Professional Documents
Culture Documents
E-01-1
E-01-1
No 01
ÃÖŸµÖ´Öê¾Ö •ÖµÖŸÖê
B-1 AGREEMENT
TENDER PAPER
NAME OF WORK : Supplying and Installation of Furniture and Required
Amenities for New Thane court Building at Thane.
EXECUTIVE ENGINEER
PUBLIC WORKS DIVISION NO.1, THANE
NAME OF WORK:- Supplying and Installation of Furniture and Required Amenities for New
Thane court Building at Thane.
INDEX
PAGES
Sr. No. DESCRIPTION
From To
1. Disclaimer B --
2. General Information of Contract C D
2. Brief Tender Notice E --
3. Detailed Tender Notice (e-Tendering Procedure) 1 11D
4. Affidavit 12A 12D
5. Articles of Agreement 13 --
6. Scope of Work 14 --
7. Specimen Form and Statements 15 22
8. Printed ‘B-1’ Agreement Form 23 46
9. Schedule ‘A’ 47 --
10. Additional Condition For Materials 48 54
11. Price Variation Clause 55 58
12. Additional General Conditions and Specifications 59 79
13. Annexure ‘A’ (Quality Control Test) 80 81
14. Annexure ‘B’ (Material Test & Frequency) 82 83
15. Additional Specifications 84 88
16. List of apparatus required in the field lab 89 --
17. Model Form of Bank Guarantee Bond 90 --
18. Declaration of Contractor 91 --
19. Integrity Pact 92 96
20. Drawings 97 --
21. Schedule ‘B’ & Item wise Specification 98 --
22. Bar Chart -- --
Issued to : _______________________________________________________________________
Transaction ID : _______________________________________________________________________
DISCLAIMER
1. Detailed Time Table for the various activities to be performed in e-tendering process by the
Tenderer for quoting their offer is given in this Tender Document under "Tender Schedule",
Contractor should carefully note down the cut-off" dates for the carrying out each e-tendering
process / activity.
2. Every effort is being made to keep the Website up to date and running smoothly 24 x 7 by the
Government and the Service Provider. However Government takes no responsibility, and will
not be liable for, the website being temporarily unavailable due to any technical issue at any
point of time.
3. In that event Public Works Department will not be liable or responsible for any damages or
expenses arising from any difficulty, error, imperfection or inaccuracy with this Website, it
includes all associated services, or due to such unavailability of the Website or any part
thereof or any contents or any associated services.
4. Tenderers must follow the time table of e-tenderinq process and get their activities of e-
tenderinq processes done well in advance so as to avoid any inconvenience due to
unforeseen technical problem if any.
5. Public Works Department will not be responsible for any incomplete activity of e-tendering
process of the tenderer due to technical error/ failure of website and it cannot be challenged
by way of appeal, arbitration and in the Court of Law. Contractors must get done all the e-
tendering activities well in advance.
GOVERNEMENT OF MAHARASHTRA
Time stipulated for completion of work : 06 (Six) Calendar Months from the date of
written order to start work, which will include
the monsoon period
2) _____________________________________
3) _____________________________________
Drawing :
DETAILS OF WORK
NAME OF WORK:- Supplying and Installation of Furniture and Required Amenities for New
Thane court Building at Thane.
GOVERNMENT OF MAHARASHTRA
PUBLIC WORKS DEPARTMENT
INVITATION FOR TENDERS
NAME OF WORK:- Supplying and Installation of Furniture and Required Amenities for New Thane
court Building at Thane.
Online percentage rate tenders in 'B-1' Form are invited by the Executive Engineer, Public
Works Division No.1, Thane for the following works from Competent Contractor. The name of
work, estimated cost, earnest money, security deposit, time limit for completion etc. are as under.
Time limit
Sr. Estimated Earnest Security Class of
in Tender
No Name of work Cost Money Deposit Contracto
(Calendar
. (Rupees) (Rupees) (Rupees) r
Months)
Supplying and Installation Rs.14,20,24,895/ (Part-A - Work Portion
1 - Cost)
06 (Six)
of Furniture and Required (Part-B - Royalty Charges Competent months
Rs. 3,56,000/- 7,12,000/- 14,24,000/-
Amenities for New Thane and Testing Charges) Contractor Including
court Building at Thane. Rs.
(Excluding GST) Monsoon
14,23,80,895/-
Tender form, conditions of contract, specifications and contract drawings can be downloaded
from the eTendering portal of Public Works Department, Government of Maharashtra i.e.
https://mahatenders.gov.in after entering the details, payment of Rs. 3,000/- + (18% GST i.e.
Rs.540) Total Rs. 3,540/- (Rupees Three Thousand Five Hundred Forty Only) should be paid Via
SBI MOPS Online Payment Gateway Mode Only. The fees of tender document will be non
refundable. Further information regarding the work can be obtained from the above office.
Affidavit on Rs.100/- stamp paper in prescribed form given in Annexure I sworn before
Executive Magistrate / Notary, Additional Performance Security Deposit (If required), should be
submitted Via SBI MOPS Online Payment Gateway Mode Only. Bids will be opened as per the
Tender Schedule, in the presence of such intending Tenderers or his/ their authorized representatives
who may be present at that time.
TENDERING PROCEDURE: -
1.1. Blank Tender Forms.
1.1.1 Tender Forms can be downloaded from the eTendering portal of Public Works Department,
Government of Maharashtra i.e. https://mahatenders.gov.in Document Tender Fee and
EMD to be paid Via SBI MOPS Online Payment Gateway Mode Only. And upload
successful payment receipt in ENVELOPE NO.1 TECHNICAL BID Documents.
1.1.2 The tender submitted by the tenderer shall be based on the clarification, additional facility
offered (if any) by the Department, and this tender shall be unconditional. Conditional
tenders will be summarily REJECTED.
1.1.3 All tenderers are cautioned that tenders containing any deviation from the contractual terms
and conditions, specifications or other requirements and conditional tenders will be treated
as non responsive. The contractor should clearly mention in forwarding letter that his offer (in
Envelope No.1 & 2) does not contain any condition, deviations from terms and conditions
stipulated in the tender.
1.1.4 Tenderers should have valid III Digital Signature Certificate (DSC) obtained from any
Certifying Authorities.
1.1.5 For any assistance on the use of Electronic Tendering System, the Users may call the below
Toll Free Ph. No. 1800 3070 2232
E-Mail : cppp-support@nic.in
1.2 Special Instructions to the Contractors / Bidders for the e-submission of the bids online
through this tender site: https://mahatenders.gov.in
Bidder must register themselves on https://mahatenders.gov.in portal by clicking “Online
Bidder Enrollment” and then map Digital Signature certificate.
1.2.2 Bidder then login to the site giving User id / Password chosen during registration.
1.2.3 The DSC e-token that is registered should be used by the bidder and should not be misused by
others.
1.2.4 The Bidders can update well in advance, the documents such as certificates, purchase order
details etc., under My Documents option and these can be selected as per tender
requirements and then attached along with bid documents during bid submission.
1.2.5 After downloading / getting the tender schedules, the Bidder should go through them carefully
and then submit the documents as asked, otherwise, the bid will be rejected.
1.2.6 If there are any clarifications, this may be obtained online through the tender site, or through
the contact details. Bidder should take into account of the corrigendum published before
submitting the bids online.
1.2.7 Bidder, in advance, should get ready the bid documents to be submitted as indicated in the
tender schedule and they should be in PDF/XLS/RAR formats. If there is more than one
document, they can be clubbed together.
1.2.8 Document Tender Fee and EMD to be paid via SBI MOPS Online Payment Gateway Mode
only. and upload successful payment receipt in ENVELOPE NO.1 TECHNICAL BID
Documents.
1.2.9 The bidder reads the terms & conditions and accepts the same to proceed further to submit the
bids.
1.2.10 The bidder has to submit the tender document online well in advance before the prescribed
time to avoid any delay or problem during the submission process.
1.2.11 After the bid submission, the acknowledgement number, given by the e-tendering system
should be printed by the bidder and kept as a record of evidence for online submission of bid
for the particular tender.
1.2.12 Document Tender Fee and EMD to be paid via SBI MOPS Online Payment Gateway Mode
only. And upload successful payment receipt in Envelope No.1 Technical Bid Documents.
and BOQ in .xls format file to Uploaded in ENVELOPE NO.2 FINANCIAL BID Documents.
1.2.13 The Tender Inviting Authority (TIA) will not be held responsible for any sort of delay or the
difficulties faced during the submission of bids online by the bidders.
1.2.14 The bidder may submit the bid documents either by online mode through the site
(https://mahatenders.gov.in) as indicated in the tender.
1.2.15 The tendering system will give a successful bid updating message after uploading all the bid
documents submitted & then a bid summary will be shown with the bid no, date & time of
submission of the bid with all other relevant details. The documents submitted by the bidders
will be digitally signed using the DSC e-token of the bidder and then submitted.
1.2.16 The bid summary has to be printed and kept as an acknowledgement as a token of the
submission of the bid. The bid summary will act as a proof of bid submission for a tender
floated and will also act as an entry point to participate in the bid opening date.
1.2.17 Bidder should log into the site well in advance for bid submission so that he submits the bid in
time i.e on or before the bid submission end time. If there is any delay, due to other issues,
bidder only is responsible.
1.2.18 The bidder should see that the bid documents submitted should be free from virus and if the
documents could not be opened, due to virus, during tender opening, the bid is liable to be
rejected.
1.2.19 The time settings fixed in the server side & displayed at the top of the tender site, will be valid
for all actions of requesting, bid submission, bid opening etc., in the e-tender system. The
bidders should follow this time during bid submission.
1.2.20 All the data being entered by the bidders would be encrypted using PKI encryption techniques
to ensure the secrecy of the data. The data entered will not viewable by unauthorized persons
during bid submission & not be viewable by any one until the time of bid opening. Overall, the
submitted tender documents become readable only after the tender opening by the authorized
individual.
1.2.21 The confidentiality of the bids is maintained since the secured Socket Layer 128 bit encryption
technology is used. Data storage encryption of sensitive fields is done.
1.2.21 The bidders are requested to submit the bids through online eTendering System to the TIA well
before the bid submission end date & time (as per Server System Clock).
1.2.22 The bidder should logout of the tendering system using the normal logout option available at
the top right hand corner and not by selecting the (X) option in the browser.
1.2.23 The bidder should upload the Technical Bid in .rar format single file to upload in Technical
cover and then BOQ in .xls format single file to Uploaded in ENVELOPE NO.2 FINANCIAL
BID Documents.
1.4.2 Earnest money of the value of Rs. 7,12,000/- to be paid Via SBI MOPS Online Payment
Gateway Mode Only.
1.4.3 Scanned copy of Valid certificate as a Registered (Furniture) Contractor with the
Government of Maharashtra, Public Works Department in appropriate class and sub
contractor for electric work as may be applicable in original or attested copy thereof (Attested
by a Gazetted Officer).
Scan copy of original documents defining the construction or legal status place of
registration and principal place of business
1.4.5 Scanned copy of The list of Machinery and plants immediately available with the tenderer
for use on this work and list of machinery proposed to be utilized on this work, but not
immediately available and the manner in which it is proposed to be procured (in
Statement No.2 on Page No.16) Good quality centering plates of marine ply wood and sand
washing machine must be available with the contractor.
1.4.5a In case, the department finds such designs or assumptions unacceptable, offer based on
such designs in envelope No.2 shall not be opened by the department and the same will be
recorded. “Notwithstanding” any assumption / stipulation or anything contained in forwarding
note and / or accompanying working drawings in envelope No.1 the provisions / stipulations
in N.I.T., to be read with common set of deviation shall prevail unless specifically changed
and approved by competent authority.
1.4.6 Scanned copy of Proof of appointment of employees including technical personnel by way of valid
Professional Tax Registration certificate in form PT/R/ under section (I) of section 5 of Maharashtra
Sales Tax on Profession, Trade, Callings and employment Act, 1975, rule 3(2) from the Professional
Tax Officer of the concerned District in Maharashtra. The Professional Tax Clearance Certificate with
list of Employees duly attested by Professional Tax Officer shall be enclosed.
1.4.7 Scanned copy of Details of work done during last Five years with the value of work unfinished.
(Information to be given in Statement No.5 on Page No. 21)
1.4.8 Scanned copy of Details of work of similar type and magnitude carried out by the contractor. (in
Statement No.3 on Page No. 19)
1.4.9 Scanned copy of Details of list of works in hand and works tendered for. (Information to be given in
Performa of Statement No.1 on Page No.15)
1.4.10 Scanned copy of Details of Technical Personnel on the rolls of the tenderer.(Information to be given
in Performa of Statement No.4 on Page No. 20)
1.4.11 Scanned copy of Partnership Deed and Power of Attorney, in case of a firm tendering for work. (True
copy attested by a Gazetted Officer.)
After New Plant and initial machinery setup as well as relocation of old machinery to a new site, it is obligatory to obtained Certificate
from Assistant Chief Engineer (Mechanical)
As per instruction given by Government Resolution letter dated 11.5.2022. Contractor who has taken up the tender
Rs.30.00 Lakh and above all works, it is obligatory to submit Technical Manpower Deployment Certificate through
computer portal.
While submitting tender by the contractor, it is essential to submit the details of availability of manpower provided
by contractor as mentioned in Annexure a.
If the contractor's tender is found to be the lowest. An e-mail will be sent to deposit the security deposit for the
work at the end of the tender process. After depositing the security deposit by the contractor, the details of the
manpower will be provided along with the work order by the Department.
To execute the works in P.W.Department, it is mandatory that, the contractor should provide experience and
experience technical manpower for the work executions. Therefore contractor should provide an affidavit on a stamp
paper of Rs.500/ that he will not be raised any kind of claims / compensation for damages against department for
the availability of experience of technical manpower.
QR based Technical Manpower Deployment certificate will be mandatory in the technical envelope under each
tender of the Government Department
Note-1: Financial turnover and cost of completed works of previous year shall be given linear weightage of
10% per year on Rupee value to bring them at 2024-2025 price value.
Note-2: The necessary certificate as mentioned in qualification criteria from Sr. No. (a) to (c) are required to be
obtained from the officer not below the rank of Executive Engineer. A copy of these certificate duly
attested by a Gazetted Officer with his / her name written by him / herself along with availability of
equipments for this work as mentioned in Sr. No. 1.4.4 shall be put in Envelope No.1 only. In absence of
these certificates Envelope No.2 (Financial Bid) shall not be opened.
Note-3: Signature of the officer checking / issuing requisite certificate should bear the concerned
officer.
Note-4: Statement No.1 to 6 on Pages (14) to (22)
Note-5: The abstract of information in Statement No.1 on Page No.14 (Statement showing work done in all
classes of civil engineering construction works during last three years) shall be given in Statement No.5 in
the proforma enclosed on Page No.21. The abstracted Statement No.5 (on Page No.19) need to be
signed by the tenderer or holder of his power of attorney.
(e) Bidders who meet the minimum qualification criteria will be qualified only if their
available bid capacity is more than the total bid value. The available bid capacity
will be calculated as under:-
Required bid capacity is not less than Rs. 14,23,80,895/-
Assessed Available Bid Capacity = [(A x N x 2) - B]
Where.....
A-Maximum Value of Furniture work executed in anyone year during last five years taking into account
the completed as well as ongoing work.
N= Number of years prescribed for completion of the works for which bids are invited.
B= Value of existing Commitments & ongoing works in hand (During period of work under
consideration)
a) Bid Capacity system has been developed for the Contractors in Public Works
Department. The said computer system is available on www.mahapwd.gov.in via
"bidcap.emahapwd.com" Link. As per Government Resolution dated 11.5.2022, for all the
works amounting to Rs.30.00 lakhs above, also those contractors who has taken up the 3
works amounting to Rs.30.00 Lakhs or above in one financial year. If such contractors are
willing to take works in same financial year, it is obligatory while uploading the tender,
contractor should upload Bid Capacity Certificate by using web based system.
c) Contractor has to upload Bid Capacity Certificate along with each tender by using Bid
Capacity computer system. While scrutinizing the bid capacity of the contractor who has
submit the tender in Department. In progress work (as detail in GST R 7), awarded work with
below offer of contractor, work orders shall be available through Computer portal for inspection
to Executive Engineer.
While scrutinizing the bid capacity of the contractors who have submitted tenders for
the works in Department, after deducting, the works held by the contractor & the works
awarded with lowest price etc., if there is sufficient bid capacity, then the further action should
be initiated by the Executive Engineer in context of technical envelope
But if the contractor does not have enough bid capacity, then contacting to the other
department, such contractor is LI Bidder then further action/decision should be taken by the
Department.
f) QR based Bid Capacity certificate will be mandatory in the technical envelope under
each tender of the Government Department.
1.4.14 The contractor shall submit an affidavit (as per format given on Page No.12/13) regarding completeness,
correctness and truthfulness of documents submitted in Envelope No.1
Scanned copy of Affidavit in respect of genuineness of documents contained in the Envelope No.1 in the
prescribed proforma provided with tender set on Stamp Paper of Rs.100/- (Proforma of Affidavit is attached
with Tender)
The affidavit is also to be submitted physically as per schedule given in tender in original and will be the part
and parcel of contract agreement.
Contractor will be solely responsible and liable for action under Indian Penal Code for uploading or physical
submission of any false / fraudulent document / information of Envelope No. 1 & 2.
Contractor will be solely responsible and also liable for action under Indian Penal Code for submission of any
false information, false bills / invoice / vouchers of purchase of material in supporting proof of purchase, proof
of testing / test results and any other required documents submitted by his staff / representative or by himself
or subletting company / contractor during contract period or even after completion of work till finalization of bill
and completion of defect liability period.
