullah Akbar AA 10 Office boy

Total 10

S/N Manhour
Support Man-Hours

2 Mohammed Hussein MH 10 CEO

Total hours/ Technical 3 Ruel RL 10 Admin. / Secretary


1 Warehouses 10 10
Activities
4 Carla Sacdalan CS 10 PRO
5 Ruba Sammour RS 8 Accountant

6 Manivel Periyasamy MP 12 Driver


Warehouses
50 Total 50
(S)
Total hours/ Support
2 50
Activities

Sub Contractor
0
(C)

3 Total 60

Page 13 of 17
Project name Assets Preservation and General Maintenance Services

Contract No. EFP-10-10200(1)(Phase 1)


Friday
Contractor: Miraj Projects Company FZE DAILY PROGRESS REPORT Date:
28-06-2024

Report No. 10200-00-F-RA-1230-D28062024-B1 Weather Sunny Temp. (Max) 46 ºC (Min) 36 ºC Location Warehouse LV-19 C & D

NON PRODUCTIVE MAN-HOURS FOR POTENTIAL VARIATION WORKS

S/N Personnel Code Discipline


S/N Manhour Technical Man-Hours Hrs

Total hours/ Technical


1 Warehouses 0 0
Activities

Total 0

Warehouses
0
(S)
Total hours/ Support
2 0
Activities

Sub Contractor
0
(C)

3 Total 0
*Legend: WO - Weekly Off, SL- Sick Leave, AL- Annual Leave, EH - Eid Holiday,
PH - Public Holiday, L - Leave, A - Absent

S/N Additional Notes (important items started or completed, major equipment received, visitors, etc)

Page 14 of 17
Project name Assets Preservation and General Maintenance Services

Contract No. EFP-10-10200(1)(Phase 1)


Friday
Contractor: Miraj Projects Company FZE DAILY PROGRESS REPORT Date:
28-06-2024

Report No. 10200-00-F-RA-1230-D28062024-B1 Weather Sunny Temp. (Max) 46 ºC (Min) 36 ºC Location Warehouse LV-19 C & D

PHOTOS

1. Temperature monitoring and maintaining LV-19 D 2. Document Storage room temperature LV-19 C

08:21 AM - 23 ºC 05:07 PM - 22 ºC 08:17 AM - 20.7 ºC 05:03 PM - 20.8 ºC

3. Hosusekeeping

Reviewed by Prepared & Checked by Approved for Issue

Title: Employer Representative Planning Engineer Project Manager

Name: James Murray Thomson Mohammed Zubair Yasir Hussein

Date: 05-07-2024 05-07-2024

Signature:

Page 15 of 17
Project name Assets Preservation and General Maintenance Services

Contract No. EFP-10-10200(1)(Phase 1)

Contractor: Miraj Projects Company FZE DAILY PROGRESS REPORT Date: Friday 28-06-2024

Report No. 10200-00-F-RA-1230-D28062024-B1 Weather Sunny Temp. (Max) 46 ºC (Min) 36 ºC Location SPA & LV-19 C&D

3. SUMMARY OF OPEN YARD & WAREHOUSE MAN-HOURS

Page 16 of 17
Project name Assets Preservation and General Maintenance Services

Contract No. EFP-10-10200(1)(Phase 1)

Contractor: Miraj Projects Company FZE DAILY PROGRESS REPORT Date: Friday 28-06-2024

Report No. 10200-00-F-RA-1230-D28062024-B1 Weather Sunny Temp. (Max) 46 ºC (Min) 36 ºC Location SPA & LV-19 C&D

Activity type Quantity Completed Performed by Time (Hrs)


Activity
ITP's Activity ID Activities Equipment Remarks
status
D/W/M/3M Planned Actual Y/N Code Planned Actual

SUMMARY OF OPEN YARD & WAREHOUSE MAN-HOURS


S/N Technical Activities Manhours

1 Electrical & Instrumentation - Daily Activities 8


2 Electrical & Instrumentation - Weekly Activities 0
3 Electrical & Instrumentation - Monthly Activities 0
4 Electrical & Instrumentation - Three monthly Activities 0
5 Mechanical & Structural - Weekly Activities 0
6 Mechanical & Structural - Monthly Activities 66
7 Mechanical & Structural - Three-Monthly Activities 0

8 Night Shift 11

9 General Activities 74

10 General Activities for MIRAJ temporary equipments 5

11 Warehouse 10
Sub Total 174
Support Activities

12 Support Activities - Open yard ( 5 Persons x 10 hours and 4 Persons × 12 hours) 98

13 Support Activities ( 1 Person x 8 hours, 3 Persons x 10 hours and 1 Person x 12 hours ) 50

14 Sub Contractor - Open yard ( 1 Persons x 10 hours) 10

15 Sub Contractor - Warehouse 0


Sub Total 158

POTENTIAL VARIATION WORKS - SUMMARY OF NON-PRODUCTIVE MAN-HOURS


S/N Technical Activities Manhours

1 Category 2 & 3 Assets exportation Activities - Open yard 0

2 Category 2 & 3 Assets exportation Activities - Warehouses 0

Sub Total 0

Support Activities

3 Sub Contractor - Category 2 & 3 0

Sub Total 0

S/N MAN-HOURS FOR ASSETS PRESERVATION AND GENERAL MAINTENANCE SERVICES

Open yard 164


1 Total hours / Technical Activities 174
Warehouses 10

Open yard
98
(S)

2 Warehouses
50
(S)
Total hours / Support Activities 158
CA-005-MB-108 &
0
LV-20 C
Sub Contractor
10
(C)
3 Net Total 332

4 Total cumulative manhours up to previous day 316,162

5 Total Cumulative Manhours 316,494

S/N TOTAL CUMULATIVE MAN-HOURS FOR ALL WORKS DONE BY MIRAJ PROJECTS

Open Yard 0
Total Pre-emptive Manhours for
Category 2&3 Assets / Technical
Warehouses 0
1 0
Total Pre-emptive Manhours for
Sub Contractor
Category 2&3 Assets / Support 0
(C)
Activities
Total Manhours for Assets preservation and General maintenance
2 332
Services
3 Total cumulative manhours up to previous day 319,098

4 Total Cumulative Manhours 319,430

Reviewed by Prepared & Checked by Approved for Issue

Title: Employer Representative Planning Engineer Project Manager

Name: James Murray Thomson Mohammed Zubair Yasir Hussein

Date: 05-07-2024 05-07-2024

Signature:

Page 17 of 17