11-152110-4800000649-MGC-CIV-ITP-000012_01
11-152110-4800000649-MGC-CIV-ITP-000012_01
Eng. Tamer
Eng. Ahmed Hagar Eng. Nagy Abbas
1 First Issue For Approval 04-07-2024 Ibrahim
(QC Supervisor) (Project Manager)
(QC Manager)
Signatures:
Electronic documents once printed, are uncontrolled and may become out-dated. Refer to Aconex for current revision
04 July, 2024
Document approval
2 Receiving Inspection
Building Plastering accessories, including metal MIR / Manufacturer test reports NEOM Specification 092400 NEOM-MGC-CIV-ICL-001 -
2.1 items Materials Receiving Inspection. H W W
Handling, Storage and Preservation for receiving NEOM Specification 092400 NEOM-MGC-CIV-ICL-001
2.2 Visual inspection. - H
material. S S
3 Execution
WIR \ Visual inspection. NEOM Specification 092400 NEOM-MGC-CIV-ICL-001 W W Before start any Activity must be clearance all
3.1 Surface Preparation - H
key person Civil, Electrical, Mechanical.
NEOM Specification 092400 NEOM-MGC-CIV-ICL-002
3.2 Inspection of Expansion and construction Joints Visual inspection. - H S S
All required openings for mechanical & electrical NEOM Specification 092400 NEOM-MGC-CIV-ICL-002 W W
3.3
services, conduit pipes, plugs shall be WIR / Visual Inspection H
installed and tested prior to plastering.
NEOM Specification 092400 NEOM-MGC-CIV-ICL-001
3.4 Inspection of Moisture Test. WIR / Visual Inspection H H W W
NEOM Specification 092400 NEOM-MGC-CIV-ICL-001
3.5 Inspection of Mock up WIR / Visual Inspection - H W W
Inspection of Mortar Plaster NEOM Specification 092400 NEOM-MGC-CIV-ICL-001 W W
WIR / Visual Inspection H
4 Final Inspection
Neom Specification 034060 NEOM-MGC-CIV-ICL-002 W W
4.1 Inspection of Final check level for Plaster. WIR / Visual Inspection H
General
Neom Specification 034060 NEOM-MGC-CIV-ICL-002 W W
4.2 All Inspection Done as per approved Drawing. WIR / Visual Inspection H
General
Inspection and Test Plan Approval Signature
SUBCONTRACTOR MGC EPM/BECHTEL NEOM Q&E
Name: Name: Asif khan Name: Tamer I Abouzied Name: Name:
GENERAL NOTES:
The first (3) of each inspection or testing activities listed require 100% participation of client site inspection personnel. After this period, client inspection may adjust the level of client participation based on the contractor's performance.
Hold: QA/QC team shall be notified of the schedule of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC Team/Client representative in attendance.
Review: Required qualification/certification/reports shall be submitted for the QA/QC team review and approval.
Witness: QA/QC team shall be notified of the schedule of inspection or test in advance. If the QA/QC Team/Client representative doesn’t come on time for inspection, the activity can proceed.
Legend:
S: Responsible for carrying out random surveillance of inspection or
H: Contractor must not proceed without approval. R: Responsible for reviewing certification or reports. W: Responsible for / and witnessing all inspection or test.
test/Random Check.
Document CODE : NEOM-NEN-SOP-008_FRM11 Revision Code: 01.00 Page 2 of 2
Item
No. ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
A Document Review
NEOM
Store materials inside under cover and keep them dry and
Specificaiton
A1 protected against damage from weather, direct sunlight, surface
092400
contamination, corrosion, construction traffic, and other causes.
Para 1.6.A
NEOM
Specificaiton
A2 Comply with ASTM C 926 requirements.
092400
Para 1.7.A
NEOM
Expanded-Metal Lath: made of austenitic stainless steel according Specificaiton
A3
to ASTM A240/A240M-grade 304. 092400
Para 2.1.A
NEOM
General: Comply with ASTM C 1063 and coordinate depth of trim
Specificaiton
A4 and accessories with thicknesses and number of plaster coats
092400
required.
Para 2.2.A
PLASTER MATERIALS
A. Portland Cement: ASTM C 150, Type I. Use type II where NEOM
used for soil containing moderate Specificaiton 092400
A7
amount of sulfate, or when heat build-up is a concern. Para 2.4
1. Color for Finish Coats: Gray.
B. Lime: Do not use lime
NEOM
Coordinate delivery with installation time to ensure minimum
Specificaiton
A27 holding time for items that are flammable, hazardous, easily
016000
damaged, or sensitive to deterioration, theft, and other losses.
Para 1.6.B.2
NEOM
Inspect products on delivery to ensure compliance with the
Specificaiton
A29 Contract Documents and to ensure that products are
016000
undamaged and properly protected.
Para 1.6.B.4
NEOM
Store products to allow for inspection and measurement of Specificaiton
A30
quantity or counting of units. 016000
Para 1.6.C.1
NEOM
Store materials in a manner that will not endanger Project Specificaiton
A31
structure. 016000
Para 1.6.C.2
NEOM
Store products that are subject to damage by the elements,
Specificaiton
A32 under cover in a weather tight enclosure above ground, with
016000
ventilation adequate to prevent condensation.
Para 1.6.C.3
NEOM
Protect foam plastic from exposure to sunlight, except to extent Specificaiton
A33
necessary for period of installation and concealment. 016000
Para 1.6.C.4
NEOM
Comply with product manufacturer's written instructions for
Specificaiton
A34 temperature, humidity, ventilation, and weather-protection
016000
requirements for storage.
Para 1.6.C.5
NEOM
Specificaiton
A35 Protect stored products from damage.