If false information / documents are submitted as mentioned above, the contractor ill be blacklisted and if
contract is at initial stage then such contract will be terminated and no any compensation will be payable on
any account to the contractor.
PWD Staff / PWD Officers / Divisional Acounts Officers will not be responsible for any complications due to
submission of false / fraudulent documents by the contractor as mentioned above.
Separate Affidavit shall be submitted for each work in original. Affidavit shall be compulsory Notarified.
Affidavit not confirming to these conditions will not be accepted and Envelope No.2 will not be opened.
1.4.15 Proof of use of specilised machinery for this work owned or hired agreement (Agreement on 100/- Rs. Stamp
paper and it shall be notarized) (Sample of agrrement to be given on Page No.13)
1.4.16 The undertaking of bidder, regarding distance from the plant to the site of work and assurance of maintaining
temperature of bituminous mix as per specification before laying at site. This undertaking has to be uploaded
through online. The undertaking will be verified, if necessary, at the time of opening of tender. If the
undertaking submitted by the bidder is accessed to be incorrect, his bid shall be considered as disqualified.
(Ref : ¨ÉÖ.+.ºÉÉ.¤ÉÉÆ.|ÉÉ.Ê´É., EòÉäEòhÉ, ¨ÉÖ¤Æ É<Ç 400001 ªÉÉÆSÉä {ÉjÉ Gò. (VÉÉ.Gò. ¨ÉÖ+(EòÉä)/ÊxÉÊ´ÉnùÉ ¶ÉÉJÉÉ/562 Ên. 18 ¡äò¥ÉÖ. 2022) ºÉÉ. ¤ÉÉÆ.
ʴɦÉÉMÉ {ÉÊ®ú{ÉjÉ Gò. ºÉÆEòÒhÉÇ 2007/|É.Gò. 257/®úºiÉä-1 Ênù. 21/01/2008 ¨ÉvÉÒ±É +.Gò. 2.1) (Format prescribed on tender
Page No.12A)
1.4.17 If Hot Mix Plant as required under this contract then he should give details of its current location and
undertaking (Affidavit and undertaking in format given on Page No. 12A)
1.4.18 If Contractor intends to shift already owned plant from existing location to the new location as required for this
work. He shall submit additional security as specified in 1.4.19 below. He shall give trial rub on or before 30 th
day from the date of issue of work order. (Applicable for above Rs. 15.00 Lakhs)
1.4.19 In Envelope No.1 the bidder shall submit the scan copy of FDR an additional security of Rs. 10.00 Lakh
(Rupees Ten Lakh Only) in the name of Executive Engineer, Public Works Division No.1, Thane and hard
copy of FDR will be submitted physically. If contractor fails to give grial run after 31 days of issue of said work
order, his above siad additional security shall be encashed without any notice and shall be credited to
Government revenue by the Engineer in charge immediately within 31 days. (Affidavit and undertaking in
format given on Page No. 12B)
1.4.20 BEòÉSÉ EÆòjÉÉ]õnùÉ®úÉxÉä BEòÉ Ê´ÉkÉÒªÉ ´É¹ÉÉÇiÉ iÉÒxÉ ËEò´ÉÉ iªÉÉ{ÉäIÉÉ VÉɺiÉ EòɨÉä PÉäiɱÉÒ +ºÉ±ªÉÉºÉ iªÉÉSªÉɺÉÉ`öÒ iªÉÉ Ê´ÉkÉÒªÉ ´É¹ÉÉÇiÉ
{ÉÖføÒ±É ÊxÉÊ´ÉnùÉƺÉÉ`öÒ ¤ÉÒb÷ Eìò{ÉÒºÉÒ]õÒSÉÒ ¶ÉiÉÇ ±ÉÉMÉÚ ®úɽþÒ±É. ªÉɤÉɤÉiÉ JÉÉiÉ®úVɨÉÉ Eò®úhªÉɺÉÉ`öÒ Ê±É¡òÉ¡òÉ Gò.1 ¨ÉvªÉä SÉɱÉÚ
Ê´ÉkÉÒªÉ ´É¹ÉÉÇiÉ ½þÉiÉÒ PÉäiɱÉ䱪ÉÉ ºÉ´ÉÇ EòɨÉÉÆSÉÒ ÊxÉÊ´ÉnùÉ Ê´É¹ÉªÉEò ¨ÉÉʽþiÉÒ ºÉÉnù®ú Eò®úhÉä EÆòjÉÉ]õnùÉ®úÉºÉ ¤ÉÆvÉxÉEòÉ®úEò ®úɽþÒ±É.
(¨É½þÉ®úɹ]Åõ ¶ÉɺÉxÉ, ºÉÉ. ¤ÉÉÆ. ʴɦÉÉMÉ, ¶ÉɺÉxÉ ¶ÉÖvnùÒ{ÉjÉEò Gò. ºÉÒB]õÒ-2022/|É.Gò.50/<¨ÉÉ-2 Ênù. 12/05/2022).õ
1.4.21 All the documents from Sr.No. 1.4.1 to 1.4.20 shall be given by contractor in Envelope No.1 correctly
and completely otherwise his Envelope No.2 will not be opened.
Even though the Bidder meet the above qualifying criteria, they are subject to be disqualified if they
have made.
Misleading or false representations in the Statements attachments submitted in proof of the qualification
requirements.
And / or
Record of poor performance such as abandoning the works, not properly completing the contract,
inordinate delays in completion, litigation history or financial failures etc.
1.4.22 All corresponding paras pertaining to the tender related subject to Maharashtra P. W. Manual shall be
applicable to this tender.
1.5 ENVELOPE NO.2:- (FINANCIAL BID)
The second envelope clearly marked as “Envelope No.2” shall contain only the main tender including
the Common Set of Conditions / Deviation issued by the Department after the pre-tender Conference. A
tender submitted without this would be considered as invalid.
The Tenderer should quote his offer only through online bidding process in terms of percentage of
estimated rates. He should not quote his offer anywhere directly or indirectly in Envelope No.1.
The contractor shall quote for the work as per details given in the main tender and also based on
the detailed set of conditions issued / Additional stipulations made by the Department as informed
to him by a letter from Chief Engineer / Superintending Engineer after Pre-Tender Conference. His
tender shall be unconditional.
1.6 SUBMISSION OF TENDER:
Refer to Section “Guidelines to Bidders on the operations of Electronic Tendering System of
Public Works Department” for details.
1.6.1 Submission of Hard Cord copy of online Submitted copy.
Tenderer must submit the Hard Cord copy of online submitted copy to the Concerned Executive
Engineer’s / Superintending Engineer’s Office / Chief Engineer’s Office.
The bidder shall submit the Hard Copy in "Sealed Envelope" of Technical and Financial Bids as
specified in NIT after the online submission of Bid ("Bid Lock") within 72 hrs. If problem arise
during e-tendering process the hard copy in sealed envelope will be opened.
(a) Documents submitted online in Envelope No.1 & 2 are put in separate Envelope as Envelope
No.1 (Technical Bid) and Envelope No.2 (Financial Bid) respectively and sealed properly.
(b) The above two sealed Envelope No.1 and 2 shall again put together in one common cover
and sealed. The name of work, online tender Notice Number (i.e. SGN) and Name and full
address of Tenderer with Mobile Number shall be mentioned on the said common cover
marked sealed common cover properly covers corners.
(c) The above common cover containing Envelope No.1 & 2 must be submit to the Executive
Engineer, Public Works Division No.1, Thane within the time and date specified in Tender
Schedule Flashed on Website portal on working days (during office hours) only.
(d) No delay on account of any cause will be enterained for the receipt said Hard Copy.
(e) If Tenderer fails or neglect to submit Hard Copy his online offer (Tender) will be considered
for further tendering procedure.
1.7.C +ÉÌlÉEò näùEòÉ®ú =PÉb÷±ªÉÉxÉÆiÉ®ú, ÊxÉÊ´ÉnùÉ |ÉÊGòªÉäiÉ ÊxÉÊ´ÉnùÉ |ÉÉ{iÉ EÆòjÉÉ]õnùÉ®úxÉä +lÉ´ÉÉ +xªÉ EÆòjÉÉ]õnùÉ®úÉÆxÉÒ JÉÉä ]õÒ /
¤ÉxÉÉ´É]õ EòÉMÉnù{ÉjÉä iÉÉÆÊjÉEò ʱɡòÉ¡ªÉÉºÉ VÉÉbÖ÷xÉ ÊxÉÊ´ÉnùÉ Ê¨É³ý´ÉhªÉÉSÉä / ÊxÉÊ´ÉnùÉ |ÉÊGòªÉäiÉ ¦ÉÉMÉ PÉäiɱªÉÉSÉä
ÊxÉnù¶ÉÇxÉÉºÉ +ɱªÉÉºÉ iÉÉiEòɳý ½ªÉÉ EÆòjÉÉ]õnùÉ®úÉºÉ / EÆòjÉÉ]õnùÉ®ú ¦ÉÉMÉÒnùÉ®úÒºÉ +lÉ´ÉÉ EÆò{ÉxÉÒºÉ / ºÉƪÉÖCiÉ EÆò{ÉxÉÒ
(JV / LLP / Pvt. Ltd / Public Limited Company) ¤ÉºÉ±ªÉÉºÉ ºÉƤÉÆvÉÒiÉ EÆò{ÉxÉÒºÉ 15 Ênù´ÉºÉÉÆxÉÒ xÉÉä]õÒºÉ näù>ðxÉ
EòɳýªÉÉ ªÉÉnùÒiÉ ]õÉEòhªÉÉSªÉÉ {ÉÊ®ú{ÉjÉEòÉSÉä |Éɯû{É ¶ÉɺÉxÉÉºÉ ºÉÉnù®ú Eò®úÉ´Éä ´É ¨ÉÆVÉÖ®ú Eò¯ûxÉ PÉä>ðxÉ (Website) ´É®ú
´ÉÞkÉ{ÉjÉÒªÉ |ÉʺÉvnùÒ näù>ðxÉ, |ÉlÉ¨É 3 ´É¹ÉÉÇSÉä EòɱÉÉ´ÉvÉÒ EòÊ®úiÉÉ, ¨É½þÉ®úɹ]Åõ ¶ÉɺÉxÉ ºÉÉ´ÉÇVÉÊxÉEò ¤ÉÉÆvÉEòÉ¨É Ê´É¦ÉÉMÉÉSªÉÉ
EòɳªÉÉ ªÉÉnùÒiÉ ºÉ¨ÉÉʴɹ]õ Eò®úÉ´Éä ´É {ÉÊ®ú{ÉjÉEò ÊxÉMÉǨÉxÉÉSªÉÉ ÊnùxÉÉÆEòÉ{ÉɺÉÖxÉ 3 ´É¹Éæ ºÉÉ´ÉÇVÉÊxÉEò ¤ÉÉÆvÉEòÉ¨É Ê´É¦ÉÉSªÉÉ
ÊxÉÊ´ÉnùÉ |ÉÊGòªÉäiÉ ¦ÉÉMÉ PÉähªÉÉºÉ |ÉÊiɤÉÆvÉ ®úÉʽþ±É, ½þÒ +]õ EÆò{ÉxÉÒSÉÉ ¨ÉɱÉEò / ºÉÆSÉɱÉEò / ¦ÉÉMÉÒnùÉ®ú ªÉÉÆxÉÉ ºÉƪÉÖCiÉ ´É
º´ÉiÉÆjÉ{ÉhÉä (Combined and Several Independent Liability) ±ÉÉMÉÖ ®úɽþÒ±É.
1.8 EARNEST MONEY :
(i) Earnest money of minimum Rs. 7,12,000/- shall be paid Via SBI MOPS Online
Payment Gateway Mode Only.
(ii) After Tender opening, the EMD of the unsuccessful bidder will be returned to account
provided by the bidder during the bid preparation as given in challan under
Beneficiary Account Number.
Earnest Money in the form of cheques or any other form except above will not
be accepted.
(iii) The amount will be refunded to the unsuccessful tenderers on deciding about the
acceptance or otherwise of the tender. In case of successful tenderer, it will be
refunded on his paying initial Security Deposit and completing the tender documents
in form B-1.
(iv) In case of Joint Venture, Earnest money Exemption certificate in individual capacity
will not be accepted. Earnest money shall be be paid Via SBI MOPS Online
Payment Gateway Mode Only.. The Security Deposit, additional security deposit
etc. in the form of T.D.R. / F.D.R. issued in the name of Joint Venture Company
drawn by scheduled bank having branches in Maharashtra and endorsed, in the
name of Executive Engineer, Public Works Division No.1, Thane for the period of
one year will be considered.
The amount of the (Additional Performance Security) Bank Guarantee / Demand Draft/
Fixed Deposit Receipt shall be calculated by the tenderer in accordance with the following
manner.
1.9(A1) If the tenderer had quoted below the estimated rates, the Additional Performance Security
shall be paid additionally as mentioned below.
a) If the offer submitted is below schedule ‘B’ 1% of the estimated coat put to tender
rates by more than 1% but less than 10% of
the estimated cost put to tender.
b) If below more than 10% of the estimated cost 1% of the estimated cost put to tender
put to tender plus an amount equal to the percentage
by which the offer is below 10% of the
estimated cost put to tender. (e.g. if the
offer is 14% below, the Performance
Security will be 1% + (14%-10%)= 5% of
the estimated cost put to tender.
c) If offer is more than 15% below For balance amount, submission of
double amount in the form of Bank
Guarantee / Demand Draft/ Fixed Deposit
Receipt is mandatory for example 19%
below rate
Upto 10% below rate = 01%
Upto 15% below rate = 05%
(15% - 10%)
Upto 19% below rate = 08%
(19% - 15%) = 4% x 2 = 08%
Total = 14%
Note:- (i) For more than 10% below and upto 15% below ‘b’ is applicable.
(ii) For more than 15% below ‘c’ is applicable
1.9(A2) The Bank Guarantee / Demand Draft/ Fixed Deposit Receipt shall be valid beyond one month
after expiry of Defect Liability Period.
1.9(A3) In case it is found that the document Bank Guarantee / Demand Draft/ Fixed Deposit Receipt
submitted by tenderer are false or misleading, his earnest money shall be forfeited. Also the
registration of the tenderer shall be suspended for the period of one year. Additionally legal
action may be initiated agaist the tenderer.
1.9(A4) The work order shall be given to the concerned tenderer after the clearance of the Bank
Guarantee / Demand Draft/ Fixed Deposit Receipt submitted by him.
1.9(A6) Non submission of Additional Performance Deposit and performance security or submission
of less amount of the Additional Performance Security deposit shall be liable to summarily
rejection of his tender.
1.9(A7) After complete tender procces, if bidder submitted the Demand Draft with tender, then the
lowest bidder will be submit requisite amountof Bank Guarantee and then Demand Draft will
be refunded with tender.
1.14 CORRECTION:
No corrections shall be made in the tender documents. Any corrections that are to be made,
shall be made by crossing the incorrect portion and writing the correct portions above with the
initials of tenderer.
1.17(a) The Tenderers shall be presumed to have carefully examined the drawings, conditions and
specifications of the work and have fully acquainted themselves with all details of the site, the
conditions of rock and its joints, pattern, river, weather characteristics, labour conditions and
in general with all the necessary information and data pertaining to the work, prior to
tendering for the work.
1.17(b) The data whatsoever supplied by the Department alongwith the tender documents are meant
to serve only as guide for the tenderers while tendering and the Department accepts no
responsibility whatsoever either for the accuracy of data or for their comprehensiveness.
1.17(b) The data whatsoever supplied by the Department alongwith the tender documents are meant
to serve only as guide for the tenderers while tendering and the Department accepts no
responsibility whatsoever either for the accuracy of data or for their comprehensiveness.
1.17(c) The quarries for extraction of metal, murum etc. provided in the sanctioned estimate are as
per survey conducted by the Department. The Contractor should however examine these
quarries and see whether full quantity of materials required for execution of the work strictly
as per specification are available in these source before quoting the rates. In case the
materials are not available due to reasons whatsoever, the contractor will have to bring the
materials from any other source with no extra cost to Government. The rates quoted, should
therefore be for all leads and lifts from wherever the materials are brought at site of work and
inclusive of royalty to be paid to the Revenue Department by the Contractor.
1.19 The tenderer may, in the forwarding letter, mention any points he may wish to make clear but
the right is reserved to reject the same or the whole of the tender if the same becomes
conditional tender thereby.
1.20 The contractor or the firms tendering for the work shall inform the Department if they appoint
their authorized Agent on the work.
1.21 No foreign exchange will be released by the Department for the purchase of plants and
machinery for the work by the Contractor.
1.22 Any dues arising out of contract will be recovered from the contractor as arrears of Land
Revenue, if not paid amicably. Moreover, recovery of Government dues from the Contractors
will be effected from the payment due to the Contractor from any other Government works
under execution with them.
1.23 All pages of tender documents, conditions, specifications, correction slips etc. shall be
initialed by the tenderer. The tender should bear full signature of the tenderer, or his
authorized power of Attorney holder in case of a firm.
1.24 The Income Tax at prevailing rates including surcharge or percentage in force from time to
time or at the rate as intimated by the competent Income Tax authority shall be deducted from
bill amount whether measured bill, advance payment or secured advance.
1.25 The successful tenderer will be required to produce, to the satisfaction of the specified
concerned authority a valid concurrent license issued in his favour under the provisions of the
Contract Labour (Regulation and Abolition) Act 1970 for starting the work. On failure to do so,
the acceptance of the tender shall be liable to be withdrawn and also liable for forfeiture of the
earnest money.
1.26 The tenderer shall submit the list of apprentices engaged by the Contractor under Apprentice
Act.
