SH TG KARANG (NTI) WEEK 3
SH TG KARANG (NTI) WEEK 3
QMS-TM-WCPR Rev1
SITE NAME NTI SH TG KARANG SITE ID N/A DATE 16TH MARCH 2023 PROGRAM NTI PROJECT
INFINITE PROJECT
MHT PM/CM HADIRON CONTRACTOR L3 SITE MANAGER LIM CHEN LUN SUBPROGRAM C&M
MANAGEMENT
PROGRESS PHOTOS
Install project signboard and hoarding on the site area. Setup crash barrier on the site area. Setup green zone and red zone.
Setup guard house and toilet. Fabricate washing facilities and wheel wash through area.
Page 1 of 2
WEEKLY CONSTRUCTION REPORT
QMS-TM-WCPR Rev1
Exposure hours this week 600 Travel time to site this week 35 KM High / medium risk activities this week + exposure hours High / medium risk activities next week NM / PI this week 3
Exposure hours this month 992 Travel time to site this month 63 KM 1. Install project signboard and hoarding on the site 1. Continue setup pile points on the NM / PI this month 3
Exposure hours cumulative 992 Travel time to site cumulative 63 KM area. site area. NM / PI cumulative 3
Reduction of exposure hours 2. Setup red zone, green zone on site area. 2. Construct pre cast man-hole HSSE incidents cumulative -
3. Setup guard house and toilet. LSR violations cumulative
4. Construct washing facilities and wheel wash
-
through -
5. Set pile points on the site area.
PO Amount per site Cost to complete Potential VO's amount List of VO's
Financial - -
Reporting RM RM ---, ---. -- RM ---, ---. -- - -
- -
Remarks - Piling work on hold due to Pak Sani did not agree to start piling until he get the agreement from both party