PROJECT : MEMBINA JALAN BAHARU DARI KAMPUNG GAGU - ULU BERANANG, NEGERI SEMBILAN

Proposed Rate Amount


BILL NO. 2 - DRAINAGE Labour Cost (RM)
Item Description Unit Qty

DRAINAGE

NEW PIPE CULVERT

Q100 EXCAVATION

Culvert excavation shall be deemed to include preparation


of surfaces, double handling, disposal of surplus
excavated material, upholding sides of excavation,
allowance for joints, backfilling, and removal of dead
services and reinstatement of original Surface unless
covered by separate items.

Q151.1 Earth commencing from ground level for culvert m3 6,702 -

Type of Foundation

Type A - Plain Concrete Cradle Foundation

I111 Grade C12/15 Concrete; Blinding mass concrete, 50mm m2 2,503 5.00 12,515.00
thick to footing.

I511 Formwork - F1: rough finish to bases. m2 1,825 25.00 45,625.00

I132 Grade C20/25 Concrete; m3 1,149 24.00 27,576.00

Fill Material

The following items for filling shall include compaction,


and additional filling necessities by settlement or
penetration into underlying material as applicable.

F312 Filling; Other stated material; imported sand material. m3 411 4.00 1,644.00

Type A1 - Reinforced Concrete Cradle Foundation

I111 Grade C12/15 Concrete; Blinding mass concrete, 50mm m2 359 4.00 1,436.00
thick to footing.

I511 Formwork - F1: rough finish to bases. m2 257 25.00 6,425.00

I132 Grade C20/25 Concrete; m3 160 24.00 3,840.00

TO COLLECTION 99,061.00

BQ 2 - 1/6
PROJECT : MEMBINA JALAN BAHARU DARI KAMPUNG GAGU - ULU BERANANG, NEGERI SEMBILAN

Proposed Rate Amount


BILL NO. 2 - DRAINAGE Labour Cost (RM)
Item Description Unit Qty

DRAINAGE (CONT'D)

NEW PIPE CULVERT (cont'd)

Fill Material

The following items for filling shall include compaction,


and additional filling necessities by settlement or
penetration into underlying material as applicable.

F312.1 Filling; Other stated material; imported sand material. m3 58 4.00 232.00

Box Culvert - Foundation


Fill Material

The following items for filling shall include compaction,


and additional filling necessities by settlement or
penetration into underlying material as applicable.

F312.2 Filling; Other stated material; imported hardcore material. m3 381 5.00 1,905.00

Precast Concrete Pipe Culvert

Single precast concrete pipe culvert, Class Z in standard


length of 1.52m. (Rebate Joint)

Q611.1 1500mm diameter m 552 50.00 27,600.00

Q611.2 1800mm diameter m 34 60.00 2,040.00

Single precast concrete pipe culvert, Class 1.5Z in standard


length of 1.52m. (Rebate Joint)

Q611.3 1500mm diameter m 624 50.00 31,200.00

Single precast concrete pipe culvert, Class 2.0Z in standard


length of 1.52m. (Rebate Joint)

Q611.4 1500mm diameter m 171 50.00 8,550.00

TO COLLECTION 71,527.00

BQ 2 - 2/6
PROJECT : MEMBINA JALAN BAHARU DARI KAMPUNG GAGU - ULU BERANANG, NEGERI SEMBILAN

Proposed Rate Amount


BILL NO. 2 - DRAINAGE Labour Cost (RM)
Item Description Unit Qty

DRAINAGE (CONT'D)

NEW PIPE CULVERT (cont'd)

Precast Concrete Pipe Culvert (CONT'D)

Cast in-situ concrete box culvert

Q621.1 1500mmx1500mm m 49 60.00 2,940.00

Q621.2 2100mmx2100mm m 311 70.00 21,770.00

Q621.3 2400mmx2400mm m 125 80.00 10,000.00

Inlet/ Outlet

Items for inlet and outlet structure shall be deemed to


include concrete reinforcement formwork, rip-raps, river
protection and all associated works

Headwall/ Wingwall

Q891 Cast In-Situ nr 58 1,600.00 92,800.00

Inlet/Outlet Integration/ Protection

Q892 Cast In-Situ nr 58 1,600.00 92,800.00

For construction of Inlet/Outlet (Item Q891/Q892) ; Quanity to be remeasured & provisional


Based on Sub-labour & machinery rate as follow :
Lean Concrete, 50mm thick m2
Concrete m2
Formwork m3
Rebar : T12 & above kg
Rebar : T16 & above kg

Q100 SURFACE DRAIN

Item for surface drains shall be deemed to include


preparation of surfaces, double handling, disposal of surplus
excavated material, upholding sides of excavation,
allowance for joints, backfilling, and removal of dead
services and reinstatement of Original Surface unless covered
by separate items

TO COLLECTION 220,310.00

BQ 2 - 3/6
PROJECT : MEMBINA JALAN BAHARU DARI KAMPUNG GAGU - ULU BERANANG, NEGERI SEMBILAN

Proposed Rate Amount


BILL NO. 2 - DRAINAGE Labour Cost (RM)
Item Description Unit Qty

DRAINAGE (CONT'D)

Q100 SURFACE DRAIN (CONT'D)

Excavation

Culvert excavation shall be deemed to include preparation


of surfaces, double handling, disposal of surplus
excavated material, upholding sides of excavation,
allowance for joints, backfilling, and removal of dead
services and reinstatement of original Surface unless
covered by separate items

Q111 Excavation; Depth not exceeding 1.5 m m 96,092 -

Type of Foundation

I111 Grade C12/15 Concrete; Blinding mass concrete, 50mm m2 122,725 5.00 613,625.00
thick.