1.28 CASHLESS
Contractor shall submit a certificate to the effect that “All the payments to the labour / staff are
made in bank accounts of staff linked to Unique Identification Number (AADHAR CARD)” The
certificate shall be submitted by the contractor within 60 days from the commencement of
contract. Iof the time period of contract is less than 60 days then such certificate shall be
submitted within 15 days from the date of commencement of contract. (Vide Marathi
G.R.No.Tender-2016 / C.R.20 / Shikana / Bldg-2, Dated 09/12/2016)
The prospective tenderers are free to ask for any additional information or clarification
either in writing or orally concerning the work, and the reply to the same will be given by
the Chief Engineer / Superintending Engineer, in writing and this clarification referred
to as Common Set of Conditions/Deviations (C.S.D.), shall form part of tender documents
and which will also be common and applicable to all tenderers. The point/points if any
raised in writing and/or verbally by the contractor in pre-tender conference and not finding
place in C.S.D. issued after the pre- bid conference, is/are deemed rejected. In such
case the provision in NIT shall prevail. No individual correspondence shall be made
thereafter with the contractor in this regard.
1.31 Payment of Security Deposit by Bank Guarantee and Online Bank Guarantee
Verification : If the contractor wishes to deposit security deposit by Bank Guarantee after
tender approval then it is mandatory for contractor to verify the Bank Guarantee by paying
verification fees of Rs. 1000/- + GST through the line provided below
(https://onlinebg.emahapwd.com).
1.32 It is Compulsory to pay appropriate amount of stamp duty to revenue authority by contractor
after acceptance of tender as per Government of Maharashtra, Revenue and Forest
Departement Circular No. ¨ÉÖpùÉE
Æ ò-2020/+xÉÖ.Gò. 01-2016/|É.Gò. 218/¨É-1 (vÉÉä®úhÉ), ¨ÉÆjÉɱɪÉ, ¨ÉÖƤÉ<Ç-
400032 Ênù. 18 ¨ÉÉSÉÇ 2021.
1.33 A The cost of civil construction work should be shown separately as Part-A and also the cost of
quality control test result and royalty charges shown as Part-B. It is mandatory to submit on
the cost of civil construction work i.e. Part-A also for test fee, ownership etc. Clause-36,
Clause No. 47-A(f), Clause No. 56.
(7) ʴɨÉÉ ºÉÆSÉɱÉxÉÉ±ÉªÉ ªÉÉ EòɪÉÉDZɪÉÉºÉ Ê´É¨Éɽþ{iÉÉ ®úCEò¨É |ÉÉ{iÉ ZÉɱªÉÉxÉÆiÉ®ú EÆòjÉÉ]õÒ EòɨÉÉSÉÉ Ê´É¨ÉÉ
ªÉÉäMªÉ ʴɨÉÉ{ÉjÉEòÉJÉɱÉÒ =iÉ®úʴɱªÉɺÉƤÉÆvÉÒSªÉÉ {ÉÞ¹`ö¬lÉÇ Ê´É¨ÉÉ{ÉjÉEò +lÉ´ÉÉ Ê´É¨ÉÉ Îº´ÉEòÉ®ú{ÉjÉ
ÊxÉMÉÇʨÉiÉ Eò®úhªÉÉiÉ ªÉä<DZÉ.
(8) VÉ®ú EòÉähÉiªÉɽþÒ EÆòjÉÉ]õnùÉ®úÉxÉä ={É®úÉäCiÉ {ÉvnùiÉÒxÉä ʴɨÉÉ{ÉjÉ xÉ PÉäiÉÉ {É®úº{É®ú ʴɨÉÉ EÆò{ÉxÉÒEòbÚ÷xÉ
ʴɨÉÉ{ÉjÉ PÉäiɱªÉÉºÉ ºÉnù®ú ʴɨÉÉ{ÉjÉEäò +OÉÉÁ +ºÉiÉÒ±É.
(9) VÉä´½þÉ EÆòjÉÉ]õÒ EòɨÉÉSÉä ¨ÉÚ±ªÉ ¯û. 50 EòÉä]õÒ{ÉäIÉÉ +ÊvÉEò +ºÉä±É, iªÉÉ´Éä³ýÒ EÆòjÉÉ]õnùÉ®úÉxÉä ʴɨÉÉ
ºÉÆSÉɱÉxÉɱɪÉÉSªÉÉ xÉÉʨÉEòÉ|Éʴɹ`öºÉÚSÉÒ (Empanelled) ºÉ´ÉæIÉEòÉÆEòbÚ÷xÉ Ê´É¨ÉÉ{ÉÚ´ÉÇ iÉ{ÉɺÉhÉÒ +½þ´ÉɱÉ
(Pre-Insurance Inspection of Risks) |ÉÉ{iÉ Eò¯ûxÉ Ê´ÉʽþiÉ xɨÉÖxªÉÉiÉÒ±É Ê´É¨ÉÉ|ɺiÉÉ´É{ÉjÉ Ê´É¨ÉÉ
ºÉÆSÉɱÉxÉɱɪÉÉEòbä÷ ºÉÉnù®ú Eäò±ªÉÉxÉÆiÉ®ú ´É ʴɨÉɽþ{iÉÉ ®úCEò¨É |ÉnùÉxÉ Eäò±ªÉÉxÉÆiÉ®ú ºÉƤÉÆÊvÉiÉ
EÆòjÉÉ]õnùÉ®úÉºÉ EÆòjÉÉ]õÒEòɨÉÉSÉÉ Ê´É¨ÉÉ lÉä]õ +lÉ´ÉÉ ºÉ½þʴɨÉÉ ºÉä´ÉÉ {ÉvnùiÉÒJÉɱÉÒ =iÉ®úÊ´ÉhªÉɺÉÉ`öÒ
{ÉÖføÒ±É EòɪÉÇ´ÉɽþÒ Ê´É¨ÉÉ ºÉÆSÉɱÉxÉɱɪÉÉuùÉ®äú Eäò±ÉÒ VÉÉ<DZÉ. EÆòjÉÉ]õnùÉ®úÉxÉä EÆòjÉÉ]õÒ EòɨÉÉSÉÉ Ê´É¨ÉÉ
ºÉÆSÉɱÉxÉɱɪÉÉEòbä÷ +lÉ´ÉÉ Ê´É¨ÉÉ ºÉÆSÉɱÉxÉɱɪÉÉSªÉÉ ¨ÉÉxªÉiÉäxÉä ºÉ½þʴɨÉÉ ºÉä´ÉÉ (Co Insurance Cum
Servicing) {ÉviÉiÉÒJÉɱÉÒ =iÉ®úʴɱÉÉ xɺÉä±É iÉ®ú {ÉÊ®úSUäônù Gò¨ÉÉÆEò (Eò) xÉÖºÉÉ®ú, ºÉƤÉÆÊvÉiÉ |ÉEòiÉÉÇ
ªÉÉÆxÉÒ EÆòjÉÉ]õnùÉ®úÉSªÉÉ näùªÉEòÉiÉÚxÉ BEÚòhÉ EÆòjÉÉ]õÒ ¨ÉÖ±ªÉÉSªÉÉ ¯û. 1% |ɨÉÉhÉä ºÉä´ÉÉEò®úɺɽþ ®úCEò¨É
´É³ýiÉÒ Eò¯ûxÉ Ê´É¨ÉÉ ºÉÆSÉɱÉxÉɱɪÉÉEòbä÷ VɨÉÉ Eò®úhªÉÉSÉÒ nùIÉiÉÉ PªÉÉ´ÉÒ.
(¤É) ʴɨÉÉ ºÉÆSÉɱÉxÉɱɪÉÉSÉä ¨ÉÖJªÉÉ±ÉªÉ ¨ÉÖ¤Æ É<Ç iɺÉäSÉ, |ÉÉnäùʶÉEò EòɪÉÉÇ±ÉªÉ xÉÉMÉ{ÉÚ®ú ªÉälÉä +ɽäþ. ʴɨÉÉ
ºÉÆSÉɱÉxÉɱɪÉÉSÉä EòɪÉÇIÉäjÉ ºÉÆ{ÉÚhÉÇ ¨É½þÉ®úɹ]ÅõÉiÉ Ê´ÉJÉÖ®ú±Éä±Éä +ɽäþ. ʴɨÉÉ ºÉÆSÉɱÉxÉɱɪÉÉEòbä÷
={ɱɤvÉ +ºÉ±Éä±Éä ¨ÉxÉÖ¹ªÉ¤É³ý Ê´ÉSÉÉ®úÉiÉ PÉäiÉÉ, EÆòjÉÉ]õÒ EòɨÉÉSÉÉ Ê´É¨ÉÉ ´ªÉ´É½þÉ®ú ½þÉiÉɳýiÉÉxÉÉ
¨ÉªÉÉÇnùÉ ªÉäiÉ +ɽäþiÉ. iɺÉäSÉ, ¨É½þÉ®úɹ]ÅõÉSªÉÉ +ÆiÉMÉÇiÉ ¦ÉÉMÉɨÉvªÉä +ºÉ±É䱪ÉÉ EÆòjÉÉ]õnùÉ®úÉºÉ Ê´É¨ÉÉ
ºÉÆSÉɱÉxÉɱɪÉÉSªÉÉ ¨ÉÖ¤Æ É<Ç +lÉ´ÉÉ xÉÉMÉ{ÉÚ®ú ªÉälÉÒ±É EòɪÉÉDZɪÉÉEòbä÷ ºÉÆ{ÉEÇò ºÉÉvÉÚxÉ Ê´É¨ÉÉ =iÉ®úÊ´ÉhÉä
EòɽþÒ |ɺÉÆMÉÒ +ÉÌlÉEòoù¹]õ¬É iɺÉäSÉ, ´Éä³ýä +¦ÉÉ´ÉÒ ºÉÉä<ÇSÉä ½þÉäiÉ xÉɽþÒ. +¶ÉÉ |ɺÉÆMÉÒ EÆòjÉÉ]õÒ
EòɨÉÉSÉÉ Ê´É¨ÉÉ ´ªÉ´É½þÉ®ú ½þÉiÉɳýhªÉɺÉÉ`öÒ Ê´É´É®úhÉ{ÉjÉ ÊxɽþÉªÉ (Schedule Policy) ʴɨÉÉ
=iÉ®úÊ´ÉhªÉÉSÉÒ EòɪÉÇ{ÉvnùiÉ JÉɱÉÒ±É|ɨÉÉhÉä +ɽäþ.
(+) ¯û. 25 ±ÉÉJÉÉ{ÉäIÉÉ Eò¨ÉÒ EÆòjÉÉ]õÒ ¨ÉÖ±ªÉÉSÉä EòÉ¨É EÆòjÉÉ]õnùÉ®úÉºÉ ºÉÖ{ÉÚnÇù Eäò±Éä +ºÉ±ªÉÉºÉ ºÉƤÉÆÊvÉiÉ
EÆòjÉÉ]õnùÉ®úÉSªÉÉ |ÉlÉ¨É näùªÉEòÉiÉÚxÉ BEÚòhÉ EÆòjÉÉ]õÒ EòɨÉÉSªÉÉ ¨ÉÖ±ªÉÉSªÉÉ ¯û. 0.50% ªÉÉ nù®úÉxÉä
ʴɨÉɽþ{iªÉÉSÉÒ ®úCEò¨É Eò{ÉÉiÉ Eò¯ûxÉ EòɪÉÉÇnùä¶ÉÉSªÉÉ |ÉiÉҺɽþ ʴɨÉÉ ºÉÆSÉɱÉxÉɱɪÉÉEòbä÷ “ʴɨÉÉ
ºÉÆSÉɱÉEò, ¨É½þÉ®úɹ]Åõ ®úÉVªÉ, ¨ÉÖ¤Æ É<Ç” ªÉÉÆSªÉÉ xÉÉ´Éä vÉxÉÉEò¹ÉÇ / vÉxÉÉnäù¶É +lÉ´ÉÉ OÉÉºÉ |ÉhÉɱÉÒuùÉ®äú
JÉɱÉÒ±É Ê´É´É®úhÉ{ÉjÉÉiÉ nùÉxä É |ÉiÉÒiÉ 30 Ênù´ÉºÉÉiÉ ºÉÉnù®ú Eò®úhÉä +ɴɶªÉEò +ɽäþ.
+. EÆòjÉÉ]õnùÉ®úÉSÉä EÆòjÉÉ]õÒ EòɪÉÉÇnùä¶É EÆòjÉÉ]õÒ EÆòjÉÉ]õÒ ¯û. 0.50%
Gò. xÉÉ´É EòɨÉÉSÉä xÉÉ´É Gò. EòɨÉÉSÉÉ EòɨÉÉSÉä |ɨÉÉhÉä ʴɨÉÉ
EòɱÉÉ´ÉvÉÒ ¨ÉÖ±ªÉ ½þ{iªÉÉSÉÒ ®úCEò¨É
1 2 3 4 5 6 7
ºÉƤÉÆÊvÉiÉ |ÉEòiÉÉÇ Ê´É¨Éɽþ{iÉÉ ®úCEò¨É EÆòjÉÉ]õnùÉ®úÉSªÉÉ näùªÉEòÉiÉÚxÉ ´É³ýiÉÒ Eò¯ûxÉ |ÉnùÉxÉ
Eò®úÒiÉ +ºÉ±ªÉɨÉÖ³äý 30 Ênù´ÉºÉÉSÉÉ EòɱÉÉ´ÉvÉÒ IɨÉÉÊ{ÉiÉ Eò®úhªÉÉSÉÉ +ÊvÉEòÉ®ú ʴɨÉÉ ºÉÆSÉɱÉxÉɱɪÉÉSÉä
ʴɦÉÉMÉ |ɨÉÖJÉ Ê´É¨ÉÉ ºÉÆSÉɱÉEò ªÉÉÆSÉäEòbä÷ ®úɽþÒ±É.
ºÉƤÉÆÊvÉiÉ |ÉEòiÉÉÇ (Principal) ªÉÉÆSÉäEòbÚ÷xÉ Ê´É¨ÉÉ ºÉÆSÉɱÉxÉɱɪÉÉºÉ Ê´É´É®úhÉ{ÉjÉÉiÉÒ±É
iÉ{ÉʶɱÉɺɽþ |ÉÉ{iÉ ZÉɱªÉÉ´É®ú, Ê´É´É®úhÉ{ÉjÉÊxɽþÉªÉ BEòSÉ Ê´É¨ÉÉ{ÉjÉEò (Schedule Policy) ÊxÉMÉÇʨÉiÉ
Eò®úhªÉÉiÉ ªÉä<DZÉ. ªÉÉ Ê´É¨ÉÉ{ÉjÉEòÉ +ÆiÉMÉÇiÉ EÆòjÉÉ]õnùÉ®úÉSªÉÉ ºÉÆ{ÉÚhÉÇ VÉÉäJÉÒ¨É Ê´É¨ÉÉ{ÉjÉEòÉJÉɱÉÒ ËEò´ÉÉ
ºÉÉMÉ®úÒ / ºÉÉ`ö´ÉhÉ-=¦ÉÉ®úhÉÒ Ê´É¨ÉÉ{ÉjÉEòÉJÉɱÉÒ EÆòjÉÉ]õÒ EòɨÉÉSÉÉ Ê´É¨ÉÉ =iÉ®úʴɱÉÉ VÉÉhÉÉ®ú
+ºÉ±ªÉÉxÉä, iªÉÉ Ê´É¨ÉÉ{ÉjÉEòÉSªÉÉ +]õÒ ´É ¶ÉiÉÔxÉÖºÉÉ®ú ʴɨÉÉUôjÉÉSÉÉ ±ÉÉ¦É |ÉEòiÉÉÇ ªÉÉÆxÉÉ Ê¨É³ýhÉÉ®ú
+ɽäþ. iɺÉäSÉ, ºÉƤÉÆÊvÉiÉ EÆòjÉÉ]õÒ EòɨÉÉSªÉÉ Ê`öEòÉhÉÒ +{ÉPÉÉiÉɨÉÖ³äý EòɨÉMÉÉ®úÉÆxÉÉ ½þÉähÉÉ®äú xÉÖEòºÉÉxÉ
¸ÉʨÉEò xÉÖEòºÉÉxÉ ¦É®ú{ÉÉ<Ç Ê´É¨ÉÉ{ÉjÉEòÉSªÉÉ +]õÒ ´É ¶ÉiÉÔxÉÖºÉÉ®ú κ´ÉEòɯûxÉ Ê´É¨ÉÉ nùÉ´Éä ÊxÉEòɱÉÒ
EòÉfø±Éä VÉÉiÉÒ±É.
(¤É) VÉä´½þÉ EÆòjÉÉ]õnùÉ®úÉºÉ ¯û. 25õ ±ÉÉJÉÉ{ÉäIÉÉ +ÊvÉEò ®úEò¨ÉäSÉä EÆòjÉÉ]õÒ EòÉ¨É ºÉÖ{ÉÚnùÇ Eäò±Éä +ºÉ±ªÉɺÉ,
EÆòjÉÉ]õnùÉ®úÉxÉä ʴɨÉÉ ºÉÆSÉɱÉxÉɱɪÉÉSªÉÉ EòɪÉÉDZɪÉÉEòbä÷ |ÉiªÉIÉ ºÉÆ{ÉEÇò ºÉÉvÉÚxÉ Ê´É½þÒiÉ xɨÉÖxªÉÉiÉÒ±É
ʴɨÉÉ|ɺiÉÉ´É{ÉjÉ ºÉÉnù®ú Eò®úhÉä +ÊxÉ´ÉɪÉÇ +ɽäþ. ʴɨÉÉ ºÉÆSÉɱÉxÉɱɪÉÉEòbä÷ ʴɨÉɽþ{iÉÉ ®úEò¨ÉäSÉÉ ¦É®úhÉÉ
Eäò±ªÉÉ´É®ú ºÉƤÉÆvÉÒiÉ EÆòjÉÉ]õnùÉ®úÉºÉ Ê´É¨ÉÉ Îº´ÉEòÉ®ú{ÉjÉ / ʴɨÉÉ{ÉjÉ ÊxÉMÉÇʨÉiÉ Eò®úhªÉÉiÉ ªÉä<DZÉ.
