ID Task Task Name Duration Start Finish Cost

Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025 Qtr 4, 2025 Qtr 1, 2026
Mode Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
1 Construction of Drainage 282 days 09 Jun 08 Jul ₱36,137,759.02
System in Amlac Ville
Payatas Quezon City
2 Permits 6 days 09 Jun 17 Jun ₱66,683.52
3 Permits and Clearances7 days 09 Jun 17 Jun ₱66,683.52
4 Site Preparation 5 days 18 Jun 24 Jun ₱67,188.50
5 Clearing and Grubbing5 days 18 Jun 24 Jun ₱67,188.50
6 Temfacil Erection 10 days 25 Jun 08 Jul ₱380,582.34
7 Temporary Facilities 10 days 25 Jun 08 Jul ₱380,582.34
8 Excavation of Existing 8 days 09 Jul 18 Jul ₱1,804,586.54
Structures
9 Excavation 8 days 09 Jul 18 Jul ₱1,804,586.54
10 Hauling 15 days 19 Jul 08 Aug ₱687,256.16
11 Removing and 15 days 19 Jul 08 Aug ₱687,256.16
Hauling of Existing
Drainage Pipes
12 Laying of Subcourse 7 days 09 Aug 19 Aug ₱321,922.76
Aggregates
13 Gravel Bedding 7 days 09 Aug 19 Aug ₱321,922.76
14 Installation of Circular 228 days 20 Aug 03 Jul ₱32,695,411.02
Culvert
15 Installing of RC 214 days 20 Aug 13 Jun ₱28,841,222.63
Circular Pipes
16 Sidewalk 14 days 16 Jun 03 Jul ₱867,829.52
17 Curb and Gutter 13 days 16 Jun 02 Jul ₱319,391.02
18 Manholes 11 days 16 Jun 30 Jun ₱2,666,967.85
19 Road Markings 3 days 01 Jul 03 Jul ₱26,544.27
20 White Marking 3 days 01 Jul 03 Jul ₱26,544.27
21 Removal of 3 days 04 Jul 08 Jul ₱87,583.91
Equipment and
22 Materials
Cleaning and Clearing3 days 04 Jul 08 Jul ₱87,583.91

The construction of drainage at Amlac Ville, Payatas B, Quezon City, will employ reinforced concrete
circular culverts to ensure a durable and efficient drainage system. The project, estimated at PHP
36,137,759.02, is scheduled to be completed in 282 days, from June 9, 2024, to July 8, 2025, with
work limited to 8 hours per day on weekdays.

100%

90% S-Curve (Circular Culvert)


80%

70%

60%

50%

40%

30%

20%

10%

0%
6/ /...

7/ ..
7/ ...

8/ ..
8/ ...

9/ ..
9/ ...
9/ /...
10 9/...
10 3/...
11 7/...
11 0/...

12 /...
12 /...

1/ ..
1/ ...

2/ ..
2/ ...

3/ ..
3/ ...
3/ /...
4/ /...
4/ /...
5/ /...
5/ /...

6/ ..
6/ ...

7/ ..
...
/.

/.

/.

/.

/.

/.

/.
.
7/

4/

1/

5/

2/

2/

8/

6/
2/
23

21

18

15

/8

19

16

16
30
13
27
11
25

22
9

4
6/

2
/1
/2
/1
/2

/2

Line: If the S-curve is more like a straight line, it suggests that the project progress is consistent and
linear over time. This could indicate a lack of acceleration or deceleration in progress, which might be
unusual depending on the project type.
S-Curve: Represents the accumulation of costs, labor hours, or other quantities over time. A typical S-
curve shows slow progress at the beginning, rapid progress during the middle phase, and slowing
progress as the project nears completion.

