Tower TOWER R Floor 10TH FLOOR Unit(s) STAIRCASE Activity CONVENTIONAL FORMWORK- PRE & DURING CHECK WIR Created By TAPAN DAS WIR Status Approved WIR Created Date 6/4/2024 4:02:47 PM WIR Closed Date 6/5/2024 4:47:53 PM Contractor Krishna Hi-tech Pvt.Ltd.- Phase Retreat Prakriti
TASKS HISTORY
SI # Location Task User Status Scheduled Date Closed Date
1 ST-02 (10th floor - 1/2 CONVENTIONAL TAPAN Added 6/4/2024 4:02:47 landing) FORMWORK- PRE & DAS PM DURING CHECK 2 ST-02 (10th floor - 1/2 CONVENTIONAL Kabir Approved 6/5/2024 4:47:53 6/5/2024 4:47:53 landing) FORMWORK- PRE & Mondal PM PM DURING CHECK
SI # Checkpoint Client Comments Contractor Comments Last Status Photos
1 Check if Formwork erection is done as per the Pass approved shuttering drawing and method statement with sufficient tie rods, C clamps and repropping. 2 Is formwork clean, gaps are filled to avoid slurry Pass leakage? 3 Is approved make form release agent applied Pass properly? 4 Is the formwork levels, alignment and Pass dimensions are as per drawing? 5 Have markings been made on the formwork for Pass concrete level? 6 Thickness & condition of plywood is satisfactory Pass with no delamination or deterioration. 7 Runners, wailers, chawis are provided for Pass vertical side as approved in shuttering drawing. 8 Inside dimentions of formwork including Pass diagonals are as per the drawing. 9 Centre to centre alignment & orientation checked Pass & found OK. 10 MEP checking done ,it is ok & checklist filled & Pass found OK? 11 Check if Shuttering erected in plumb for Pass columns, beams and walls. 12 Between the 2 lifts, ensure gap filled with double Pass sided tape or foam. 13 Beam Bottom & slab levels are checked & found Pass OK 14 Beam width & centre line as per the drawing Pass 15 Location & detail of construction joint is as per Pass the structural consultant's approval, stoppers are provided at construction joint. 16 Sufficient cover provided in both bottom and Pass vertical face of all elements. 17 Verical supports to the slab & beams are in Pass plumb and resting on firm surface (no slush/loose materials) 18 Cross brasing is provided as approved. Pass 19 sunk dimentions ( internal ) are checked & NA found OK. 20 MEP checking done ,Is it ok & checklist filled & Pass found OK? 21 Gap between the shutter is closed with approved Pass material? 22 Footing Box properly anchored to PCC NA 23 Adequate side support for boxes provided. NA 24 Cleaning /dewatering done before actual NA concrete. 25 Gap between side ply and PCC sealed to make NA joints leak proof.