(Eò) VÉä´½þÉ EÆòjÉÉ]õÒ EòɨÉÉSÉä ¨ÉÚ±ªÉ ¯û{ɪÉä 25 ±ÉÉJÉÉ{ÉäIÉÉ VÉɺiÉ +ºÉä±É +ÉÊhÉ VÉ®ú EÆòjÉÉ]õnùÉ®úÉxÉä
EÆòjÉÉ]õÒ EòɨÉÉSÉÉ Ê´É¨ÉÉ, ʴɨÉÉ ºÉÆSÉɱÉxÉɱɪÉÉEòbä÷ ʴɨÉÉ =iÉ®úÊ´ÉhªÉÉSÉÉ {ÉÖ®úÉ´ÉÉ ¨½þhÉÚxÉ Ê´É¨ÉÉ
ºÉÆSÉɱÉxÉɱɪÉÉxÉä ÊxÉMÉÇʨÉiÉ Eäò±Éä±Éä ʴɨÉÉ Îº´ÉEòÉ®ú{ÉjÉ / ʴɨÉÉ{ÉjÉEò ºÉƤÉÆÊvÉiÉ |ÉEòiÉÉÇ (Principal)
ªÉÉÆxÉÉ ºÉÉnù®ú Eäò±Éä xÉɽþÒ. iÉ®ú ºÉƤÉÆÊvÉiÉ |ÉEòiÉÉÇ ªÉÉÆxÉÒ BEÚòhÉ EÆòjÉÉ]õÒ EòɨÉÉSªÉÉ ¨ÉÖ±ªÉÉSªÉÉ ¯û.1 %
ªÉÉ nù®úÉxÉä EÆòjÉÉ]õnùÉ®úÉSªÉÉ |ÉlÉ¨É näùªÉEòÉiÉÚxÉ ®úCEò¨É ´É³ýiÉÒ Eò¯ûxÉ Ê´É¨ÉÉ ºÉÆSÉɱÉxÉɱɪÉÉEòbä÷
vÉxÉÉEò¹ÉÇ / vÉxÉÉnäù¶É +lÉ´ÉÉ OÉÉºÉ |ÉhÉɱÉÒuùÉ®äú EÆòjÉÉ]õnùÉ®úÊxɽþÉªÉ JÉɱÉÒ±É Ê´É´É®úhÉ{ÉjÉɺɽþ 30
Ênù´ÉºÉÉiÉ ½þºiÉÉÆiÉ®úÒiÉ Eò®úhªÉÉSÉÒ nùIÉiÉÉ PªÉÉ´ÉÒ.
+. EÆòjÉÉ]õnùÉ®úÉSÉä EÆòjÉÉ]õÒ EòɪÉÉÇnùä¶É EÆòjÉÉ]õÒ EÆòjÉÉ]õÒ ¯û. 1% |ɨÉÉhÉä
Gò. xÉÉ´É EòɨÉÉSÉä xÉÉ´É Gò. EòɨÉÉSÉÉ EòɨÉÉSÉä ʴɨÉÉ ½þ{iªÉÉSÉÒ
EòɱÉÉ´ÉvÉÒ ¨ÉÖ±ªÉ ®úCEò¨É
1 2 3 4 5 6 7
(1) |ÉEòiÉÉÇ ªÉÉÆxÉÒ EÆòjÉÉ]õnùÉ®úÉSªÉÉ näùªÉEòÉiÉÚxÉ 0.50 ËEò´ÉÉ 1 ]õCEäò|ɨÉÉhÉä ʴɨÉɽþ{iÉÉ ®úCEò¨É VɨÉÉ Eäò±ÉÒ
+ºÉ±ªÉÉºÉ –
(+) VÉ®ú EÆòjÉÉ]õnùÉ®úÉxÉä ʴɨÉÉ ºÉÆSÉɱÉxÉɱɪÉÉEòbä÷ EÆòjÉÉ]õÒ EòɨÉÉSÉÉ Ê´É¨ÉÉ =iÉ®úʴɱªÉÉSÉÉ {ÉÖ®úÉ´ÉÉ ¨½þ hÉÚxÉ
ʴɨÉÉ{ÉjÉEò / ʴɨÉÉκ´ÉEòÉ®ú{ÉjÉ |ÉEòiÉÉÇ ªÉÉÆxÉÉ ºÉÉnù®ú xÉ Eäò±ªÉɺÉ, EÆòjÉÉ]õnùÉ®úÉSªÉÉ |ÉlÉ¨É näùªÉEòÉiÉÚxÉ
¶ÉɺÉxÉ {ÉÊ®ú{ÉjÉEòÉxÉÖºÉÉ®ú ʴɨÉÉ ½þ{iªÉÉSÉÒ ®úCEò¨É Eò{ÉÉiÉ Eò¯ûxÉ Ê´É¨ÉÉ ºÉÆSÉɱÉxÉɱɪÉÉEòbä÷ VɨÉÉ Eäò±ÉÒ
+ºÉä±É ´É iªÉÉxÉÆiÉ®ú EÆòjÉÉ]õÒ EòɨÉÉSÉÉ EòɱÉÉ´ÉvÉÒ Ê´ÉºiÉÉ®úÒiÉ ZÉɱÉÉ +ºÉä±É iÉ®ú, ʴɺiÉÉ®úÒiÉ
EòɱÉÉ´ÉvÉÒEò®úÒiÉÉ Ê´É¨ÉÉUôjÉÉSÉÉ ±ÉÉ¦É näùhªÉɺÉÉ`öÒ JÉɱÉÒ±É EòÉä¹]õEòÉiÉ xɨÉÖnù Eò®úhªÉÉiÉ +ɱÉ䱪ÉÉ
nù®úÉxÉÖºÉÉ®ú BEÚòhÉ EÆòjÉÉ]õÒ ¨ÉÖ±ªÉÉ´É®ú ®úCEò¨É Eò{ÉÉiÉ Eò¯ûxÉ Ê´É¨ÉÉ ºÉSÉɱÉxÉɱɪÉÉEòbä÷ Ê´ÉʽþiÉ
{ÉvnùiÉÒxÉä VɨÉÉ Eò®úhªÉÉiÉ ªÉÉ´ÉÒ.
(¤É) 24 ¨ÉʽþxªÉÉ{ÉäIÉÉ +ÊvÉEò EòɱÉÉ´ÉvÉÒ +ºÉ±ªÉÉºÉ ºÉƤÉÆÊvÉiÉ |ÉEòiÉÉÇ / EÆòjÉÉ]õnùÉ®ú ªÉÉÆxÉÒ |ÉiªÉIÉ
ʴɨÉÉ ºÉÆSÉɱÉxÉɱɪÉɶÉÒ ºÉÆ{ÉEÇò ºÉÉvÉÚxÉ ªÉɤÉɤÉiÉSÉÒ EòɪÉÇ´ÉɽþÒ Eò®úhªÉÉiÉ ªÉÉ´ÉÒ.
(Eò) EÆòjÉÉ]õÒ EòɨÉÉSªÉÉ ¨ÉÖ±ªÉɨÉvªÉä ´ÉÉfø ZÉɱªÉɺÉ, EÆòjÉÉ]õÒ EòɨÉÉSªÉÉ ´ÉÉføÒ´É ¨ÉÖ±ªÉÉ´É®ú ¶ÉɺÉxÉ
{ÉÊ®ú{ÉjÉEòÉxÉÖºÉÉ®ú 0.50 / 1 ]õCEäò iɺÉäSÉ Ê´ÉºiÉÉ®úÒiÉ EòɱÉÉ´ÉvÉÒEòÊ®úiÉÉ ´É®úÒ±É EòÉä¹]õEòÉiÉ
xɨÉÚnù Eò®úhªÉÉiÉ +ɱÉ䱪ÉÉ nù®úÉxÉÖºÉÉ®ú BEÚòhÉ EÆòjÉÉ]õÒ ¨ÉÖ±ªÉÉ´É®ú (´ÉÉføҺɽþ) ®úCEò¨É VɨÉÉ
Eò®úhªÉÉiÉ ªÉÉ´ÉÒ.
(2) EÆòjÉÉ]õnùÉ®úÉxÉä EÆòjÉÉ]õÒ EòɨÉÉSÉÉ Ê´É¨ÉÉ ºÉÆSÉɱÉxÉɱɪÉÉEòbä÷ =iÉ®úʴɱÉÉ +ºÉ±ªÉÉºÉ -
EÆòjÉÉ]õnùÉ®úÉxÉä EÆòjÉÉ]õÒ EòɨÉÉSÉÉ Ê´É¨ÉÉ, ʴɨÉÉ ºÉÆSÉɱÉxÉɱɪÉÉEòbä ÷ =iÉ®úʴɱªÉɤÉɤÉiÉSÉÉ {ÉÖ®úÉ´ÉÉ
¨½þhÉÚxÉ Ê´É¨ÉÉ ºÉÆSÉɱÉxÉɱɪÉÉxÉä ÊxÉMÉÇʨÉiÉ Eäò±Éä±Éä ʴɨÉÉ{ÉjÉEò / ʴɨÉÉκ´ÉEòÉ®ú{ÉjÉ |ÉEòiÉÉÇ ªÉÉÆxÉÉ
ºÉÉnù®ú Eäò±Éä +ɽäþ. +¶ÉÉ EÆòjÉÉ]õÒ EòɨÉÉSÉÉ ¨ÉÖ±ªÉɨÉvªÉä ´ÉÉfø ZÉɱÉÒ +ºÉä±É ËEò´ÉÉ EòɨÉÉSÉÉ
EòɱÉÉ´ÉvÉÒ Ê´ÉºiÉÉ®úÒiÉ ZÉɱÉÉ +ºÉä±É, iÉ®ú ºÉƤÉÆÊvÉiÉ EÆòjÉÉ]õnùÉ®úɱÉÉ ´ÉÉføÒ´É ¨ÉÖ±ªÉÉSÉÉ /
EòɱÉÉ´ÉvÉÒ Ê´É¨ÉÉ =iÉ®úÊ´ÉhªÉɺÉÉ`öÒ |ÉEòiÉÉÇ ªÉÉÆxÉÒ ÊxÉnæù¶É ÊxÉMÉÇʨÉiÉ Eò®úÉ´ÉäiÉ. VÉ®ú, ºÉƤÉÆÊvÉiÉ
EÆòjÉÉ]õnùÉ®ú ªÉÉÆxÉÒ ªÉɤÉɤÉiÉSÉÉ {ÉÖ®úÉ´ÉÉ |ÉEòiÉÉÇ ªÉÉÆxÉÉ ºÉÉnù®ú Eäò±ÉÉ xÉɽþÒ, +¶ÉÉ |ɺÉÆMÉÒ, |ÉEòiÉÉÇ
ªÉÉÆxÉÒ EÆòjÉÉ]õnùÉ®úÉSªÉÉ näùªÉEòÉiÉÚxÉ {ÉÊ®úSUäô 1(+) ¨ÉvÉÒ±É EòÉä¹]õEòɨÉvªÉä xɨÉÚnù Eò®úhªÉÉiÉ
+ɱÉ䱪ÉÉ nù®úÉxÉÖºÉÉ®ú ®úCEò¨É Eò{ÉÉiÉ Eò¯ûxÉ Ê´É¨ÉÉ ºÉÆSÉɱÉxÉɱɪÉÉEòbä÷ VɨÉÉ Eò®úhªÉÉiÉ ªÉÉ´ÉÒ.
´É®úÒ±É|ɨÉÉhÉä Eò{ÉÉiÉ Eò®úhªÉÉiÉ +ɱÉä±ÉÒ Ê´É¨ÉÉ ½þ{iªÉÉSÉÒ ®úCEò¨É JÉɱÉÒ±É
Ê´É´É®úhÉ{ÉjÉÉiÉÒ±É iÉ{ÉʶɱÉɺɽþ 2 |ÉiÉÒiÉ Ê´É¨ÉÉ ºÉÆSÉɱÉxÉɱɪÉÉEòbä÷ “ʴɨÉÉ ºÉÆSÉɱÉEò, ¨É½þÉ®úɹ]Åõ
®úÉVªÉ, ¨ÉÖ¤Æ É<Ç” ªÉÉÆSªÉÉ xÉÉ´Éä vÉxÉÉnäù¶É / vÉxÉÉEò¹ÉÇ +lÉ´ÉÉ OÉÉºÉ |ÉhÉɱÉÒuùÉ®äú (GRAS-
Government Receipt Accounting System) |ÉEòiÉÉÇ ªÉÉÆxÉÒ VɨÉÉ Eò®úhÉä +ɴɶªÉEò +ɽäþ.
iªÉÉxÉÖºÉÉ®ú, Ê´É´É®úhÉ{ÉjÉÊxɽþÉªÉ ºÉɨÉÉ<ÇEò ʴɨÉÉ{ÉjÉEò / {ÉÞ¹`öÉÆEòxÉ ÊxÉMÉÇʨÉiÉ Eò®úhªÉÉiÉ ªÉä<DZÉ. ÷
+. EÆòjÉÉ]õnùÉ®úÉSÉä EÆòjÉÉ]õÒ EòɪÉÉÇnäù¶É EÆòjÉÉ]õÒ EÆòjÉÉ]õÒ Eò{ÉÉiÉ Eäò±Éä±ÉÒ
Gò. xÉÉ´É EòɨÉÉSÉä Gò. EòɨÉÉSÉÉ EòɨÉÉSÉä ʴɨÉÉ ½þ{iªÉÉSÉÒ
xÉÉ´É EòɱÉÉ´ÉvÉÒ ¨ÉÖ±ªÉ ®úCEò¨É
1 2 3 4 5 6 7
1.35 ,
. /
, ,
NHAI (National Highways
Authority of India)
+3 ,
1.36 As per Government in Revenue and Forest Department Circular dated 18.03.2021 & as per
prevailing act of Maharashtra Mundrak Adhiniyam in accordance to this work contract,
required stamp duty to be incurred and essential preceding documents along with the
required stamp duty should be submitted to District Registrar (Class I) / Or Collector Stamp
in response to which obtained stamp duty Receipt should be submit to this office
immediately before execution of work.
EòɨÉÉSÉä xÉÉÆ´É -
ºÉnù®úÒ±É EòɨÉÉiÉ ½þÉì]õ ʨÉCºÉ ºÉÆnù¦ÉÉÇiÉÒ±É EòɨÉä ¨ÉÒ / +ɨ½þÒ ½þÉì]õ ʨÉCºÉ {±ÉÉÆ]õ vÉÉ®úEòÉEòb÷Ú÷xÉ ÊxÉÊ´ÉnäùiÉÒ±É +]õÒ ´É
¶ÉiÉÔxÉÖºÉÉ®ú Eò¯ûxÉ näùhÉäºÉ ¤ÉÉÆvÉÒ±É +ɽäþ / +ɽþÉäiÉ.
----------------------------------------------------------------------------------------------------------------------------------------------------
EòɨÉÉSÉä xÉÉÆ´É -
ªÉÉ ºÉiªÉ|ÉÊiÉYÉÉ ±ÉäJÉÉuÉ®äú ʱɽÚþxÉ näùiÉÉä EòÒ, ´É®úÒ±É Ê´É¹ÉªÉÉiÉÒ±É EòɨÉɨÉvÉÒ±É b÷ÉƤɮúÒEò®úhÉÉSÉä EòÉ¨É ½þÉì]õ ʨÉCºÉxÉä Eò¯ûxÉ
näùhÉäºÉ ¤ÉÉÆvÉÒ±É +ɽäþ. iɺÉäSÉ b÷É¤Æ É®ú {±ÉÉÆ]õ -------------------- ªÉÉ Ê`öEòÉhÉÒ +ºÉÖxÉ EòɨÉÉSªÉÉ Ê`öEòÉhÉÉ{ÉɺÉÖxÉSÉä +ÆiÉ®ú
---------- ÊEò.¨ÉÒ. +ºÉÖxÉ ¶ÉɺÉxÉ ºÉÉ.¤ÉÉÆ. ʴɦÉÉMÉ {ÉÊ®ú{ÉjÉEò Gò. ºÉÆÊEòhÉÇ-2007/|É.Gò.257/®úºiÉä-1 Ênù. 21/01/2008
xÉÖºÉÉ®ú b÷ÉƤɮú ʨÉCºÉSÉä iÉÉ{ɨÉÉhÉ ªÉÉäMªÉ iªÉÉ ¨ÉÉxÉÉÆEòÉ|ɨÉÉhÉä ®úÉJÉÖxÉ `äö´ÉhªÉÉiÉ ªÉä<DZÉ. iɺÉäSÉ ºÉnù®úSªÉÉ ºÉiªÉiÉÉ
|ɨÉÉhÉ{ÉjÉÉiÉ jÉÖ]õÒ +Éfø³ý±ªÉÉºÉ ¨É±ÉÉ ÊxÉÊ´ÉnùÉ |ÉÊGòªÉäiÉÖxÉ +{ÉÉjÉ `ö®úÊ´ÉhªÉÉºÉ ½þ®úEòiÉ xÉɽþÒ.