Using the reinforced concrete circular culvert, the project is is planned to be completed in 282 days,
from June 9, 2024, to July 8, 2025, working 8 hours per day on weekdays. The project's S-Curve,
which presents a line-like curve, indicates a steady progress rate throughout the construction period,
ensuring systematic and timely completion of the drainage system.
Bill of Works:
Reinforced Concrete Circular Culvert
Project Name: Construction of Drainage at Amlac Ville Payatas B. Quezon City

Description Cost
Permits and Clearances ₱ 66,683.52
Site Preparation ₱ 67,188.50
Temporarity Facilities ₱ 380,582.34
Excavation ₱ 1,804,586.54
Removing and Hauling of Existing Drainage Pipes ₱ 687,256.16
Gravel Bedding ₱ 321,922.76
Installation of RC Circular Culvert ₱ 28,841,222.63
Sidewalk ₱ 867,829.52
Curb and Gutter ₱ 319,391.02
Manholes ₱ 2,666,967.85
White Marking ₱ 26,544.27
Cleaning and Clearing ₱ 87,583.91

Grand Total ₱ 36,137,759.02

The construction of drainage at Amlac Ville, Payatas B, Quezon City involves the use of reinforced
concrete circular culverts, which are known for their durability and ability to handle significant water
flow. This choice of material ensures a robust and long-lasting drainage system. The project is
estimated to cost PHP 36,137,759.02, covering extensive civil works and installation, aimed at
effectively mitigating flood risks and enhancing the area's water management capabilities.

ID Task Task Name Duration Start Finish Cost


Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025 Qtr 4, 2025 Qtr 1, 2026
Mode Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
1 Construction of Drainage 211 days 09 Jun 31 Mar ₱28,514,471.06
System in Amlac Ville
Payatas Quezon City
2 Permits 6 days 09 Jun 17 Jun ₱66,683.52
3 Permits and Clearances
7 days 09 Jun 17 Jun ₱66,683.52
4 Site Preparation 5 days 18 Jun 24 Jun ₱67,188.70
5 Clearing and Grubbing5 days 18 Jun 24 Jun ₱67,188.70
6 Temfacil Erection 10 days 25 Jun 08 Jul ₱380,582.34
7 Temporary Facilities 10 days 25 Jun 08 Jul ₱380,582.34
8 Excavation of Existing 8 days 09 Jul 18 Jul ₱1,804,586.54
Structures
9 Excavation 8 days 09 Jul 18 Jul ₱1,804,586.54
10 Hauling 15 days 19 Jul 08 Aug ₱687,256.16
11 Removing and 15 days 19 Jul 08 Aug ₱687,256.16
Hauling of Existing
Drainage Pipes
12 Laying of Subcourse 7 days 09 Aug 19 Aug ₱321,922.76
Aggregates
13 Gravel Bedding 7 days 09 Aug 19 Aug ₱321,922.76
14 Installation of Box 157 days 20 Aug 26 Mar ₱25,072,122.86
Culvert
15 Installing of RC Box 143 days 20 Aug 06 Mar ₱21,289,606.93
Culvert
16 Sidewalk 14 days 07 Mar 26 Mar ₱866,907.09
17 Curb and Gutter 13 days 07 Mar 25 Mar ₱316,367.13
18 Manholes 11 days 07 Mar 21 Mar ₱2,599,241.71
19 Road Markings 3 days 24 Mar 26 Mar ₱26,544.27
20 White Marking 3 days 24 Mar 26 Mar ₱26,544.27
21 Removal of 3 days 27 Mar 31 Mar ₱87,583.91
Equipment and
22 Materials
Cleaning and Clearing3 days 27 Mar 31 Mar ₱87,583.91

