810857 (1)

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

810857: GODREJ PRAKRITI-TOWER R

-CONVENTIONAL FORMWORK- PRE & DURING CHECK

Company Godrej Properties Project GODREJ PRAKRITI


Tower TOWER R Floor 10TH FLOOR
Unit(s) STAIRCASE Activity CONVENTIONAL
FORMWORK- PRE &
DURING CHECK
WIR Created By TAPAN DAS WIR Status Approved
WIR Created Date 6/7/2024 10:35:44 AM WIR Closed Date 6/7/2024 11:15:54 AM
Contractor Krishna Hi-tech Pvt.Ltd.- Phase Retreat
Prakriti

TASKS HISTORY

SI # Location Task User Status Scheduled Date Closed Date


1 ST-02(1/2 landing - 11 CONVENTIONAL TAPAN Added 6/7/2024
th floor) FORMWORK- PRE & DAS 10:35:44 AM
DURING CHECK
2 ST-02(1/2 landing - 11 CONVENTIONAL Kabir Approved 6/7/2024 6/7/2024
th floor) FORMWORK- PRE & Mondal 11:15:54 AM 11:15:54 AM
DURING CHECK

SI # Checkpoint Client Comments Contractor Comments Last Status Photos


1 Check if Formwork erection is done as per the Pass
approved shuttering drawing and method
statement with sufficient tie rods, C clamps and
repropping.
2 Is formwork clean, gaps are filled to avoid slurry Pass
leakage?
3 Is approved make form release agent applied Pass
properly?
4 Is the formwork levels, alignment and Pass
dimensions are as per drawing?
5 Have markings been made on the formwork for Pass
concrete level?
6 Thickness & condition of plywood is satisfactory Pass
with no delamination or deterioration.
7 Runners, wailers, chawis are provided for Pass
vertical side as approved in shuttering drawing.
8 Inside dimentions of formwork including Pass
diagonals are as per the drawing.
9 Centre to centre alignment & orientation checked Pass
& found OK.
10 MEP checking done ,it is ok & checklist filled & Pass
found OK?
11 Check if Shuttering erected in plumb for Pass
columns, beams and walls.
12 Between the 2 lifts, ensure gap filled with double Pass
sided tape or foam.
13 Beam Bottom & slab levels are checked & found NA
OK
14 Beam width & centre line as per the drawing NA
15 Location & detail of construction joint is as per NA
the structural consultant's approval, stoppers are
provided at construction joint.
16 Sufficient cover provided in both bottom and NA
vertical face of all elements.
17 Verical supports to the slab & beams are in NA
plumb and resting on firm surface (no
slush/loose materials)
18 Cross brasing is provided as approved. NA
19 sunk dimentions ( internal ) are checked & NA
found OK.
20 MEP checking done ,Is it ok & checklist filled & NA
found OK?
21 Gap between the shutter is closed with approved NA
material?
22 Footing Box properly anchored to PCC NA
23 Adequate side support for boxes provided. NA
24 Cleaning /dewatering done before actual NA
concrete.
25 Gap between side ply and PCC sealed to make NA
joints leak proof.

Page 1|1

You might also like