Title:MEPL-EMD-SMP-005
MEENAKSHI ENERGY Page: Page 2 of 6
Date: 22/06/2016
PVT LTD Rev: A
Maintenance
Standard Procedure for Biennial Preventive
Procedure maintenance of 390kV Lightning Arrestor &
Maintenance Surge Counter
Section-Electrical
Table of contents
1 Purpose.........................................................................................
2 Scope............................................................................................
3 Responsibility.................................................................................
4 Safety, Health and Environment Issues..............................................
5 Reference Documents & Protocols.....................................................
6 Special Tools, Spares & Consumables................................................
7 Precautions....................................................................................
8 Procedure......................................................................................
9 Codes and Standards.......................................................................
10 Revision history …………………………………………………………………………………….6
Title:MEPL-EMD-SMP-005
MEENAKSHI ENERGY Page: Page 3 of 6
Date: 22/06/2016
PVT LTD Rev: A
Maintenance
Standard Procedure for Biennial Preventive
Procedure maintenance of 390kV Lightning Arrestor &
Maintenance Surge Counter
Section-Electrical
1 Purpose:
Purpose of this document is to provide a detailed procedures for carrying
out the Preventive maintenance of 390 kV Lightning Arrestor in a safe and
effective manner to improve the reliability and to upkeep the long term
healthiness of the same.
2 Scope:
This document applicable for the bi annual preventive maintenance of all
12 No’s of 390kV Lightning Arrestor installed in the switchyard.
3 Responsibility:
Maintenance Apply for PTW, receive PTW, Guide technicians in
Engineer carrying out the job and clear the PTW.
Area Operator/SCE: Issue of PTW.
Personal Supervisor Supervise the job continuously without leaving the work
area till the work is completed or suspended.
Maintenance Execute the job safely and efficiently as per the
Technician: Standard Maintenance Procedure and fill the protocols.
7 Precautions:
Wear all the required PPE
Ensure the Isolation of correct Breaker and Isolators.
Ensure that live equipment beside is cordoned off.
Follow standard EHS and engineering practices throughout the job.
8 Procedure:
Quarterly:
10 Revision History:
Date Revision# Page # Purpose
22-06-2016 A All First issue