The construction of drainage at Amlac Ville, Payatas B, Quezon City, will utilize reinforced concrete
box culverts, which offer high durability and effective water management. The project is estimated to
cost PHP 28,514,471.06 and is scheduled to be completed in 211 days, from June 9, 2024, to March
31, 2025, working 8 hours per day on weekdays.
The construction of drainage at Amlac Ville, Payatas B, Quezon City, involves the use of reinforced
concrete box culverts, known for their durability and efficiency in managing water flow. The project
is scheduled to be completed in 211 days, from June 9, 2024, to March 31, 2025, with work occurring
8 hours per day on weekdays. The S-Curve, presenting a line-like curve, indicates a consistent and
steady progress rate throughout the project, ensuring systematic and timely completion of the drainage
system.
Bill of Works:
Reinforced Concrete Box Culvert
Project Name: Construction of Drainage at Amlac Ville Payatas B. Quezon City

Description Cost
Permits and Clearances ₱ 66,683.52
Site Preparation ₱ 67,188.70
Temporarity Facilities ₱ 380,582.34
Excavation ₱ 1,804,586.54
Removing and Hauling of Existing Drainage Pipes ₱ 687,256.16
Gravel Bedding ₱ 321,922.76
Installation of RC Box Culvert ₱ 21,289,606.93
Sidewalk ₱ 866,907.09
Curb and Gutter ₱ 316,367.13
Manholes ₱ 2,599,241.71
White Marking ₱ 26,544.27
Cleaning and Clearing ₱ 87,583.91

Grand Total ₱ 28,514,471.06


Bill of Works:
Reinforced Concrete Circular Culvert
Project Name: Construction of Drainage at Amlac Ville Payatas B. Quezon City

Description Cost
Permits and Clearances ₱ 66,683.52
Site Preparation ₱ 67,188.70
Temporarity Facilities ₱ 380,582.34
Excavation ₱ 1,804,586.54
Removing and Hauling of Existing Drainage Pipes ₱ 687,256.16
Gravel Bedding ₱ 321,922.76
Installation of RC Box Culvert ₱ 21,289,606.93
Sidewalk ₱ 866,907.09
Curb and Gutter ₱ 316,367.13
Manholes ₱ 2,599,241.71
White Marking ₱ 26,544.27
Cleaning and Clearing ₱ 87,583.91

Grand Total ₱ 28,514,471.06

Construction of drainage in Amlac Ville, Payatas B, Quezon City, will employ reinforced concrete
box culverts, recognized for their robust load-bearing capacity and effectiveness in handling
substantial water volumes. The project is budgeted at approximately PHP 28,514,471.06, covering all
essential civil works and installation expenses.

ID Task Task Name Duration Start Finish Cost


Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025 Qtr 4, 2025 Qtr 1, 2026
Mode Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
1 Construction of Drainage 215 days 09 Jun 04 Apr ₱22,450,733.75
System in Amlac Ville
Payatas Quezon City
2 Permits 6 days 09 Jun 17 Jun ₱66,683.52
3 Permits and Clearances
7 days 09 Jun 17 Jun ₱66,683.52
4 Site Preparation 5 days 18 Jun 24 Jun ₱67,188.50
5 Clearing and Grubbing5 days 18 Jun 24 Jun ₱67,188.50
6 Temfacil Erection 10 days 25 Jun 08 Jul ₱380,582.34
7 Temporary Facilities 10 days 25 Jun 08 Jul ₱380,582.34
8 Excavation of Existing 8 days 09 Jul 18 Jul ₱1,804,586.54
Structures
9 Excavation 8 days 09 Jul 18 Jul ₱1,804,586.54
10 Hauling 15 days 19 Jul 08 Aug ₱687,256.16
11 Removing and 15 days 19 Jul 08 Aug ₱687,256.16
Hauling of Existing
Drainage Pipes
12 Laying of Subcourse 7 days 09 Aug 19 Aug ₱321,922.76
Aggregates
13 Gravel Bedding 7 days 09 Aug 19 Aug ₱321,922.76
14 Installation of Open 159 days 20 Aug 28 Mar ₱19,008,385.75
Channel Culvert
15 Installing of Open 145 days 20 Aug 10 Mar ₱17,824,189.10
Channel Culvert
16 Sidewalk 14 days 11 Mar 28 Mar ₱867,829.52
17 Curb and Gutter 13 days 11 Mar 27 Mar ₱316,367.13
18 Road Markings 3 days 28 Mar 01 Apr ₱26,544.27
19 White Marking 3 days 28 Mar 01 Apr ₱26,544.27
20 Removal of 3 days 02 Apr 04 Apr ₱87,583.91
Equipment and
21 Materials
Cleaning and Clearing3 days 02 Apr 04 Apr ₱87,583.91

