WEEKLY CONSTRUCTION REPORT

QMS-TM-WCPR Rev1

SITE NAME NTI SH TG KARANG SITE ID N/A DATE 23TH MARCH 2023 PROGRAM NTI PROJECT

INFINITE PROJECT
MHT PM/CM HADIRON CONTRACTOR L3 SITE MANAGER LIM CHEN LUN SUBPROGRAM N/A
MANAGEMENT

PROGRESS PHOTOS

Construct pre-cast manhole and set pile point on the Set up storage area Mobilize RC pile to site
site area.

Work progress Start Finish


Wk1 Wk2 Wk3 Wk4 Wk5 WK6 Wk7 Wk8 Wk9 Wk10 Wk11 Wk12 Wk13 Wk14 Wk15 Wk16 Wk17 Wk18 Wk19 Wk20 Wk21 Wk22

2/3/2023 9/3/2023 16/3/2023 23/3/2023


Plan 24.02.2023 2% 2.5% 3% 3.5%
Actual 07.07.2023 2% 3% 5% 9%

Page 1 of 2
WEEKLY CONSTRUCTION REPORT
QMS-TM-WCPR Rev1
Refer legend Legend for Project Status:
Major tasks this week Major tasks next week Project Status
1. Construct precast man-hole 1. Continue setup pile points on the site area. Schedule - Red at risk, behind schedule / HSSE
incident
2. Set pile points on the site area. 2. Continue construct pre-cast manhole.
HSSE - Amber to be monitored, minor
3. Set up storage area 3. Continue set pile point delays
4. Mobilize RC pile to site 4. Start piling works. Quality - Green Good, on or ahead of
schedule
Exposure hours reduction -

Exposure hours this week 640 Travel time to site this week 21 KM High / medium risk activities this week + exposure hours High / medium risk activities next week NM / PI this week 3
Exposure hours this month 1632 Travel time to site this month 84 KM 1. Install project signboard and hoarding on the site 1. Continue setup pile points on the NM / PI this month 6
Exposure hours cumulative 1632 Travel time to site cumulative 84 KM area. site area. NM / PI cumulative 6
Reduction of exposure hours 2. Setup red zone, green zone on site area. 2. Continue fabricate pre-cast HSSE incidents cumulative -
3. Setup guard house and toilet. manhole. LSR violations cumulative
4. Fabricate washing facilities, wheel wash through 3. Start piling works.
-
area and fabricate pre-cast manhole. -
5. Set pile points on the site area.

PO Amount per site Cost to complete Potential VO's amount List of VO's
Financial - -
Reporting RM RM ---, ---. -- RM ---, ---. -- - -
- -

Remarks - Piling work still unable to starts due to unsolved issue with Pak Sani