(Affidavit and undertaking on stamp paper of Rs. 100/- registered before the
notary or Executive Magistrate)
...................................................................................................................................................
we have our owned Drum Mix Plant / Batch Mix Plant located at ............................. in
working condition. This plant is located at such a location that required hot mix material can
reach work site with appropriate & specified temperature as per latest Govt. Circular
OR
We don’t have our owned Drum Mix Plant / Batch Mix Plant within vicinity of
We undertake to shift our owned Drum Mix Plant / Batch Mix Plant & Machine
such a location it will satisfy all the specification of MORT&H within 31 days receipt of work
order. We are enclosing a F.D.R. for Rs. 10.00 Lakhs as a security for same. In case if not
shifted plants & machinery and not able to give trial run the additional security shall be
{ÉÊ®úʶɹ]õ-1
(ʱɡòÉ¡òÉ Gò.1 =PÉb÷±ªÉÉxÉÆiÉ®ú, ¶ÉɺÉxÉ ÊxÉhÉǪÉÉxÉÖºÉÉ®ú ÊxÉÊ´ÉnäùºÉÉä¤ÉiÉ VÉÉäb÷±É䱪ÉÉ JªÉÉä]õ¬É EòÉMÉnù{ÉjÉÉ
ºÉÆnù¦ÉÉÇiÉ ºÉÆ{ÉÖhÉÇ{ÉhÉä ÊxÉÊ´ÉnùÉ ºÉÉnù®ú Eò®úhÉÉ®äú EÆòjÉÉ]õnùÉ® VɤÉɤÉnùÉ®ú ®úɽþiÉÒ±É. ºÉÉ´ÉÇVÉÊxÉEò ¤ÉÉÆvÉEòɨÉ
ʴɦÉÉMÉÉSÉä ÊxÉÊ´ÉnùÉ UôÉxÉxÉÒ Eò®úhÉÉ®äú +ÊvÉEòÉ®úÒ ´É Eò¨ÉÇSÉÉ®úÒ VɤÉɤÉnùÉ® ®úɽþhÉÉ® xÉɽþÒiÉ)
xɨÉÖxÉÉ ºÉiªÉ|ÉÊiÉYÉÉ {ÉjÉ
(¯û.100/- SªÉÉ º]ìõ¨{É {Éä{É®ú´É®ú)
¨ÉvªÉä VÉÒ EòÉMÉnù{ÉjÉä ºÉÉnù®ú Eäò±ÉÒ +ɽäþiÉ iÉÒ JÉ®Ò, ¤É®úÉä¤É®ú ´É {ÉÚhÉÇ +ɽäþiÉ. iªÉɨÉvªÉä EòÉähÉiªÉɽþÒ jÉÖ]Ò, SÉÖEòÉ xÉɽÒiÉ
ªÉÉSÉÒ ¨ÉÒ JÉÉjÉÒ Eäò±Éä±ÉÒ +ºÉÖxÉ +ºÉä ¶É{ÉlÉ{ÉÚ´ÉÇEò JÉɱÉÒ±É +]õÒ ´É ¶ÉlÉԺɽþ ¨ÉÉxªÉ Eò®úÒiÉ +ɽäþ. ªÉÉ EòÉMÉnù{ÉjÉÉƨÉvªÉä
EòÉ½Ò SÉÖEòÒSÉÒ, Ênù¶ÉɦÉÚ±É Eò®úhÉÉ®Ò, JÉÉä]õÒ ´É iɺÉäSÉ +{ÉÚhÉÇ ¨ÉÉʽþiÉÒ +Éfø³ý±ªÉÉºÉ ¨ÉÒ ¦ÉÉ®úiÉÒªÉ nÆùb÷ºÉÆʽþiÉÉ +ÆiÉMÉÇiÉ
EòɪÉnäù¶ÉÒ®ú EòɪÉÇ´ÉɽþÒºÉ {ÉÉjÉ ®úɽþÒxÉ.
1. VÉ®ú EÆòjÉÉ]õ EòɱÉÉ´ÉvÉÒ nù®ú¨ªÉÉxÉ, ¨ÉÒ ¨ÉÉZªÉÉ EòɪÉÉDZɪÉÉxÉä ËEò´ÉÉ ¨ÉÉZªÉÉ Eò¨ÉÇSÉÉ-ªÉÉÆxÉÒ ºÉÉ´ÉÇVÉÊxÉEò ¤ÉÉÆvÉEòɨÉ
ʴɦÉÉúMÉɱÉÉ EòÉähÉiÉÒ½þÒ JÉÉä]õÒ ¨ÉÉʽþiÉÒ ËEò´ÉÉ näùªÉEòÉ ºÉ¨É´ÉäiÉ iɺÉäSÉ {ÉjÉ ´ªÉ´É½þÉ®úÉiÉ JÉÉä]õÒ / ¤ÉxÉÉ´É]õ
ºÉÉʽþiªÉ JÉ®äúnùÒSÉÒ EòÉMÉnù{ÉjÉä ºÉÉnù®ú Eäò±ÉÒ +ºÉ±ªÉɺÉ, ¨ÉÒ ¦ÉÉ®úiÉÒªÉ nÆùb÷ºÉÆʽþiÉÉ +ÆiÉMÉÇiÉ EòɪÉnäù¶ÉÒ®ú
EòɪÉÇ´ÉɽþÒºÉ {ÉÉjÉ ®úɽþÒxÉ.
2. VÉ®ú EÆòjÉÉ]õ EòɱÉÉ´ÉvÉÒ nù®ú¨ªÉÉxÉ +ÉÊhÉ EòÉ¨É ºÉ¨ÉÉ{iÉÒ xÉÆiÉ®ú, +ÆiÉÒ¨É näùªÉEò näùhÉÉSªÉÉ iÉÉ®úJÉä{ɪÉÇiÉ ºÉÉnù®ú
Eäò±Éä±ÉÒ EòÉähÉiÉä½þÒ EòÉMÉnù{ÉjÉä JÉÉä]õÒ / ¤ÉxÉÉ´É]õ ËEò´ÉÉ ¡òºÉ´ÉÒ +Éfø³ý±ªÉɺÉ, ¨ÉÒ ¦ÉÉ®úiÉÒªÉ nÆùb÷ºÉÆʽþiÉÉ
+ÆiÉMÉÇiÉ EòɪÉnäù¶ÉÒ®ú EòɪÉÇ´ÉɽþÒºÉ {ÉÉjÉ ®úɽþÒxÉ.
3. VÉ®ú EòÉ¨É ºÉ¨ÉÉ{iÉÒú xÉÆiÉ®ú nùɹä É nùÉʪÉi´É EòɱÉÉ´ÉvÉÒ nù®ú¨ªÉÉxÉ ËEò´ÉÉ iªÉÉxÉÆiÉ®ú EòÉähÉiªÉɽþÒ ´Éä³ýÒ, EòÉähÉiÉÒ½þÒ
¨ÉɽþÒiÉÒ ËEò´ÉÉ EòÉMÉnù{ÉjÉä JÉÉä]õÒ / ¤ÉxÉÉ´É]õ ËEò´ÉÉ ¡òºÉ´ÉÒ ËEò´ÉÉ Ênù¶ÉɦÉÚ±É Eò®úhÉÉ®úÒ +Éfø³ý±ªÉɺÉ, ¨ÉÒ
¦ÉÉ®úiÉÒªÉ nÆùb÷ºÉÆʽþiÉÉ +ÆiÉMÉÇiÉ EòɪÉnäù¶ÉÒ®ú EòɪÉÇ´ÉɽþÒºÉ {ÉÉjÉ ®úɽþÒxÉ.
ANNEXURE - 1
AFFIDAVIT
(on Rs.100/- Stamp Paper)
1. I am liable for action under Indian Penal Code for submission of any false / fraudulent
paper / information submitted in envelope no.1
2. I am liable for action under Indian Penal Code if during contract period and defect liability
period, any false information, false bill of purchases supporting proof of purchase, proof of
testing submitted by my staff, subletting company or by myself, I will be liable for action
under Indian Penal Code.
3. I am liable for action under Indian Penal Code if any paper are found false / fraudulent
during contract period and even after the completion of contract (finalisation of final bill)
(Signature of Contractor)
(Seal of Company)
(This document should be on Original Stamp Paper of Rs.100/- not on Xerox Copy)
This Agreement of Hire of Machinery made and executed at _____________on this, the __________
Day of the month of _________ 20________ BETWEEN :-
1) Shri / M/s.__________________________________________
A Sole Trading concern Pvt. Ltd. Co. / Public Ltd. Co, / Partnership firm registered under the
provisions of respective Acts in force and having his / their Office situated. at———————------- and
managed by Shri -_________________________
who is a,
i) Sole Proprietor of the above mentioned concern.
ii) Partner of the above mentioned partnership firm.
iii) Holder of power of attorney of the above mentioned firm, Executive Director or Manager of the
above mentioned company as approved by the present board of Director of the above mentioned
Company, Hereinafter for the sake of brevity referred to as “The Owner” (Which expression shall,
unless it be repugnant to the meaning of context thereof, mean and included the firm of all partners of
the firm, the company at material time and their successors).
Party of the First Part.
AND
2) Shri / M/s _________________________________________ Contractors.
A sole trading concern / Private Limited Company / Public Limited Company / Partnership firm
registered under the provisions of respective acts in force and registered Government contractors
registered in appropriate dass with Government of Maharashtra Having his / their office situated at —
———— and managed by Shri. _________________
Who is a,
i) Sole Proprietor of the above mentioned concern.
ii) Partner of the above mentioned partnership firm.
iii) Holder of power of attorney of the above mentioned firm, Executive Director or Manager of the
above mentioned company. Hereinafter for the sake of brevity referred to as “The Hirer” (Which
expression shall, unless it be repugnant to the meaning of context thereof, mean and included the
firm of all partners of the firm, the company at material time and their successors).
Party of the Second Part.
Where in the party of the first part herein is an absolute owner of the
___________________________ Name of machine / s and to substantiate or establish it the
documentary evidence in token of voucher enclosed. Where as party of the second part herein is a
registered Government Contractors as stated in appropriate class with Government of Maharashtra.
AND where as the party of the second part is or is likely to submit the tender for
______________________ Executive Engineer / Superintending Engineer,
AND WHERE AS the party of the second part intends to use the machinery of the said work as is
being stipulated by the Department and desirous of taking the one / s on monthly hire charges basis.
AND WHERE AS the party of the first part, is desirous of giving the machinery on hire charges basis
to the party of the second part.
AND WHERE AS to these presents are desirous of recording the terms and of the agreement, reduce
the same to writing. Now therefore these articles of agreement witness as under.
1) ______________________________
2) ______________________________
SCOPE OF WORK
NAME OF WORK:- Supplying and Installation of Furniture and Required Amenities for New
Thane court Building at Thane.
STATEMENT NO.1
WORKS IN HAND
SPECIMEN FORM
Probable
Name and Time Other
Name of work Tendered Date when
Sr.No. address limit Relevant
amount decision is
of client details if any
expected
1 2 3 4 5 6 7
SPECIMEN FORM
Note: This is only a standard form. Details are to be furnished in this format in form of typewritten
statements, which shall be uploaded online in enclosed No.1
STATEMENT NO.2
SPECIMEN FORM
Note 1: This is only a standard form. Details are to be furnished in this format. In form of typewritten
statements which shall be uploaded online in envelope No.1
Note 2: List of Machinery proposed to be utilized on this work but not immediately available and the
manner in which it is proposed to be procured shall be given in above statement No.2
(Applicable for works for which use of modern machineries for concreting and asphalting is specified)
Proforma for information regarding availability of machinery required for this work. (Ref. 1.4.12 Page No.13) is
given below.
QUESTION: 1
Is the above machinery at Sr. No. (A) is owned or hired by you and available with you immediate on this work?
If 'Yes' give following information.
Names of
works on Output in Quantity in tonnes of Hot
Type of Number
which Location tonnes of Mix balance for execution Remarks
Machine of Units
deployed at mix per day on work in hand
present
1 2 3 4 5 6
Along with this statement Contractor shall submit their proof of ownership or lease of machinery (i.e. Attested
copies of invoices) as well as the Scanned copy of Valid Certificate issued by the Assistant Chief
Engineer (Mech.) of Public Works Department to the effect that these Machineries are in "Efficient" -
"Working condition" and Plant with MORT&H Specifications must be enclosed in Envelope No. 1 in absence of
this this Certificate, Envelope No.2 will not be opened.
STATEMENT SHOWING DETAILS OF CONCRETE BATCH MIX PLANT AVAILABLE WITH THE
TENDERER FOR THIS WORK
STATEMENT NO.3
Name and
address of Total
Name the Place Date of Cost Principal
Sr. Agreement Tendered Date of
of organisation and Commen- of Features
No. No. Cost Completion
work for whom country cement work in Brief
the work done
was done
1 2 3 4 5 6 7 8 9 10
SPECIMEN FORM
Note: This is only a standard form. Details are to be furnished in this format. In form of typewritten
statements which shall be uploaded online in envelope No. 1
STATEMENT NO.4
Period for
Experience
Whether which the
of
Designation Name of working in person is
Sr. No. Qualification execution Remarks
Person field or working
of similar
office with the
work
tenderer
1 2 3 4 5 6 7 8
SPECIMEN FORM
Note:- This is only a standard form. Details are to be furnished in this format. In form of typewritten
statements which shall be uploaded online in envelope No. 1
STATEMENT NO.5
2019-20
2020-21
2021-22
2022-23
2023-24
of tender/ Commen- Remarks
No. ent executed
Work tendered cement
2024-25
cost
(Rs. In
Lakhs)
1 2 3 4 5 6 7 8 9 10 11 12 13 14
SPECIMEN FORM
Note: This is only a standard form. Details are to be furnished in this format. In form of typewritten
statements which shall be enclosed in envelope No. 1
STATEMENT NO.6
STATEMENT SHOWING WORK DONE IN ALL CLASSES OF CIVIL ENGINEERING
CONSTRUCTION DURING LAST FIVE YEARS
2019-20
2020-21
2021-22
2022-23
2023-24
be executed
(Rs. in lakhs)
(Rs. in lakhs.)
1 2 3 4 5 6 7 8 9 10 11 12 13
SPECIMEN FORM
Signature Signature
REMARKS
QUANTITY OF WORK PERFORMED (Indicate
YEAR NAME
Contract
-- Reference)
1 2 3 4 5 6 6 7
2019-20
2020-21
2021-22 SPECIMEN FORM
2022-23
2023-24
Note: This is only a standard form. Details are to be furnished in this format. In form of typewritten
statements which shall be uploaded online in envelope No. 1
-
Turnover Details as per Chartered Accountant Certificate (Last 5 years)
2 2020-21
3 2021-22
4 2022-23
5 2023-24
-
(List of Key personnel to be deployed on contract work)
Note :-Bidder shall submit the name and C.V. s of above personnel with all details in field
given in software.
FORM B-1
PERCENTAGE RATE TENDER & CONTRACT FOR WORKS
DEPARTMENT : PUBLIC WORKS DEPARTMENT, MAHARASHTRA
REGION : PUBLIC WORKS REGION, MUMBAI
CIRCLE : PUBLIC WORKS CIRCLE, THANE
DIVISION : PUBLIC WORKS DIVISION NO.1, THANE
NAME OF WORK : Supplying and Installation of Furniture and Required Amenities for New
Thane court Building at Thane.
This form will state the work to be carried out as well as the date for submitting and opening
tenders, and the time allowed for carrying out the work, also the amount of earnest money to
be deposited with the tender, and the amount of the security deposit to be deposited by the
successful tenderer and the percentage, if any, to be deducted from bills. Copies of the
specifications, designs and drawings and estimated rates, schedule rates and any other
documents required in connection with the work shall be signed by the Executive Engineer for
the purpose of identification and shall also be open for inspection to contractors in the office
of Executive Engineer during office hours.
Where the works are proposed to be executed according to the specifications recommended
to a contractor and approved by a competent authority on behalf of the Governor of
Maharashtra, such specifications with designs and drawings shall form part of the accepted
tender.
2. In the event of the tender being submitted by a firm, it must be signed separately by each
partner thereof, and in the event of the absence of any partner, it shall be signed on his behalf
by a person holding a power of attorney authorizing him to do so.
2.(A) I) The contractor shall pay alongwith the tender the sum of Rs. 7,12,000/- Earnest money
shall be paid Via SBI MOPS Online Payment Gateway Mode Only. The said amount of
earnest money shall not carry any interest whatsoever.
----------------------------------------------------------------------------------------------------------------------------
* Strike out which is not required.
II) In the event of his tender being accepted, subject to the provisions of sub-clause(iii) below,
the said amount of earnest money shall be appropriated towards the amount of security
deposit payable by him under the General Conditions of contract.
III) If, after submitting the tender, the contractor withdraws his offer or modifies the same, or if,
after the acceptance of his tender the contractor fails or neglects to furnish the balance of
security deposit, within 10 days from receipt of acceptance letter without prejudice to any
other rights and powers of the Government, hereunder, or in law, Government shall be
entitled to forfeit the full amount of the earnest money deposited by him.
IV) In the event of the tender not being accepted, the amount of earnest money deposited by
the contractor shall, unless it is prior thereto forfeited under the provisions of sub-clause (iii)
above, be refunded to him on passing receipt therefor.
(B. & C. Deptt. Resolution No. CAT - 1272 / 44277 -Q Dt. 3-3-73.)
3. Receipts for payments made on account of any work, when executed by a firm, should also
be signed by all the partners except where the contractors are described in their tender as a
firm, in which case the receipt shall be signed in the name of the firm by one of the partners,
or by some other person having authority to give effectual receipts for the firm.
16. Successful tenderer shall have to produce to the satisfaction of the accepting authority a valid
and current license issued in his favour under the provisions of Contract Labour (Regulation
and Abolition) Act, 1973 before starting the work. Failing which, acceptance of the tender
shall be liable for withdrawal and earnest money shall be forfeited to the Government (refer
Government of Maharashtra, Irrigation and Power Department’s letter No. Lab
1076h181/(666E-17), dated 8/9/1976.)
