Initial Check / Routine Check (Strike out which is not applicable) Site:
Make & Model: Equipment No.:
10
CHECK ITEMS (to be checked on day of use ) - Complied -√ Not complied - X
Sl. No. DESCRIPTION Date The ON/OFF switch free of concrete and it is working 1 properly.
2 The fan guard in place (for diesel/petrol).
3 The body earthing connected properly.
4-Core cable should be used for 3-Phase Vibrator & 4 provided with 5- pin IP- 44 plug/top. The Cable connected to the Terminal Box & no live parts are 5 exposed.
6 The supply power to the Vibrator routed through RCCB.
7 The power cable free from damage & joints
8 All the parts of machine are properly Bolted.
9 No diesel / oil leakage from machine.
10 The couplings are fitted properly.
11 The vibrator needle works properly.
Equipment is fit for use - Yes / No
Checked by Contractor Safety officer / Supervisor
Checked by SIEMENS Safety Officer / Site In Charge
Note: If any of the above points are not complied, check all the points again after rectification Remarks