Professional Documents
Culture Documents
06-WMS - False Ceiling -R0
06-WMS - False Ceiling -R0
9PBR/SO/R0
Date:
METHOD STATEMENT
FOR
FALSE CEILING WORK
PROJECT
Reviewed by Approved
Particulars Prepared by Reviewed by
Client by Client
Name
Quality Project
Designation Project Engineer Client Engineer
(site in charge) Manager
Sign
Date
Page 1|6
Document No: Ref/007
9PBR/SO/R0
Date:
Table of Contents
1. Method statement Revision History
2. Scope/Objectives
3. Reference Codes/Tender Specifications
4. Material & Equipment Requirements
5. Responsibilities
6. Procedures /Method to be Employed.
7. Health and Safety Provisions
8. Quality records/documents
9. PMC Approval
2. Scope Objectives
The objective of this method statement is to outline the step-by-step procedure for false
ceiling work control while ensuring adherence to safety and quality standards.
• Gyproc Board
• Gyproc Framing material like Channels, Studs etc.
Page 2|6
Document No: Ref/007
9PBR/SO/R0
Date:
• Gyproc Finishing material like Pro fill/Easi fill 90/ Easi Fill TG60 as per specification
mentioned in WO.
• Right angle,
• Grinding Machine,
• Level Tube, jointing tape etc.
• Drills machines.
• Cut resistant hand gloves for knives working
• Screw drivers, Sand paper, Scrapers
• Scaffolding material to be used as per Safety norms.
Material to be used:
Relevant Indian
S.No. Gypsum
Standard
IS 2095 (Part 1) :
1 Gyproc Board
2011
2 Gyproc- Expert Channel
5. Responsibility:
The Project Manager will be responsible for the delegation of work and to designate the
responsibilities to the concern persons.
1) Mark required level for false ceiling taking reference from FFL as per approved
drawing.
2) start of suspended ceiling works the following works need to be completed and
Page 3|6
Document No: Ref/007
9PBR/SO/R0
Date:
• Protection of flooring
3) Before starting of the first fix services of false ceiling clearance will be obtained from
the contractor, consultant, and MEP subcontractor as the first fix services of M.E.P
above the false ceiling to be completed and approved.
4) An area for mockup will be prepared for inspection and approval before proceeding
with the overall installation.
5) QAQC procedures shall be followed, WIR shall be raised, inspections shall be carried
out at different work tiers and clearances shall be obtained at progressive levels as
mentioned therein.
Page 4|6
Document No: Ref/007
9PBR/SO/R0
Date:
o Before starting of the Gypsum Board fixing services of false ceiling clearance
will be obtained by the contractor, consultant and M.E.P sub contractor,
services of M.Ε.Ρ above the false ceiling to be completed and approved as well
inspection of the suspension frame of false ceilings should be carried out by
the consultant and should be rectified to comments if given by them.
• Before start of the finish works including filler and paint, services of false ceiling
marking will be made by M.E.P sub contractor as per approved shop drawings for all
the electrical points, A/C supply and return air diffuser position, sprinkler points and
position of access panel as per approved coordinated drawings and inspection by the
consultant and contractor to be obtained for final approval of cutting, gypsum boards
shall be cut mechanically
• Peel off the paper at the square edge of the boards
• Apply joint filler in all the joints to fill the gaps
• Apply joint filler over the mesh and screw positions in level of the boards and leave it
to get dry.
• The ceiling shall be finished with an approved paint, minimum two coats of paint on
approved dry wall primer. QAQC engineer will review surface preparation before start
of final finishing and painting works.
• The ceiling shall be paint finish, a primer-stucco-paint finish coat shall be done in
compliance with manufacturers standards, and the ceiling shall be properly cleaned
prior to start of paint finish.
Page 5|6
Document No: Ref/007
9PBR/SO/R0
Date:
8. Quality Records:
Page 6|6