18. The contractor shall comply with the provisions of Apprentices Act,1961 and the rules and
orders issued thereunder from time to time. If he fails to do so, his failure shall be breach of
the contract and the Chief Engineer Superintending Engineer, may in his discretion cancel the
contract. The contractor shall also be liable for any pecuniary liability arising on account of
any violation by him of the provisions of the said Act.
MEMORANDUM
E) Percentage, if any to be deducted from bills so as to make up the total E) This percentage where
amount required as security deposit by the time, half the work as necessary deposit is taken
measured by the costs is done - 1% (One Percent) will vary from 5 percent to
10 percent according to the
requirements of the case.
F) Time allowed for the work from the date of written order to commence. Where security deposit is
06 (Six) Calendar months (including monsoon) taken see note 1 to clause 1
of conditions of contract.
2. I/We agree that the offer shall remain open for acceptance for a
minimum period of 90 (Ninety) days from the date fixed for opening of F) Give schedule where
envelope No.2 (Financial Bid) and thereafter until it is withdrawn by me/ necessary, showing dates
us by notice in writing duly addressed to the authority opening the tenders by which the various items
are to be completed.
and sent by registered post A.D. or otherwise delivered at the office of
such authority Treasury Bank Challan No. and date or Deposit at Call
Receipt No.___ and date ________ in respect of the sum of
Rs.______________ (in words Rs.
___________________________________________ only) representing
the earnest money is herewith forwarded. The amount of earnest money
shall not bear interest and shall be liable to be forfeited to the
Government, should I/We fail to (I) abide by the stipulation to keep the
offer open for the period mentioned above or (II) Sign and complete the
contract documents as required by the Engineer and furnish the security
deposit as specified in item (d) of the memorandum contained in
paragraph (1) above within the time limit laid down in clause (1) of the
annexed General Conditions of contract. The amount of earnest money
may be adjusted towards the security deposit or refunded to me/us if so,
desired by me/ us in writing, unless the same or any part thereof has
been forfeited as aforesaid.
Address : ____________________________________________
(Witness) $ : ____________________________________________
Address : ____________________________________________
____________________________________________
(Occupation) : ____________________________________________
the unexecuted work done by the new contractor and as to the value of
the work so done shall be final and conclusive against the contractor.
In case the contract shall be rescinded under clause (a) above the Action when the
Contractor shall not be entitled to recover or be paid, any sum for any progress
work therefor actually performed by him under this contract unless and of any particular
until the Executive Engineer shall have certified in writing the performance portion
of such work and the amount payable to him in respect thereof and he of the work is
shall only be entitled to be paid the amount so certified. In the event of unsatisfactory.
either of the courses referred to in clause (b) or (c) being adopted and the
cost of work executed departmentally or through a new contractor and
other allied expenses exceeding the value of such work credited to the
Contractors, the amount of excess shall be deducted from any money due
to the Contractor, by Government under the contract or otherwise
howsoever or from his security deposit or the sale proceeds thereof
provided, however that the Contractor shall have no claim against
Government even if the certified value of the work done departmentally or
through a new contractor exceeds the certified cost of such work and
allied expenses, provided always that whichever of the three courses
mentioned in clauses (a) , (b) or (c) is adopted by the Executive Engineer,
the Contractor shall have no claim to compensation for any loss sustained
by him by reason of his having purchased, or procured any materials, or
entered into any engagements or made any advances on account of, or
with a view to the execution of the work or the performance of the
contract.
Clause 4:- If the progress of any particular portion of the work is Contractor remains
unsatisfactory, the Executive Engineer shall notwithstanding that the liable
general progress of the work is in accordance with the conditions to pay compensation if
mentioned in clause 2, be entitled to take action under clause 3(b) after action not taken under
giving the Contractor 10 days notice in writing. The Contractor will have Clause 3 & 4.
no claim for compensation, for any loss sustained by him owing to such
action.
Clause 5:- In any case in which any of the powers conferred upon the Power to take
Executive Engineer by clause 3 and 4 hereof shall have become possession
exercisable and the same shall not have been exercised, the non of or require removal of
exercise thereof shall not constitute a waiving of any of the conditions or sell contractor’s
hereof and such powers shall notwithstanding be exercisable in the event plant.
of any future case of default by the contractor for which under any
clause hereof he is declared liable to pay compensation amounting to the
whole of his security deposit and the liability of the contractor for past and
future compensation shall remain unaffected. In the event of the
Executive Engineer taking action under sub - clause (a) or (c) of clause
3, he may, if he so desires, take possession of all or any tools, plant,
materials and stores, in or upon the works or the site thereof or belonging
to the contractor, or procured by him and intended to be used for the
execution of the work or any part thereof, paying or allowing for the same
in account at the contract rates, or in the case of contract rates not being
applicable at current market rates, to be certified by the Executive
Engineer whose certificate thereof shall be final. In the alternative, the
Executive Engineer may, after giving notice in writing to the contractor or
his clerk of the work, foreman or other authorized agent require him to
remove such tools and plants, materials, or stores from the premises
within a time to be specified in such notice, and in the event of the
contractor failing to comply with any such requisition, the Executive
Engineer may remove them at the contractor’s expenses or sell them by
auction or private sale on account of the contractor and at his risk in all
respects, and the certificate of the Executive Engineer as to the
expenses of any such removal and the amount of the proceeds and
expense of such sale shall be final and conclusive against the Contractor.
Clause 8 :- No payment shall be made for any work, estimated to cost Payment on
less than Rupees One Thousand till after the whole of work shall have intermediate certificate
been completed and a certificate of completion given. But in the case of to be regarded as
advances.
works estimated to cost more than Rupees One Thousand, the Contractor
shall on submitting a monthly bill therefore, be entitled to receive payment
proportionate to the part of the work then approved and passed by the
Engineer - in- charge, whose certificate if such approval and passing of
the sum so payable shall be final and conclusive against the Contractor.
All such intermediate payments shall be regarded as payments by way of
advance against the final payments only and not as payments for work
actually done and completed, and shall not preclude the Engineer-in-
charge from requiring any bad, unsound, imperfect or unskillful work to be
removed or taken away and reconstructed or re-erected nor shall any
such payment be considered as an admission of the due performance of
the Contract or any part thereof in any respect or the occurring of any
claim, nor shall it conclude, determine or affect in any other way
the powers of the Engineer- in-charge as to the final settlement and
adjustment of the accounts or otherwise, or in any other way vary or affect
the Contract. The final bill shall be submitted by the Contractor within one
month of the date fixed for the completion of the work. otherwise the
Engineer-in-charge's certificate of the measurements and of the total
amount payable for the work shall be final and binding on all parties.
Clause 9:-The rates for several items of works estimated to cost more Payment at reduced
than Rs.1000/- agreed to within shall be valid only when the item rates on account of
concerned is accepted as having been completed fully in accordance with items of work not
accepted as completed
the sanctioned specifications. In cases where the items of work are not to be at the desecration
accepted as so completed, the Engineer-in-charge may make payment on of the Engineer in
account of such items at such reduced rates as he may consider charge.
reasonable in the preparation of final or on-account bills.
Clause 10:- A bill shall be submitted by the Contractor in each month on Bill to be submitted
or before date fixed by the Engineer-in-charge for all works executed in monthly.
the previous month, and the Engineer-in-charge shall take or cause to be
taken the requisites measurement for the purpose of having the same
verified and the claim, so far as it is admissible, shall be adjusted , if
possible, within ten days from the presentation of the bill. If the Contractor
does not submit the bill within the time fixed as aforesaid, the Engineer-in-
charge may depute a subordinate to measure up the said work in the
presence of the Contractor or his duly authorized agent whose
countersignature to the measurement list shall be sufficient warrant, and
the Engineer-in-charge may prepare a bill from such list which shall be
binding on the Contractor in all respect.
Clause 11:- The Contractor shall submit all bills in electronic form to be Bills to be in electronic
had on application at the office of the Engineer-in-charge. The charges to form.
be made in the bills shall always be entered at the rates specified in the
tender or in the case of any extra work ordered in pursuance of these
conditions and not mentioned or provided for in the tender, at the rates
hereinafter provided for such work.
Clause 12:- If the specification or estimate of the work provides for the Stores supplied by
use of any special description of material to be supplied from the stores of Government.
the Public Works Department store or if it is required that the contractor
shall use certain stores to be provided by the Engineer-in-charge (such
material and stores and the prices to be charged therefore as hereinafter
mentioned being so far as practicable for the convenience of the
contractor but not so as in any way to control the meaning or effect of this
contract specified in the schedule or memorandum hereto annexed) the
contractor shall be supplied with such materials and stores as may be
required from time to time to be used by him for the purpose of the
contract only, and the value of the full quantity of the materials and stores
so supplied shall be set off or deducted from any sums then due or
thereafter to become due to the contractor under the contract, or
otherwise, or from the security deposit, or the proceeds of the sale thereof,
if the security deposit is held in Government securities, the same or a
sufficient portion thereof shall in that case be sold for the purpose. All
materials supplied to the contractor shall remain the absolute property of
Government and shall on no account be removed from the site of the
work, and shall at all times be open to inspection by the Engineer-in-
charge. Any such materials unused and in perfectly good condition at the
time of completion or determination of the contract shall be returned to the
Public Works Departmental store, if the Engineer-in-charge so requires by
a notice in writing given under his hand, but the contractor shall not be
entitled to return any such materials except with consent of the Engineer-
in-charge and he shall have no claim for compensation on account of any
such material supplied to him as aforesaid but remaining unused by him or
for any wastage or damage to any such materials.
Clause 13:- The contractor, shall execute the whole and every part of the Works to be executed
work in the most substantial and workman like manner, and both as in accordance with
regards materials and every other respect in strict accordance with specifications
drawings,
specifications. The contractors shall also conform exactly, fully and orders, etc.
faithfully to the designs, drawings and instructions in writing relating to the
work signed by the Engineer-in-charge and lodged in his office and to
which the contractor shall be entitled to have access for the purpose of
inspection at such office, or on the site of the work during office hours. The
contractor will be entitled to receive three sets of contract drawings and
working drawings as well as one certified copy of the accepted tender
along with the work order free of cost. Further copies of the contract
drawings and working drawings if required by him, shall be supplied at the
rate of Rs.300/- per set of contract drawings and Rs.150/- per working
drawing except where otherwise specified.
Clause 14:- The Engineer-in-charge shall have power to make any Alterations in
alterations in or additions to the original specifications, drawings, designs, specifications in
and instructions that may appear to him to be necessary or advisable designs not to
during the progress of the work, and the Contractor shall be bound to invalidate contracts.
carry out the work in accordance with any instructions in this connection
which may be given to him in writing signed by the Engineer-in-charge and
such alteration shall not invalidate the contract, and any additional work
which the Contractor may be directed to do in the manner above specified
as part of the work shall be carried out by the Contractor on the same
conditions in all respects on which he agreed to do the main work, and at
the same rates as are specified in the tender for the main work. And if the
additional and altered work includes any class of work for which no rates Rates for works not
is specified in this contract, then such class of work shall be carried out at entered in estimate, or
the rates entered in the Schedule of Rates of the Division prevailing at the schedule of rates
of the contract.
time when the extra items crop up or at the rates mutually agreed upon
between the Engineer-in-charge and the contractor whichever are lower.
If the additional or altered work for which no rate is entered in the
Schedule of Rates of the Division, is ordered to be carried out before the
rates are agreed upon then the Contractor shall within seven days of the
date of receipt by him of the order to carry out the work inform the
Engineer-in-charge of the rate which it is his intention to charge for such
class of work, and if the Engineer-in-charge does not agree to this rate, he
shall by notice in writing be at liberty to cancel his order to carry out such
class of work, and arrange to carry it out in such manner as he may
consider advisable provided always that the Contractor shall commence
work or incur any expenditure in regard thereto before the rates shall have
been determined as lastly here in before mentioned, then in such case he
shall only be entitled to be paid in respect of the work carried out or
expenditure incurred by him prior to the date of the determination of the
rates as aforesaid according to such rate or rates as shall be fixed by the
Engineer-in-charge. In the event of a dispute, the decision of the
Superintending Engineer of the Circle will be final.
Where, however, the work is to be executed according to the designs, Extensions of time in
drawings and specifications recommended by the contractor and consequence of
accepted by the competent authority the alterations above referred to additions or alterations.
shall be within the scope of such designs, drawings and specifications
appended to the tender.
The time limit for the completion of the work shall be extended in the
proportion that the increase in its cost occasioned by alterations or
additions bears to the cost of the original contract work, and the certificate
of the Engineer-in-charge as to such proportion shall be conclusive.
Clause 15:- (1) If at any time after the execution of the contract No claim to any
documents, the Engineer shall for any reason what-so-ever (other than payment or
default on the part of the Contractor for which the Government is entitled compensation for
to rescind the contract) desires that the whole or any part of the work alteration in or
specified in the tender should be suspended for any period or that the restriction of work.
whole or part of the work should not be carried out at all, he shall give to
the Contractor a notice in writing of such desire and upon the receipt of
such notice the Contractor shall forthwith suspend or stop the work wholly
or in part as required, after having due regard to the appropriate stage at CAT-1268/59382-Q
which the work should be stopped or suspended so as not to cause any DT.14-3-74.
damage or injury to the work already done or endanger the safety thereof
provided that the decision of the Engineer as to the stage at which the
work or any part of it could be or could have been safely stopped or
suspended shall be final and conclusive against the Contractor. The
Contractor shall have no claim to any payment or compensation
whatsoever by reason of or in pursuance of any notice as aforesaid, on
account of any suspension, stoppage or curtailment except to the extent
specified hereinafter.
(2) Where the total suspension of work ordered as aforesaid continued for
a continuous period exceeding 90 days the Contractor shall be at liberty to
withdraw from the contractual obligations under the contract so far as it
pertains to the unexecuted part of the work by giving a 10 days prior
notice in writing to the Engineer, within 30 days of the expiry of the said
period of 90 days, of such intention and requiring the Engineer to record
the final measurements of the work already done and to pay final bill.
Upon giving such notice the Contractor shall be deemed to have been
discharged from his obligation to complete the remaining unexecuted work
under his contract. On receipt of such notice the Engineer shall proceed
to complete the measurement and make such payment as may be finally
due to the Contractor within a period of 90 days from the receipt of such
notice in respect of the work already done by the Contractor. Such
payment shall not in any manner prejudice the right of the Contractor to
any further compensation under the remaining provisions of this clause.
(3) Where the Engineer requires the Contractor to suspend the work for a
period in excess of 30 days at any time or 60 days in the aggregate the
Contractor shall be entitled to apply to the Engineer within 30 days of the
resumption of work after such suspension for payment of compensation to
the extent of pecuniary loss suffered by him in respect of working
machinery rendered idle on the site or on account of his having had to
pay the salary or wages of labour engaged by him during the said period
of suspension, provided always that the contractor shall not be entitled to
any claim in respect of any such working machinery, salary or wages for
the first 30 days whether consecutive or in the aggregate of such
suspension or in respect of any suspension whatsoever occasioned by
unsatisfactory work or any other default on his part. The decision of the
Engineer in this regard shall be final and conclusive against the
Contractor.
It shall be open to the Contractor, within 90 days from the service of (i)
the notice of stoppage of work or (ii) the notice of withdrawal from the
contractual obligations under the contract on account of the continued
suspension of work or (iii) notice under clause 15(1) resulting in such
curtailment, to produce to the Engineer satisfactory documentary evidence
that he had purchased for agreed to purchase material for use in the
contract work, before receipt by him of the notice of stoppage, suspension
or curtailment and require the Government to take over on payment such
material at the rates determined by the Engineer, provided, however such
rates shall in no case exceeds the rates at which the same were acquired
by the Contractor. The Government shall thereafter take over the material
so offered, provided the quantities offered, are not in excess of the
requirements of the unexecuted work as specified in the accepted tender
and are of quality and specifications approved by the Engineer.
Clause 17:- If at any time before the security deposit or any part thereof is Action and
refunded to the Contractor it shall appear to the Engineer-in-charge or his compensation
subordinate in charge of the work, that any work has been executed with payable in case of bad
work.
unsound, imperfect or unskillful workmanship or with materials of inferior
quality or that any materials or articles provided by him for the execution of
the work are unsound or of a quality inferior to the that Contracted for, or
are otherwise not in accordance with the Contract, it shall be lawful for the
Engineer-in-charge to intimate this fact in writing to the Contractor and
then not with standing the fact that the work, materials or articles
complained of may have been inadvertently passed, certified and paid for, P.W.D. Resolution
the Contractor shall be bound forthwith to rectify, or remove and No. CAT-1087/
reconstruct the work so specified in whole or in part, as the case may be CR-94/
require or if so required shall remove the materials or articles so specified Bldg.2 dt.14-6-89.
and provide other proper and suitable materials or articles at his own
charge and cost and in the event of his failing to do so within a period to
be specified by the Engineer-in-charge in the written intimation aforesaid,
the contractor shall be liable to pay compensation at the rate of one
percent on the amount of the estimate for every day not exceeding 10
days during which the failure so continuous and in the case of any such
failure the Engineer-in-charge may rectify or remove and re-execute the
work or remove and replace the materials or articles complained of, as the
case may be at the risk and expense in all respects of the Contractor.
Should the Engineer-in-charge consider that any such inferior work or
materials as described above may be accepted or made use of it shall be
within his discretion to accept the same at such reduce rates as he may fix
therefor.
Clause 18 :- All works under or in course of execution or executed in Work’s to be opened to
pursuance of the contract shall at all times be open to the inspection and inspection.
supervision of the Engineer-in-charge and his subordinates, and the
Contractor shall at all times during the usual working hours, and at all Contractor or
responsible
other times at which reasonable notice of the intention of the Engineer-in-
agent to be present.
charge and his subordinates to visit the work shall have been given to the
contractor, either himself be present to receive orders and instructions , or
have a responsible agent duly accredited in writing present for that
purpose. Orders given to the Contractors duly authorized agent shall be
considered to have the same force and effect as if they had been given to
the Contractor himself.
Clause 19 :- The Contractor shall give not less than five days notice in Notice to be given
writing to the Engineer-in-charge or his subordinate in charge of the work before work is covered
before covering up or otherwise placing beyond the reach of measurement up.
any work in order that the same may be measured and correct dimension
thereof taken before the same is so covered up or placed beyond the
reach of measurement and shall not cover up or place beyond the reach
of measurement any work without the consent in writing of the Engineer-
in-charge or his subordinate in charge of the work, and if any work shall be
covered up or placed beyond the reach of measurement, without such
notice having been given or consent obtained the same shall be
uncovered at the Contractors expense, and in default thereof no payment
or allowance shall be made for such work or for the materials with which
the same was executed.
Clause 20:- If during the period of 05 (Five) Years from the date of Contractor liable for
completion as certified by the Engineer-in-charge pursuant to clause-7 of damage done, and for
the contract or in the opinion of the Executive Engineer the said work is Imperfections.
defective in any manner whatsoever, the Contractor shall forthwith on
receipt of notice in that behalf from the Executive Engineer, duly P.W.D. Resolution
commence execution and completely carry out at his cost in every respect No.CAT-1087/CR-
all the work that may be necessary for rectifying and setting right the 94/Bldg.2.dt.14-6-89.
defects specified therein including dismantling and reconstruction of
unsafe portions strictly in accordance with and in the manner prescribed
and under the supervision of the Executive Engineer. In the event of the
Contractor failing or neglecting to commence execution of the said
rectification work within the period prescribed therefor in the said notice
and /or to complete the same as aforesaid as required by the said notice,
the Executive Engineer may get the same executed and carried out
departmentally or by any other agency at the risk, on account and at the
cost of the Contractor. The Contractor shall forthwith on demand pay to
the Government the amount of such cost, charges and expenses
sustained or incurred by the Government of which the certificate of the
Executive Engineer shall be final and binding on the Contractor. Such
costs, charges and expenses shall be deemed to be arrears of land
revenue and in the event of the Contractor failing or neglecting to pay the
same on demand as aforesaid without prejudice to any other rights and
remedies of the Government, the same may be recovered from the
contractor as arrears of land revenue. The Government shall also be
entitled to deduct the same from any amount which may then be payable
or which may thereafter become payable by the Government to the
contractor either in respect of the said work or any other work whatsoever
or from the amount of security deposit retained by Government.
Clause 21:- The Contractor shall supply at his own cost all material
(except such special materials, if any as may, in accordance with the Contractor to supply
contract, be supplied from the P.W. Departmental stores), plant, tools plant, ladders
appliances, implements, ladders, cordage, tackles, scaffolding and scaffoldings,
temporary works requisite or proper for the proper execution of the work, etc.
whether in the original, altered or substituted from, and whether included
in the specification or other documents forming part of the contract or
referred to in these conditions or not and which may be necessary for the And is liable for
purpose of satisfying or complying with the requirements of the Engineer- damages arising from
in-charge as to any matter as to which under these conditions he is non provisions
entitled to be satisfied, or which he is entitled to require together with the of lights, fencing etc.
carriage therefor to and from the work. The Contractor shall also supply
without charge the requisite number of persons with the means and
materials necessary for the purpose of setting out works and counting,
weighing and assisting in the measurement or examination at any time
and from time to time of the work or the materials, failing which the same
may be provided by the Engineer-in-charge at the expense of the
contractor and the expenses may be deducted from any money due to the
Contractor under the contract or from his security deposit or the proceeds
of sale thereof, or of sufficient portion thereof. The Contractor shall provide
all necessary fencing and lights required to protect the public from
accident, and shall also be bound to bear the expenses of defence of
every suit, action or other legal proceeding, that may be brought by any
person for injury sustained owing to neglect of the above precautions, and
to pay any damages and cost which may be awarded in any such suit,
action or proceedings to any such person, or which may with the consent
of the Contractor be paid for compromising any claim by any such person.
a) Suitable scaffolds shall be provided for workmen for all works that
cannot be safely done from a ladder or by other means.
Clause 21(B):- The Contractor shall comply with the following regulations
as regards the Hoisting Appliances to be used by him :-
a) Hoisting machines and tackles, including their attachments,
anchorages and supports shall.
i) be of good mechanical construction, sound material and
adequate strength and free from patent defect;
and
ii) be kept in good repair and in good working order.
d) Every chain, ring, hook, shackle, swivel and pulley block used in
hoisting or lowering materials or as a means of suspension shall be
periodically examined.
Clause 22:- The Contractor shall not set fire to any standing jungle, trees,
brushwood or grass without a written permit from the Executive Engineer. Measure for prevention
When such permit is given, and also in all cases when destroying, cut or of fire.
dug up trees, brushwood, grass etc. by fire, the Contractor shall take
necessary measures to prevent such fire spreading to or otherwise
damaging surrounding property.
The Contractor shall make his own arrangements for drinking water for the
labour employed by him and provide sanitary and other arrangements.
Clause 26:- The contract shall not be assigned or sublet without the
written approval of the Engineer-in-charge. And if the Contractor shall Work not to be sublet
assign or sublet his contract, or attempt to do so, or become insolvent or
commence any proceedings to get himself adjudicated and insolvent or
make any composition with his creditors, or attempt so to do or if bribe, Contract may be
gratuity, gift loan, perquisite, reward or advantage, pecuniary or otherwise rescinded and security
shall either directly or indirectly be given, promised or offered by the deposit forfeited for
subletting it without
Contractor or any of his servants or agents to any public officer or person
approval or for bribing
in the employ of Government in any way relating to his office or a public officer or if
employment, or if any such officer or person shall become in any way contractor becomes
directly or indirectly interested in the contract, the Engineer-in-charge may insolvent.
thereupon by notice in writing rescind the contract, and the security
deposit of the Contractor shall thereupon stand forfeited and be absolutely
at the disposal of Government, and the same consequences shall ensure
as if the contract had been rescinded under Clause 3 thereof and in
addition the Contractor shall not be entitled to recover or be paid for any
work therefor actually performed under the contract.
Clause 27:- All sums payable by a Contractor by way of compensation Sum payable by way of
under any of these conditions shall be considered as a reasonable compensation to be
compensation to be applied to the use of Government without reference to considered as
reasonable
the actual loss or damages sustained, and whether any damage has or compensation without
has not been sustained. reference to actual loss.
Clause 28:- In the case of tender by partners, any change in the Change in the
constitution of a firm shall be forthwith notified by the Contractor to the constitution of firm to
be notified.
Engineer-in-charge for his information.
Clause 29:- All works to be executed under the contract shall be Direction and control of
executed under the direction and subject to the approval in all respects of the Superintending
the Superintending Engineer of the Circle, for the time being, who shall be Engineer.
entitled to direct at what point or points and in what manner they are to be
commenced, and from time to time carried on.
Clause 30(1):- Except where otherwise specified in the contract and Direction and control of
subject to the powers delegated to him by Government under the code, the Superintending
Engineer.
rules then in the force, the decision of the Superintending Engineer of the
Circle for the time being shall be final, conclusive and binding on all
parties of the contract upon all questions relating to the meaning of the
specifications, designs, drawings and instruction hereinbefore mentioned
and as to the quality of workmanship or materials used on the work, or as
to any other question, claim right, matter or things whatsoever, if any way
arising out of, or relating to the contract, designs, drawings, specifications,
estimates , instructions, orders, or other conditions, or otherwise
concerning the works, or the execution, or failure to execute the same,
whether arising during the progress of the work, or after the completion or
abandonment thereof.
Clause 30 (2):- The Contractor may within thirty days of receipt by him of
any order passed by the Superintending Engineer of the Circle as
aforesaid appeal against it to the Chief Engineer, concerned with the
contract work or project provided that -
Clause 30 (3):- If the Contractor is not satisfied with the order passed by
the Chief Engineer as aforesaid, the Contractor may, within thirty days of
receipt by him of any such order appeal against it to the concerned
Secretary, Public Works Department/Irrigation Department who, if
convinced that Prima-facie the Contractors claim rejected by
Superintending Engineer/Chief Engineer is not frivolous and that there is
some substance in the claim of the Contractor as would merit a detailed
examination and decision by the Standing Committee, shall put up to the
Standing Committee at Government level for suitable decision
(Vide PW Circular No. CAT-1086-CR-110/Bldg.2 Dated 7.5.1986)
Clause 33:- In the case of any class of work for which there is no such Action where no
specification as is mentioned in Rule 1 of Form B-1 such work shall be specifications.
carried out in accordance with the Divisional specifications, and in the
event of there being no Divisional specification, then in such case the
work shall be carried out in all respects in accordance with all instructions
and requirements of the Engineer-in-charge .
Clause 34:- The expression "Work" or "Works" where used in these Definition of work.
conditions, shall unless there be something in the subject or context
repugnant to such construction, be constructed to mean the work or works
contracted to be executed under or in virtue of the contract, whether
temporary or permanent and whether original, altered, substituted or
additional.
Clause 35:- The percentage referred to in the tender shall be deducted Contractor’s percentage
from/added to the gross amount of the bill before deducting the value of whether applied to net or
any stock issued. gross amount of bill.
Clause 36:- All quarry fees, royalties, octroi dues and ground rent for Quarry fees and
stacking materials, if any, should be paid by the contractor. royalty royalties.
charges including surcharges on all minor minerals shall be reimbursed
separately on production of proof to that effect. Compensation under
Clause 37:- The Contractor shall be responsible for and shall pay any workmen's
compensation to his workmen payable under the Workmen's Compensation Act.
Compensation Act.1923 (VIII of 1923), (hereinafter call the said Act) for
injuries caused to the workmen. If such compensation is payable/paid by
the Government as principal under sub-section (1) of Section 12 of the
said Act on behalf of the Contractor, it shall be recoverable by the
Government from the Contractor under sub-section (2) of the said section.
Such Compensation shall be recovered in the manner laid down in Clause
1 above.
Clause 37 (A):- The Contractor shall be responsible for and shall pay the
expenses of providing medical aid to any workmen who may suffer a
bodily injury as a result of an accident. If such expenses are incurred by
Government the same shall be recoverable from the Contractor forthwith
and be deducted without prejudice to any other remedy of the Government
from any amount due or that may become due to the Contractor .
Clause 37(B):- The Contractor shall provide all necessary personal safety
equipment and first aid apparatus available for the use of the persons
employed on the site and shall maintain the same in condition suitable for
immediate use at any time and shall comply with the following regulations
in connection therewith :-
Clause 37(C):- The Contractor shall duly comply with the provisions of
"The Apprentices Act. 1961" (III of 1961) the rules made thereunder and
the orders that may be issued from time to time under the said Act and the
said Rules and on his failure or neglect to do so he shall be subjected to
all the liabilities and penalties provided by the said Act and said Rules.
(Govt. Circular No. CAT-6076/3336/(400)/Bldg.2 dt. 16-8-1985.)
Clause 38:- (1) Quantities shown in the tender are approximate and no Claim for quantities of
claim shall be entertained for quantities of work executed being either work entered in the
more or less than those entered in the tender or estimate. tender or estimates.
(2) Quantities in respect of the several items shown in the tender are
approximate and no revision in the tendered rates shall be permitted in
respect of any of the items so long as, subject to any special provision
contained in the specifications prescribing a different percentage of
permissible variation in the quantity of the item does not exceed the
tender quantity by more than 25 percent and so long as the value of the
excess quantity beyond this limit at the rate of the items specified in the
tender, is not more than Rs.5,000/-
(3) The contractor shall if ordered in writing by the Engineer so to do,
also carry out any quantities in excess of the limit mentioned in sub-
clause (i) hereof on the same conditions as and in accordance with the
specifications in the tender and at the rates (i) derived from the rates
entered in the current schedule of rates and in the absence of such rates
(ii) at the rates prevailing in the market. The said rates increased or
decreased as the case may be, by the percentage which the total
tendered amount bears to the estimated cost of the work as put to
tender based upon the schedule of rates applicable to the year in which
the tenders were accepted (For the purpose of operation of this
clause, this cost shall be as worked out from D.S.R. prevailing at the
time of acceptance of tender.)
(4) Claims arising out of reduction in the tendered quantity of any item
beyond 25 percent will be governed by the provision of clause 15 only
when the amount of such reduction beyond 25 percent at the rate of the
item specified in the tender is more than Rs.5,000/- (This clause is not
applicable to extra items)
Clause 40:- No compensation shall be allowed for any delay caused in Claim for compensation
the starting of the work on account of acquisition of land or, in the case of for delay in starting of
clearance works, on account of any delay in according sanction to work.
estimates.
Clause 41:- No compensation shall be allowed for any delay in the Claim for compensation
execution of the work on account of water, standing in borrow pits or for delay in execution
compartments. The rates are inclusive for hard or cracked soil, excavation of work.
in mud, sub-soil water or water standing in borrow pits and no claim for an
extra rate shall be entertained unless otherwise expressly specified.
Clause 42:- The Contractor shall not enter upon or commence any portion Entering upon or
of work except with written authority and instructions of the Engineer-in- commencing any
charge or his subordinate in charge of the work. Failing such authority the portion of work.
Contractor shall have no claim to ask for measurements of the payment
for work.
Clause 43(i):- No contractor shall employ any person who is under the Minimum age of
age of 18 years. persons employed, the
(ii) No contractor shall employ donkeys or other animals with breaching of employment of donkeys
and / or other animals
string or thin ropes. The breaching must be at least three inches wide and
and the payment of fair
should be of tape (Nawar). wages.
(iii) No animal suffering from sores, lameness or emaciation or which is
immature shall be employed on the work.
(iv) The Engineer-in-charge or his Agent is authorized to remove from the
work, any person or animal found working which does not satisfy these
conditions and no responsibility shall be accepted by Government for any
delay caused in the completion of the work by such removal.
(v) The contractor shall pay fair and reasonable wages to the workmen
employed by him, in the contract undertaken by him. In the event of any
dispute arising between the contractor and his workmen on the grounds
that the wages paid are not fair and reasonable, the dispute shall be
referred without delay to the Executive Engineer shall be conclusive and
binding on the contractor but such decision shall not in any way affect the
conditions in the contract regarding the payment to be made by
Government at the sanctioned tender rates.
(vi) Contractor shall provide drinking water facilities to the workers.
Similar amenities shall be provided to the workers engaged on large work
in urban areas.
(vii) All facilities provided in the contract labour (Regulation and Abolition
Act 1971), The Maharashtra Contract Labour Regulation and Abolition
Rule 1971 should be provided.
Clause 44:- Payment to contractors shall be made by cheque drawn on Method of payment.
any treasury within the division convenient to them, provided the amount
exceeds Rs.10. Amounts not exceeding Rs.10 will be paid in cash.
Clause 45:- Any contractor who does not accept these conditions shall Acceptance of conditions
not be allowed to tender for works. compulsory before
tendering for work
Clause 48:- The rates to be quoted by the contractor must be inclusive of all
other relevant taxes except GST. No extra payment of this account will be
made to the contractor.
Clause 49:- In case of materials that may remain surplus with the Contractor
from those issued for the work contracted for, the date of ascertainment of the
materials being surplus will be taken as the date of sale for the purpose of
sales tax and the sales tax will be recovered on such sale.
Clause 50:- The Contractor shall employ the unskilled labour to be employed
by him on the said work only from locally available labour and shall give
preference to those persons enrolled under Maharashtra Government
Employment and Self Employment Department's Scheme.
Provided, however, that if the required unskilled labours from that district is
are not available locally, the Contractor shall in the first instance employ such
number of persons as is available and thereafter may with previous
permission, in writing of the Executive Engineer-in-charge of the said work,
obtain the rest of requirement of unskilled the labour from outside the above
scheme.
Clause 51:- The contractor shall pay the labourers (skilled and unskilled)
according to the wages prescribed by the Minimum Wages Act of 1948
applicable to the area in which the work of the contract is located. The
contractor shall comply with the provision of the Apprentices Act, 1961,
and the rules and orders issued thereunder from time to time, if he fails to
do so his failure will be a breach of the contract and the Superintending
Engineer, may in his discretion may cancel the contract. The Contractor
shall also be liable, for any precautionary liability, arising on account of
any violation by him of the provision of Act.
The contractor shall pay labourers skilled and unskilled according to the
wages prescribed by the Minimum Wages Act, of 1948 applicable to the
area in which work lies.
The contractor to take precautions against accidents which take place on
account of labour using loose garments while working machinery.
Clause 52:- All amounts whatsoever which the contractor is liable to pay
to the Government in connection with the execution of the work including
the amount payable in respect of (i) materials and / or stores supplied/
issued hereunder by the Government to the contractor. (ii) hire charges in
respect of heavy plant, machinery and equipment given on hire, by the
Government to the contractor for execution by him of the work and/or on
which advances have been given by the Government to the contractor
shall be deemed to be arrears of Land Revenue and the Government may
without prejudice to any other rights and remedies of the Government
recover the same from the contractor as arrears of land revenue.
(CAT-1274/40364/Desk-2 dt. 7-12-76)
Clause 53:- The Contractor shall duly comply with all the provisions of the Government Circular
Contract Labour (Regulation and Abolition ) Act, 1970 (37 of 1970) and No. CAT-1284/(120)
the Maharashtra Contract Labour (Regulation and Abolition) Rules, 1971 /Bldg.2 dt. 14.8.85.
as amended from time to time and all other relevant statutes and statutory
provisions concerning payment of wages particularly to workmen
employed by the Contractor and working on the site of the work. In
particular the Contractor shall pay wages to each worker employed by him
on the site of the work at the rates prescribed under the Maharashtra
Contract Labour (Regulation and Abolition) Rules, 1971. If the Contractor
fails or neglects to pay wages at the said rates or makes short payment
and the Government makes such payment of wages in full or part thereof
less paid by the Contractor as the case may be the amount so paid by the
Government to such workers shall be deemed to be an arrears of land
revenue and the Government shall be entitled to recover the same as
such from the contractor or deduct the same from the amount payable by
the Government to the Contractor hereunder or from any other amount/s
payable to him by the Government.
