WEEKLY CONSTRUCTION REPORT

QMS-TM-WCPR Rev1

SITE NAME NTI SH TG KARANG SITE ID N/A DATE 16TH MARCH 2023 PROGRAM NTI PROJECT

INFINITE PROJECT
MHT PM/CM HADIRON CONTRACTOR L3 SITE MANAGER LIM CHEN LUN SUBPROGRAM C&M
MANAGEMENT

PROGRESS PHOTOS

Install project signboard and hoarding on the site area. Setup crash barrier on the site area. Setup green zone and red zone.

Setup guard house and toilet. Fabricate washing facilities and wheel wash through area.

Work progress Start Finish


Wk1 Wk2 Wk3 Wk4 Wk5 WK6 Wk7 Wk8 Wk9 Wk10 Wk11 Wk12 Wk13 Wk14 Wk15 Wk16 Wk17 Wk18 Wk19 Wk20 Wk21 Wk22

2/3/2023 9/3/2023 16/3/2023


Plan 24.02.2023 2% 2.5% 3%
Actual 07.07.2023 2% 3% 4%

Page 1 of 2
WEEKLY CONSTRUCTION REPORT
QMS-TM-WCPR Rev1

Refer legend Legend for Project Status:


Major tasks this week Major tasks next week Project Status
1. Install project signboard and hoarding on the site area. 1. Continue setup pile points on the site area. Schedule - Red at risk, behind schedule / HSSE
incident
2. Setup red zone and green zone on site area. 2. Construct pre-cast man-hole.
HSSE - Amber to be monitored, minor
3. Setup guard house and toilet. delays
4. Construct washing facilities, wheel wash through area Quality - Green Good, on or ahead of
5. Set pile points on the site area. schedule
Exposure hours reduction -

Exposure hours this week 600 Travel time to site this week 35 KM High / medium risk activities this week + exposure hours High / medium risk activities next week NM / PI this week 3
Exposure hours this month 992 Travel time to site this month 63 KM 1. Install project signboard and hoarding on the site 1. Continue setup pile points on the NM / PI this month 3
Exposure hours cumulative 992 Travel time to site cumulative 63 KM area. site area. NM / PI cumulative 3
Reduction of exposure hours 2. Setup red zone, green zone on site area. 2. Construct pre cast man-hole HSSE incidents cumulative -
3. Setup guard house and toilet. LSR violations cumulative
4. Construct washing facilities and wheel wash
-
through -
5. Set pile points on the site area.

PO Amount per site Cost to complete Potential VO's amount List of VO's
Financial - -
Reporting RM RM ---, ---. -- RM ---, ---. -- - -
- -

Remarks - Piling work on hold due to Pak Sani did not agree to start piling until he get the agreement from both party

Page 2 of 2