NEPAL ELECTRICITY AUTHORITY

Distribution and Consumer Service Directorate


Planning and Technical Service Department
Bhojpur - Sankhuwasabha Rural Electrification Project

SUBMISSION OF PROGRESS REPORT


For
Contract No.: NEA/DCSD/PTSD/REP/PACKAGE-10(RE1)
Design, Supply, Installation/Erection, Testing and Commissioning of Distribution
Network in Bhojpur District

Submitted by:
M/s BP Construction Pvt. Ltd.
Naxal – 01, Kathmandu
Nepal

Page 1 of 6
BASIC PROJECT INFORMATION
1. Contract Reference: Contract No. NEA/DCSD/PTSD/REP/PACKAGE-10(RE1);

2. Project Title: Bhojpur - Sankhuwasabha Rural Electrification Project

3. Site Location: Bhojpur District

4. Client: Nepal Electricity Authority, Distribution and Consumer


Service Directorate, Planning and Technical
Service Department

5. Contractor: M/s BP Construction Pvt. Ltd.

6. Contract Effective Date: 26thth Feb. 2023


7. Contract period: 18 Months

SCOPE OF WORK
The major scope of works covered design, engineering, procurement, inspection & testing at
manufacturer’s works, supply, insurance, transportation, receipt at site, storage and
preservation at site, site handling, construction, erection, testing, commissioning, trial
operation, handing over to Employer, guarantee all equipment, spares and miscellaneous
material, catalogues, drawings, documents and services including lubricants, transformer oil,
consumables for the proposed distribution network projects of different sites in Bhojpur
District.

PROGRESS ACHIEVED TILL July 2nd, 2024


A. Line Survey and PCS Approval Status: Completed and Approved

B. Design Drawings Submission and Approval Status:

S. No. GTP and Drawing Status


1 Steel Tubular Pole and Fittings Approved
2 Covered Conductor Approved
3 AB Cable Approved
4 Distribution Transformer Approved
5 Insulator Hardware & Fittings Approved
6 MCCB & Distribution Panel Board Approved
7 Covered Conductor and AB Cable Fittings Approved

Page 2 of 6
8 LA, DS and DO Approved

C. Equipment Manufacturing, Inspection and Testing Works:

S. No. Description Status


1 Steel Tubular Pole and Fittings Completed
2 Covered Conductor Completed
3 AB Cable Completed
4 Distribution Transformer Completed
5 Insulator Hardware & Fittings Completed
6 MCCB & Distribution Panel Board Completed
7 Covered Conductor and AB Cable Fittings Completed
8 Disconnecting Switches Completed

D. Equipment Site Delivery Status

S. No. Description Status


1 Steel Tubular Pole and Fittings Completed
2 Covered Conductor Completed
3 AB Cable Completed
4 Distribution Transformer Completed
5 Insulator Hardware & Fittings Completed
6 MCCB & Distribution Panel Board Completed
7 Covered Conductor and AB Cable Completed
Fittings
8 Disconnecting Switches Completed

E. Erection, Installation and Testing Works:


The erection, installation and testing work at the sites is going on and following progress has
been achieved till date.

Page 3 of 6
Erection/Installation Progress Report
Overall Summary Name of Palika
S.
Name of Items Unit
No. Completed
PCS Qty. Salpasilicho Sadananda Amchowk Hatuagadi Ram Prasad Rai
Qty

1 11 Mtr. Steel Tubular Pole Nos 2927.00 2443 971 140 1022 176 134

2 8 Mtr. Steel Tubular Pole Nos 4162.00 3287 882 171 1570 375 289

100 sq. mm. AAAC


3 Ckt. Km 18.669 3.15 1 2.15
Covered Conductor
50 sq. mm. AAAC Covered
4 Ckt. Km 136.065 61.5 32.3 1 24.2 1.5 2.5
Conductor
5 4x95 sq. mm. AB Cable Ckt. Km 4.27 1.5 1.5
6 4x50 sq. mm. AB Cable Ckt. Km 118.03 43.7 13.9 1 20.3 3 5.5
7 4x25 sq. mm. AB Cable Ckt. Km 96.75 23.5 3.3 2 12.6 4.85 0.75

8 2x50 sq. mm. AB Cable Ckt. Km 70.44 25.05 3.55 3.5 12.3 1.5 4.2

9 Transformer- 25 kVA Nos 38.00 17 2 0 13 2

10 Transformer- 50 kVA Nos 46.00 23 5 0 13 5

11 Transformer- 100 kVA Nos 6.00 2 0 0 2

12 HT Stay Nos 1481.00 611 210 17 290 80 14


13 LT Stay Nos 1758.00 813 202 54 402 116 39

Page 4 of 6
Erection/Installation Progress Report This Bill
Overall Summary Name of Palika (This Bill)
S.
Name of Items Unit Completed
No. Ram Prasad
PCS Qty. Qty (This Salpasilicho Sadananda Amchowk Hatuagadi
Rai
Bill)

1 11 Mtr. Steel Tubular Pole Nos 2927.00 490 432 16 42 0 0

2 8 Mtr. Steel Tubular Pole Nos 4162.00 583 223 57 303 0 0

100 sq. mm. AAAC


3 Ckt. Km 18.669 3.15 0 1 2.15
Covered Conductor
50 sq. mm. AAAC Covered
4 Ckt. Km 136.065 57.6 26.2 1 23 2.8 4.65
Conductor
5 4x95 sq. mm. AB Cable Ckt. Km 4.27 1.5 1.5
6 4x50 sq. mm. AB Cable Ckt. Km 118.03 42.7 13.9 1 20.3 3 4.55
7 4x25 sq. mm. AB Cable Ckt. Km 96.75 23.5 3.3 2 12.6 4.85 0.75

8 2x50 sq. mm. AB Cable Ckt. Km 70.44 23.55 3.55 3.5 12.3 1.5 2.7

9 Transformer- 25 kVA Nos 38.00 7 2 5

10 Transformer- 50 kVA Nos 46.00 13 5 8

11 Transformer- 100 kVA Nos 6.00 1 1

12 HT Stay Nos 1481.00 374 210 17 145 0 2


13 LT Stay Nos 1758.00 491 141 54 286 0 10

Page 5 of 6
F. As-Built design drawings and other documentation works:
As-Built drawing will be prepared and submitted as per plan and schedule.