825407: GODREJ PRAKRITI-TOWER Q

-STRUCTURAL CONCRETE – DURING POUR

Company Godrej Properties Project GODREJ PRAKRITI


Tower TOWER Q Floor 15th FLOOR
Unit(s) STAIRCASE Activity STRUCTURAL CONCRETE
- DURING POUR
WIRCreatedBy Rajesh Adhikary WIRStatus Approved
WIRCreatedDate 6/14/2024 2:29:57 PM WIRClosedDate 6/14/2024 2:37:39 PM
Contractor KrishnaHi-techPvt.Ltd.- Prakriti Phase Retreat

TASKSHISTORY

SI# Location Task User Status ScheduledDate ClosedDate


1 STAIR 1 HALF STRUCTURAL CONCRETE Rajesh Added 6/14/2024
LANDINGTO15TH - DURING POUR Adhikary 2:29:57 PM
FLOOR
2 STAIR 1 HALF STRUCTURAL CONCRETE SUBHADI Approved 6/14/2024 6/14/2024
LANDINGTO15TH - DURING POUR P 2:37:39 PM 2:37:39 PM
FLOOR MALLICK

SI# Checkpoint ClientComments ContractorComments LastStatus Photos


1 Availability & functionalityof Vibrators with Pass
respective needle ( electrical & Diesel vibrator
shallbestandbycheckedbeforecommencethe concrete)

2 Existing Construction Joints are Roughed and Pass


Cleaned.AppliedwithEpoxyBondingagentto
receive Concrete.
3 CheckBatchticketasperApprovedmixdesign and the Pass
approved tolerance guidelines as per ITP

4 Doestheconcretelookhomogenouswithout Pass
segregation, bleeding & have required workability

5 Waspourplanfollowedfully?Incasepourplan was not Pass


fully followed, give reasons.
6 Allvehiclearepouredwith3hrsretentionasper mix Pass
design and NO redosing permitted
7 Ensurewalkwaysareinplacetoavoiddamage of Pass
Electrical conduits
8 EnsureStandbyElectricianandPlumbertorefix if any Pass
Electrical and Cut-out dislocations
9 EnsureSafetytools,PPEeffectivelightsincase of night Pass
concrete
10 Workabilityatthepumppointasmeasuredby Pass
slumptestshallbeasperapprovemixdesign with
tolerance of +/-25mm
11 Haveconcretingdonebylayersnotexceeding 300mm Pass
and next layer of concrete has to be placed only after
the bottom layer has been compacted properly.

12 Theconcreteshouldbefilledfirstinbeam/wall and after Pass


slab
13 IftheconcreteGradedifferencebetweenSlab Pass
concrete,Columnbeamjunctiontobepoured with
high grade ensure its being done with Tower carne
Bucket and Less Slump being ensure for Effective
application otherwise permitted by consultant for
same grade
14 Insunkenarea,Ensureformsforsunkenareties Pass
firmlyandthicknessshouldbemaintainedasper drawing
or specification.
15 InSunkenorcantileverportionsdon’tallowthe Pass
pumpconcretedirectlyPourwithhighpressure extra
care to be takenwith manual placement
16 Ensurethethicknessofconcretebyusing concrete Pass
gauge
17 Key for concrete: To Finish concrete Laying Pass
coarseaggregateontopoftheconcretesurface, it should
be key for upcoming concrete layers in Wall/ column

18 Check for top concretelevel & finishingin slab Pass


+/-10mm Max permitted with required finish
19 Earlycuringafter3hoursofconcreteorthetime of non- Pass
foot mark, Sprinkle curing to the slab surface to be
commenced to avoid Plastic Shrinkage cracks

Page1|1