016000
Para 1.6.C.6
NEOM
Provide a secure location and enclosure at Works site for
Specificaiton
A36 storage of materials and equipment, if any, to be furnished by
016000
Employer. Coordinate location with Engineer.
Para 1.6.C.7
EPM LOGO CONTRACTOR LOGO
Item
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
A Pre Installation Inspeciton
Interior Plasterwork: Maintain room temperatures at greater than
NEOM
4.4 deg C for at least 48 hours before plaster application, and
Specificaiton
A1 continuously during and after application.
092400
1. Avoid conditions that result in plaster drying out during curing
period. Distribute heat evenly; prevent concentrated or uneven Para 1.7.B
Exterior Plasterwork:
NEOM
1. Apply and cure plaster to prevent plaster drying out during
Specificaiton
A2 curing period. Use procedures required by climatic conditions,
092400
including moist curing, providing coverings, and providing barriers
Para 1.7.C
to deflect sunlight and wind.
Examine areas and substrates, with Installer present, and
NEOM
including welded hollow-metal frames,
Specificaiton
A3 cast-in anchors, and structural framing, for compliance with
092400
requirements and other conditions
affecting performance of the Work. Para 3.1.A
NEOM
Proceed with installation only after unsatisfactory conditions have Specificaiton
A4
been corrected. 092400
Para 3.1.B
NEOM
Protect adjacent work from soiling, spattering, moisture Specificaiton
A5
deterioration, and other harmful effects caused by plastering. 092400
Para 3.2.A
NEOM
Prepare solid substrates for plaster that are smooth or that do not
Specificaiton
A6 have the suction capability required to bond with plaster
092400
according to ASTM C 926.
Para 3.2.B
NEOM
Acoustical Sealant: Where required as per the Acoustical Report
Specificaiton
A8 and drawings, seal joints between edges of plasterwork and
092400
abutting construction with acoustical sealant.
Para 3.3.B
Expanded-Metal Lath: Install according to ASTM C 1063.
NEOM
1. Partition Framing and Vertical Furring: Install flat diamond-
Specificaiton
A9 mesh lath.
092400
2. Flat-Ceiling and Horizontal Framing: Install flat diamond-mesh
lath. Para 3.4.A
INSTALLING ACCESSORIES
NEOM
A. Install according to ASTM C 1063 and at locations indicated
Specificaiton
A10 on Drawings.
092400
B. Reinforcement for External Corners:
1. Install lath-type, external-corner reinforcement at exterior Para 3.5
PLASTER APPLICATION
NEOM
A. General: Comply with ASTM C 926.
Specificaiton
A11 1. Do not deviate more than plus or minus 6.4 mm in 3 m from a
092400
true plane in finished plaster surfaces, as measured by a 3-m
Para 3.6.A
straightedge placed on surface.
3. 2. Finish Plaster flush with metal frame and other built- in metal
item or accessories that act as a plaster ground unless otherwise
indicated.
4. 3.Provide plaster surfaces that are ready to receive field -applied
finishes indicated.
NEOM
Bonding Compound: Apply on unit masonry and concrete plaster Specificaiton
A12
bases. 092400
Para 3.6.B
Walls; Base-Coat Mixes for Use over Metal Lath: Scratch and
NEOM
brown coats for three-coat plasterwork, on masonry, on concrete;
Specificaiton
A13 19-mm thickness.
092400
1. Portland cement mixes.
2. Masonry cement mixes. Para 3.6.C
Ceilings; Base-Coat Mixes for Use over Metal Lath: Scratch and
NEOM
brown coats for three-coat plasterwork; 19 mm thick on concrete,
Specificaiton
A14 unless otherwise indicated to meet acoustical and fire
092400
performances indicated in both fire and acoustic report.
1. Portland cement mixes. Para 3.6.D
Walls; Base-Coat Mix: Scratch coat for two-coat plasterwork, 15
NEOM
mm thick on concrete masonry, unless otherwise indicated to
Specificaiton
A15 meet acoustical and fire performances indicated in both fire and
092400
acoustic report..
1. Portland cement mixes. Para 3.6.E
NEOM
Plaster Finish Coats: Apply to provide float finish to match Specificaiton
A16
Engineer's sample. 092400
Para 3.6.F
Concealed Interior Plasterwork:
NEOM
1. Where plaster application will be concealed behind built-in
Specificaiton
A17 cabinets, similar furnishings, and equipment, apply finish coat.
092400
2. Where plaster application will be concealed above suspended
ceilings and in similar locations, finish coat may be omitted. Para 3.6.G
Guide Point are to be 400 mm above from floor level, and 400
A21 General
mm from wall corner / edge.
Contractor NEOM
Construction Representative* PMC/ EPM Representative
Work is Complete and Ready for Inspection: T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:
Item
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
A Final Inspection
PLASTER APPLICATION
A. General: Comply with ASTM C 926. NEOM
1. Do not deviate more than plus or minus 6.4 mm in 3 m from a Specificaiton
A1
true plane in finished plaster surfaces, as measured by a 3-m 092400
straightedge placed on surface. Para 3.6
2. Finish plaster flush with metal frames and other built-in metal
PROTECTION
Remove temporary protection and enclosure of other work. NEOM
Promptly remove plaster from door frames, windows, and other Specificaiton
A3
surfaces not indicated to be plastered. Repair floors, walls, and 092400
other surfaces stained, marred, or otherwise damaged during Para 3.8
plastering.
REMARKS:
REFERENCE DOCUMENTS:
1- NEOM Specificaiton 092400
2- General
Contractor NEOM
Construction Representative* PMC/ EPM Representative
Work is Complete and Ready for Inspection: T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date: