Tower TOWER R Floor 10TH FLOOR Unit(s) STAIRCASE Activity STRUCTURAL CONCRETE - DURING POUR WIR Created By Souvik Biswas WIR Status Approved WIR Created Date 6/7/2024 7:24:08 PM WIR Closed Date 6/7/2024 9:07:49 PM Contractor Krishna Hi-tech Pvt.Ltd.- Phase Retreat Prakriti
TASKS HISTORY
SI # Location Task User Status Scheduled Date Closed Date
1 Staircase -2( half STRUCTURAL CONCRETE Souvik Added 6/7/2024 7:24:08 landing to 11th floor) - DURING POUR Biswas PM 2 Staircase -2( half STRUCTURAL CONCRETE Kabir Approved 6/7/2024 9:07:49 6/7/2024 9:07:49 landing to 11th floor) - DURING POUR Mondal PM PM
SI # Checkpoint Client Comments Contractor Comments Last Status Photos
1 Availability & functionality of Vibrators with Pass respective needle ( electrical & Diesel vibrator shall be stand by checked before commence the concrete) 2 Existing Construction Joints are Roughed and Pass Cleaned. Applied with Epoxy Bonding agent to receive Concrete. 3 Check Batch ticket as per Approved mix design Pass and the approved tolerance guidelines as per ITP 4 Does the concrete look homogenous without Pass segregation, bleeding & have required workability 5 Was pour plan followed fully? In case pour plan Pass was not fully followed, give reasons. 6 All vehicle are poured with 3 hrs retention as per 04 hours Pass mix design and NO redosing permitted 7 Ensure walkways are in place to avoid damage Pass of Electrical conduits 8 Ensure Standby Electrician and Plumber to refix Pass if any Electrical and Cut-out dislocations 9 Ensure Safety tools, PPE effective lights in case Pass of night concrete 10 Workability at the pump point as measured by Pass slump test shall be as per approve mix design with tolerance of +/-25mm 11 Have concreting done by layers not exceeding Pass 300mm and next layer of concrete has to be placed only after the bottom layer has been compacted properly. 12 The concrete should be filled first in beam/wall Pass and after slab 13 If the concrete Grade difference between Slab Pass concrete , Column beam junction to be poured with high grade ensure its being done with Tower carne Bucket and Less Slump being ensure for Effective application otherwise permitted by consultant for same grade 14 In sunken area, Ensure forms for sunken are ties Pass firmly and thickness should be maintained as per drawing or specification. 15 In Sunken or cantilever portions don’t allow the Pass pump concrete directly Pour with high pressure extra care to be taken with manual placement 16 Ensure the thickness of concrete by using Pass concrete gauge 17 Key for concrete: To Finish concrete Laying Pass coarse aggregate on top of the concrete surface, it should be key for upcoming concrete layers in Wall/ column 18 Check for top concrete level & finishing in slab Pass +/-10mm Max permitted with required finish 19 Early curing after 3 hours of concrete or the time Pass of non-foot mark, Sprinkle curing to the slab surface to be commenced to avoid Plastic Shrinkage cracks