The construction of drainage at Amlac Ville, Payatas B, Quezon City, will incorporate reinforced
concrete open channel culverts, selected for their efficiency in managing water flow. With an
estimated cost of PHP 22,450,733.75 and a planned duration of 215 days from June 9, 2024, to April
4, 2025, this project aims to improve drainage infrastructure and reduce flood risks in the area.
The construction of drainage at Amlac Ville, Payatas B, Quezon City, will implement reinforced
concrete open channel culverts, designed for efficient water management. With a planned duration of
215 days from June 9, 2024, to April 4, 2025, excluding weekends and limited to 8 hours of work per
day, the S-Curve illustrates a gradual progression throughout the project timeline, ensuring steady and
manageable construction progress.
Bill of Works:
Reinforced Open Channel Culvert
Project Name: Construction of Drainage at Amlac Ville Payatas B. Quezon City

Description Cost
Permits and Clearances ₱ 66,683.52
Site Preparation ₱ 67,188.50
Temporarity Facilities ₱ 380,582.34
Excavation ₱ 1,804,586.54
Removing and Hauling of Existing Drainage Pipes ₱ 687,256.16
Gravel Bedding ₱ 321,922.76
Installation of RC Open Channel Culvert ₱ 17,824,189.10
Sidewalk ₱ 867,829.52
Curb and Gutter ₱ 316,367.13
Manholes ₱ -
White Marking ₱ 26,544.27
Cleaning and Clearing ₱ 87,583.91

Grand Total ₱ 22,450,733.75

The construction of drainage at Amlac Ville, Payatas B, Quezon City, will utilize reinforced concrete
open channel culverts, chosen for their effective water flow management capabilities. The project's
estimated cost of PHP 22,450,733.75 reflects a comprehensive budget covering necessary civil works
and installation. This infrastructure upgrade aims to enhance drainage efficiency and mitigate flood
risks in the area.
Bill of Works:
Reinforced Concrete Open Channel
Project Name: Construction of Drainage at Amlac Ville Payatas B. Quezon City

Description Cost
Permits and Clearances ₱ 66,683.52
Site Preparation ₱ 67,188.50
Temporarity Facilities ₱ 380,582.34
Excavation ₱ 1,804,586.54
Removing and Hauling of Existing Drainage Pipes ₱ 687,256.16
Gravel Bedding ₱ 321,922.76
Installation of RC Open Channel ₱ 17,824,189.10
Sidewalk ₱ 867,829.52
Curb and Gutter ₱ 316,367.13
Manholes ₱ -
White Marking ₱ 26,544.27
Cleaning and Clearing ₱ 87,583.91

Grand Total ₱ 22,450,733.75

Bill of Works:
Reinforced Concrete Box Culvert
Project Name: Construction of Drainage at Amlac Ville Payatas B. Quezon City

Description Cost
Permits and Clearances ₱ 66,683.52
Site Preparation ₱ 67,188.70
Temporarity Facilities ₱ 380,582.34
Excavation ₱ 1,804,586.54
Removing and Hauling of Existing Drainage Pipes ₱ 687,256.16
Gravel Bedding ₱ 321,922.76
Installation of RC Box Culvert ₱ 21,289,606.93
Sidewalk ₱ 866,907.09
Curb and Gutter ₱ 316,367.13
Manholes ₱ 2,599,241.71
White Marking ₱ 26,544.27
Cleaning and Clearing ₱ 87,583.91

Grand Total ₱ 28,514,471.06