Interceptor Drain

Q210.1 Interceptor drains; cast in-situ reinforced concrete grade 20; m 13,356 25.00 333,900.00
300mm wide x 450mm deep x 75mm thick trapezoidal
shape.

Q210.2 Interceptor drains; cast in-situ reinforced concrete grade 20; m 463 30.00 13,890.00
450mm wide x 600mm deep x 75mm thick trapezoidal
shape.

Q210.3 Interceptor cascade drains; cast in-situ reinforced concrete m 1,813 40.00 72,520.00
grade 20; 300mm wide x 450mm deep x 75mm thick
trapezoidal shape.

Bench Drain

Q220.1 Bench drains; cast in-situ concrete grade 20; 750mm wide m 26,668 30.00 800,040.00
(average) x 300mm deep x 75mm thick trapezoidal shape
thick V-shape.

Berm Drain

Q220.2 Berm drains; cast in-situ concrete grade 20; 900mm wide x m 17,966 35.00 628,810.00
300mm deep x 75mm thick V-shape.

TO COLLECTION 2,462,785.00

BQ 2 - 4/6
PROJECT : MEMBINA JALAN BAHARU DARI KAMPUNG GAGU - ULU BERANANG, NEGERI SEMBILAN

Proposed Rate Amount


BILL NO. 2 - DRAINAGE Labour Cost (RM)
Item Description Unit Qty

DRAINAGE (CONT'D)

Roadside Drains for Rural Area

Roadside drain; cast in-situ reinforced concrete drain

Q230.1 900mm wide with average 300mm high m 10,873 30.00 326,190.00

Q230.2 1350mm wide with average 450mm high m 7,002 40.00 280,080.00

Q230.3 1800mm wide with average 600mm high m 289 50.00 14,450.00

Embankment Toe Drains

Toe drain; cast in-situ reinforced concrete;

Q250 1650mm wide x 450mm deep m 12,070 35.00 422,450.00

Cascade toe drain; cast in-situ reinforced concrete;

Q260.1 1650mm wide x 450mm deep m 2,703 50.00 135,150.00

Cascade Drain

Q260.2 Cascade drains; cast in-situ concrete drain; 600mm wide x m 773 55.00 42,515.00
450mm deep at berms

Shoulder Drain

Cast in-situ concrete grade 20; embankment shoulder drain

Q290.1 175mm deep m 289 25.00 7,225.00


175mm deep (Precast Unit)

Q300 SUB-SURFACE DRAIN

Excavation

Q111 Depth not exceeding 1.5 m (bottom of roadside drain) m 13,432 -

TO COLLECTION 1,228,060.00

BQ 2 - 5/6
PROJECT : MEMBINA JALAN BAHARU DARI KAMPUNG GAGU - ULU BERANANG, NEGERI SEMBILAN

Proposed Rate Amount


BILL NO. 2 - DRAINAGE Labour Cost (RM)
Item Description Unit Qty

DRAINAGE (CONT'D)

Subsoil Drains

Q310 Subsoil drains; 1000mm deep x 400mm wide; 150mm m 13,432 15.00 201,480.00
diameter porous pipe including aggregate (35 mm – 40 mm)
wrapped with geotextiles filter.

SUMP

Cast In-Situ Sump, including cover

Q710.1 900mm x 900mm x 1500mm nr 15 480.00 7,200.00

Q710.2 900mm x 1200mm x 1500mm nr 106 520.00 55,120.00

Q710.3 900mm x 2150mm x 1500mm nr 5 550.00 2,750.00

Q710.4 1200mm x 1500mm x 1500mm nr 86 550.00 47,300.00

Q710.5 1200mm x 1800mm x 1500mm nr 33 550.00 18,150.00

Q710.6 1200mm x 2100mm x 1500mm nr 1 600.00 600.00

Q710.7 1500mm x 1500mm x 1500mm nr 1 700.00 700.00

Q710.8 1500mm x 1800mm x 1500mm nr 9 750.00 6,750.00

Q710.9 2100mm x 2100mm x 1500mm nr 1 900.00 900.00

TO COLLECTION 340,950.00

COLLECTION

From Page No. BQ2 - 1/6 ………………… 99,061.00

From Page No. BQ2 - 2/6 ………………… 71,527.00

From Page No. BQ2 - 3/6 ………………… 220,310.00

From Page No. BQ2 - 4/6 ………………… 2,462,785.00

From Page No. BQ2 - 5/6 ………………… 1,228,060.00

From Page No. BQ2 - 6/6 ………………… 340,950.00

TOTAL CARRIED TO FINAL SUMMARY 4,422,693.00