CP107 - RAILWAY SYSTEMS AND TRACKWORK

JAKARTA MASS RAPID TRANSIT PROJECT

SCHEDULE FOR JOINT PIT 1/3

NTS 7/150/SBS/3004 - B

7-150/SBS/3004.DWG
NOTES:
CP107 - RAILWAY SYSTEMS AND TRACKWORK
1. AFTER COMPLETE ALL JOINTING WORK INCLUDE FILLING INSULATING OIL TO CABLE JOINT FOR A TIME, WATER LEVEL IS NO PROBLEM
JAKARTA MASS RAPID TRANSIT PROJECT
2. SNAKING IF APPLIED WILL BE DONE OUTSITE CABLE TRENCH, NOT INSIDE DUE TO BENDING RADIUS OF CABLE

3. IF POSSIBLE TO MAKE WATER SEAL FOR CABLE TRENCH IT WILL BE BETTER, AND NO PROBLEM IF IMPOSSIBLE

NTS 7/150/SBS/3004 - B

7-150-SBS-3004.DWG
LINK BOX

Earthing cable

NOTES:
CP107 - RAILWAY SYSTEMS AND TRACKWORK
1. AFTER COMPLETE ALL JOINTING WORK INCLUDE FILLING INSULATING OIL TO CABLE JOINT FOR A TIME, WATER LEVEL IS NO PROBLEM
JAKARTA MASS RAPID TRANSIT PROJECT
2. SNAKING IF APPLIED WILL BE DONE OUTSITE CABLE TRENCH, NOT INSIDE DUE TO BENDING RADIUS OF CABLE

3. IF POSSIBLE TO MAKE WATER SEAL FOR CABLE TRENCH IT WILL BE BETTER, AND NO PROBLEM IF IMPOSSIBLE

NTS 7/150/SBS/3004 - B

7-150-SBS-3004.DWG