Clause 54:- The contractor shall engage apprentice such as brick layer,
carpenter, wiremen, plumber, as well as blacksmith by recommended by
the State Apprenticeship Advisor Director of Technical Education, Dhobi
Talaw, Mumbai :400 001. In the construction work (as per Government of
Maharashtra, Education Government No.TSA/5170/T5689, dated
7.7.1972).
3. The “Crushed Sand” shall be free of dust and other deleterious material.
4. The “Crushed Sand” shall be manufactured using “Automatic Vertical Shaft Impactor” type crusher
only.
5. The quantity of micro fines (Partices below 75 microns) in “Crushed Sand” shall not be more than 7%
6. The Contractor shall intimate the Engineer in charge regarding the source of supply of Crushed Sand.
The source of supply of “Crushed Sand” shall be got approved by the Executive Engineer (Engineer
in charge) prior to the start of work.
7. Each load of crushed sand whenever brought on site shall be tested for “Fineness Modulus”. Finess
modulus shall be within permissible limits. If it doesn’s fall within acceptable limit, it shall be rejected.
8. The test of compressive strength of concrete / mortar using “Crushed Sand” shall be carried out in
presence of Department’s Engineer as given below.
(a) 100% cube testing in presence of Junior / Asstt. / Sectional Engineer.
(b) 25% cube testing in the presence of Sub-Divisional Engineer.
(c) 5% cube testing in the presence of Executive Engineer (Engineer in charge).
9. The flakiness Index and Elongation Index tests shall be within permissible limits.
10. The Concrete Mix Design for each grade of concrete using “Concrete Sand” shall not be used.
11. As far as possible freshly produed “Crushed Sand” shall be used stored “Crushed Sand” shall not be used.
12. For plastering purpose, if the use of crushed sand is proposed it shall be used with addition of super
plasticisors at the rateof 100 ml. / Bag of cement without extra cost to Government. Separate permission
shall be taken for use in plastering from concerned Executive Engineer.
13. The following tets shall be carried out for the use of “Crushed Sand”.
(a) Sieve Analysis
(b) Specific Gravity
(c) Water Absorption
(d) Bulk Density
(e) Alkali Aggregate Reaction
(f) Sundness
(g) Deleterious Material
(h) Organic Impurities
(i) Micro Fines Content
(j) Test for Silt and Clay
(k) Fineness Modulus Test
14. Necessary Bon regarding the use of “Crushed Sand” shall be submitted by the contractor clearly stating
that, if any defects are observed during exeution and defect liability period, the samd shall be rectified as
his own risk and cost.
15. Grading Zone-II mentioned under Clause 6.3 table 9 of fine aggregates of IS 383:2016 shall only be used
for concreting.
16. Reversible Drum Type / Batch Mix Palnt (Pan type) concrete mixer shall be used for concrete.
17. Crushed Sand shall not be used for prestressed concrete works.
Clause 57:- Building and Other Construction Workers Welfare Cess Government in P.W.Deptt.
As per Government of Maharashtra, Industry, Energy & Labour Deptt. G.R. letter (in Marathi)No. Misc /
No. BLA 2009/ Pra.Kra.108 / Kamgar-7A, dt 17/6/2010 & Public Works 10 1091 Pra.Kra.2771
Department Circular No. BDG-2010/ Pra.kra. 277 / Building-2, dated BWg.-2, Mantralaya,
28/09/2010, Building and Other Construction Workers Welfare Cess at one Mumbai - 32 dated
percent or at the rates amended from time to time as intimated by the 17/08/2010.
competent authority under Building and Other Constructions Worker Welfare
Act 1996 will be deducted from the Bill amount, whether measured Bill,
advance payment or Secured Advance.
SCHEDULE A
NAME OF WORK:- Supplying and Installation of Furniture and Required Amenities for New
Thane court Building at Thane.
Schedule showing (approximately) the materials to be supplied from the P.W. Department
Stores for Work contracted to be executed and preliminary and ancillary works and the rates at which
they are to be charged for.
Note –
1) The person on firm submitting the tender should see that the rates in the above schedule are
filled up by the Executive Engineer In charge on the issue of the form prior to the submission
of the tender.
2) The rates mentioned in Schedule “A” are inclusive of all taxes and storage charges.
1. All material such as cement, steel etc. required for execution of work shall be brought by
Contractor at his own cost.
2. The contractor shall maintain the record of these materials in the prescribed proforma and
registers as directed by Engineer in charge. The sample of prescribed proforma is attached at
the end. These registers shall be signed by both contractors and representative of Engineer in
charge. These registers shall be made available for inspection, verification for the department
as and when required. These registers shall be in the custody of department and shall be
maintained by the department.
The Contractor shall submit periodically as well as on completion of work, an account of all
materials used by him on the work. In addition, a separate register shall be maintained on
site for recording daily item wise asphalt, cement consumption and also item wise
consumption of other materials. This shall be signed daily by Contractor or his representative
and representative of Engineer-In-Charge.
3. The material required only for this work shall be kept in the godown at site. No materials shall
be shifted outside of the godown except for the work for which this agreement is entered
without prior approval of the Engineer-In-Charge.
4. The material i.e. cement, steel etc. brought on the work site shall be accompanied with the
necessary Company / Manufacturing firm’s test certificates. In addition these material shall be
tested as per frequency prescribed by the department and the cost of such testing shall be
borned by the Contractor. If the test results are satisfactory, then and then only the material
shall be allowed to be used on the work. If the test results are not as per standards, these
materials shall be immediately removed from the work site at contractor’s cost. In case of
cement, if so requested by the contractor in writing, material will be allowed to be used before
receipt of test results but this will be entirely at the risk and cost of the contractor.
5. The contractor shall produce sufficient documentary evidence i.e. bill for the purchase octroi
receipts etc. for the purchase of material brought on the work site at once if so requested by
the department.
6. All these material i.e. cement, steel etc. shall be protected from any damages, rains etc. by
the contractor at his own cost.
7. The contractor will have to erect temporary shed of approved specifications for storing of
above materials at work site at contractors cost having double lock arrangements (By Double
lock it is meant that godown shall always be locked by two locks, one lock being owned &
operated by contractor & other by Engineer in charge or his authorised representative & the
door shall be openable only after both locks are opened.)
8. If required, the weighment of bulk asphalt bouzers etc. brought by the contractor shall be
carried out by the contractor at his own cost.
9. The contractor shall not use cement and other material for the item to be executed outside
the scope of this contract except for such ancillary small item as are connected and
absolutely necessary for execution of this work as may be decided by the Engineer in charge.
10. The Government shall not be responsible for the loss in cement, steel etc. during transit to
work site. The cement brought by the contractor at the work site store shall mean 50kg.
equivalent to 0.0347 cubic metre per bag by weight. The rate quoted should correspond to
this method of reckoning, in case of ordinary / controlled concrete if cement is found short, the
storage / shortage will be made good by contractor at his own cost.
11. INDEMNITY
The condition regarding indemnity as defined on Page No.67 at Sr. No.8.6 will apply mutatis
mutandis in case of material brought by contractor at the site for the execution of the work
being executed under this contract.
12. In case the materials brought by the contractor become surplus owing to the change in the
design of the work, the materials should be taken back by the contractor at his own cost after
prior permission of Engineer in charge.
13. All empty bags or empty asphalt drums shall be the property of contractor and the same shall
be removed immediately after completion of work.
14. The 30/40 grade and 60/70 grade bitumen use for bituminous work must be refinery
produced.
15. In order to ensure proper grade of bitumen use for bitumen that is to be used for bituminous
work, following procedure shall be adopted.
a) The schedule of arrival of bouzers and the procurement of bitumen obtained from the
Government refinery shall be submitted by the contractor before preparation of the
bitumen mix.
b) The necessary instruments / machineries (with latest calibration) on plant / site for
testing of materials shall be made available by the contractor.
c) The original challan and delivery memo of the bitumen obtain the Government Refinery
shall be submitted to the Engineer in charge and the same shall recorded in the
measurement book of that work.
d) Engineer in charge shall collect the sample of the bitumen received from the
Government refinery prior to unloading the plant, and shall verify the quality from the
Government laboratory and the results obtain shall be recorded. If he is satisfied with
the results than only he shall permit in writing to the contract to unload the bitumen in
the presence of Engineer in charge or his authorized representative. The workwise
register shall be maintained on the plant containing Bouzers number, Challan Number,
Delivery Memo Number, Net Weight of the bitumen, grade of the bitumen and name of
the officer who conduct the test.
xÉÉånù´É½þÒ Gò. 1
xÉÉånù´É½þÒ Gò¨ÉÉÆEò 2
1 B¨É.{ÉÒ.B¨É.
2 ¤ÉÒ.B¨É.
3 ¤ÉÒ.ºÉÒ.
xÉÉånù´É½þÒ Gò¨ÉÉÆEò 3
EòɨÉÉSÉä xÉÉÆ´É:-
+.Gò. ʨɳýɱÉ䱪ÉÉ {ÉÉäiªÉÉÆSÉÒ ºÉÆJªÉÉ ´ÉÉ{É®ú±É䱪ÉÉ {ÉÉäiªÉÉÆSÉÒ ºÉÆJªÉÉ Ênù´ÉºÉÉSªÉÉ +JÉä®úÒºÉ EòɨÉÉSªÉÉ
Ê`öEòÉhÉÒ ®úÉʽþ±Éä±ÉÒ {ÉÉäiÉÒ
BEÖòhÉ
xÉÉånù´É½þÒ Gò¨ÉÉÆEò 4
ÊxÉ®úÊxÉ®úɳý¬É ¤ÉɤÉÓ´É®ú +É`ö´Éb÷¬ÉƨÉvªÉä ={ɪÉÉäMÉÉiÉ +ÉhɱÉä +ɴɶªÉEò +ºÉ±Éä±Éä ʺɨÉå]õ {ÉÊ®ú¨ÉÉhÉ ´É |ÉiªÉIÉÉiÉ
={ɪÉÉäMÉÉiÉ +ÉhɱÉä±Éä {ÉÊ®ú¨ÉÉhÉ ªÉÉÆSÉÒ iÉÖ±ÉxÉÉ nùÉJÉÊ´ÉhÉÉ®äú EòÉä¹]õEò
+É`ö´Éb÷¬É¨ÉvªÉä Eäò±É䱪ÉÉ EòɨÉÉSÉä BEÚòhÉ +ÆnùÉVÉ {ÉÊ®ú¨ÉÉhÉ
1) {ÉÉ<Ç{É ´É ¨ÉÉä-ªÉÉ
2) <iÉ®ú ºÉÆEòÒhÉÇ
xÉÉånù´É½þÒ Gò. 5
xÉÉånù´É½þÒ Gò¨ÉÉÆEò 6
------ ±ÉÉ ºÉÆ{ÉhÉÉ-ªÉÉ ¨ÉʽþxªÉÉSÉÒ {ÉÉä±ÉÉnùÉSÉÒ nèùxÉÆÊnùxÉ +É´ÉEò VÉÉ´ÉEò +ÉÊhÉ Ê¶É±±ÉEò
xÉÉånù´É½þÒ Gò¨ÉÉÆEò 7
±ÉÉ ºÉÆ{ÉhÉÉ-ªÉÉ ¨ÉʽþxªÉɨÉvªÉä {ÉÉä±ÉÉnùÉSÉä ÊEòiÉÒ {ÉÊ®ú¨ÉÉhÉ ´ÉäMÉ´ÉäMɳý¬É ¤ÉɤÉÓ´É®ú ={ɪÉÉäMÉÉiÉ +ÉhÉɴɪÉÉºÉ {ÉÉʽþVÉä
½þÉiä Éä ´É |ÉiªÉIÉÉiÉ ÊEòiÉÒ {ÉÊ®ú¨ÉÉhÉ ´ÉÉ{É®ú±Éä ½þÒ iÉÖ±ÉxÉÉ Eò®úhªÉɺÉÉ`öÒ +ɴɶªÉEò +ºÉ±Éä±ÉÒ MÉhÉxÉÉ
F0 = The official retail price of High Speed Diesel (HSD) at the existing consumer
pumps of lac at nearest center on the day 28 days prior to the date of opening of
Bids.
F1 = The official retail price of High Speed Diesel (HSD) at the existing consumer
th
pumps of IOC at nearest center for the 15 day of month of the under
consideration.
Pf = Percentage of fuel and lubricant component of the work
Note: For the application of this clause, the price of High Speed Diesel oil has been
chosen to represent fuel and lubricants group.
(C) Adjustment of Other Materials Component (Excluding Bitumen, Steel and Cement)
Price adjustment for increase or decrease in the cost of local materials other than cement,
steel bitumen and POL procured by the contractor shall be paid in accordance with the
following formula:
Vm = 0.85 x Pm/100 x R x (F1 - F0)/F0
Vm = Increase or decrease in the cost of work during the month under consideration due
to changes in rates for local materials other than cement, steel bitumen and POL
M0 = The all India wholesale price index (all commodities) on 28 days preceding the
date of opening of Bids, as published by the Ministry of Industrial Development,
Government of India, New Delhi.
M1 = The all India wholesale price index (all commodities) for the month under
consideration as published by the Ministry of Industrial Development, Government
of India, New Delhi.
Pm = Percentage of local materials component (other than cement, steel bitumen and
POL of the work)
Component percentage as given below are as of the total cost of work put to tender,
3. ERASER:
Persons tendering are informed that no erasers of any alterations by them in the text of the
documents set herewith will be allowed and any such eraser or an alteration will be
disregarded. If there is any error in writing, no overwriting should be done but the wrong
words or figures should be struck out and the correct one written above or near it in an
unambiguous way. Such correction should be initialed and dated.
4. ACCEPTANCE:
Intimation of acceptance of tender will be given by a telegram or a letter sent by Registered
Post to the address given below the signature of the tenderer in the tenders. The tenders
which do not fulfill any of the above conditions or those in the form and which are incomplete
in any respect shall be liable for rejection.
(B) In all cases of omission and / or doubts of discrepancies in the dimensions or description of
any item or specifications, a reference shall be made to the Engineer, whose elucidation,
elaboration or decision shall be considered as authentic. The contractor shall be held
responsible for any errors that may occur in the work through lack of such reference and
precaution.
PROGRESS SCHEDULE
(b) The Contractor shall furnish within the period stipulated in writing by the Engineer-in-charge of
the order to start the work, progress schedule using PERT/CPM technique in quadruplicate
indicating the date of actual start, the monthly progress expected to be achieved and
anticipated completion date of each major item of work to be done by him, also indicating and
setting up materials, plants and machinery. The schedule is to be such as is practicable of
achievement towards the completion of the whole work in the time limit and of the particular
items, if any on the due date specified in the contract and shall have the approval of the
Engineer-in-charge. No revised schedule shall be operative without such acceptance in
writing. The Engineer is further empowered to ask for more detailed schedule or schedules in
weekly form, for any item or items, in any case of urgency of work as will be directed by him
and the contractor shall supply the same as and when asked for.
(c) The Contractor shall employ sufficient plant, equipment and labour as may be necessary to
maintain the progress schedule. The working and shift hours restricted to one shift a day for
operations to be done under the Government supervision shall be such as may be approved
by the Engineer-in-charge. They shall not be varied without the prior approval of the Engineer.
Night work requiring supervision shall not be permitted expect when specifically allowed by
Engineer on each item, if requested by Contractor. The Contractor shall provide necessary
lighting arrangements etc. for night work as directed by the Engineer without extra cost to
Government. Further, the contractor shall submit the progress of work in prescribed forms
and charts etc. at periodical intervals, as may be specified by the Engineer-in-charge.
Schedule shall be in the form of progress charts, forms, progress statement and/or reports as
may be approved by the Engineer. The contractor shall maintain proforma, charts, details
regarding machinery, equipment, labour, materials, personnel etc. as may be specified by the
Engineer and submit periodical returns thereof as may be specified by the Engineer-in-
charge.
6.5 QUARRIES:
6.5.1 The Contractor (s) shall have to arrange himself / themselves to procure the quarry. However
necessary assistance without any extra cost to Government will be rendered by the
Department for procuring the quarries if required by the Contractor.
6.5.2 The quarrying operation shall be carried out by the Contractor with proper equipment such as
compressor, jack-hammers, drill bits, explosives etc. and sufficient numbers of workmen shall
be employed so as to get the required out-turn.
6.5.3 The Contractor shall carry out the works in the quarries in conformity with all the rules and
regulations already laid down or that may be laid down from time to time by the Government.
Any cost incurred by the Government due to noncompliance of any rules or regulations or due
to damages by the Contractor shall be the responsibility of the Contractor. The Engineer-in-
charge or his representative shall be given full facility by the Contractor for inspection at all
times of the working of the quarry, records maintained, the stocks of the explosives and
detonators etc. So as to enable him to check that the working records and storage are all in
accordance with the relevant rules. The Engineer-in-charge or his representative shall at any
times be allowed to inspect the work, building and equipment at the quarters.
6.5.4 The Contractor shall maintain at his own cost the books, registers etc. required to be
maintained under the relevant rules and regulations and as directed by the Engineer-in-
charge. These books shall be open for inspection at all times by the Engineer-in-charge or his
representative and the Contractor shall furnish the copies or extract of books or registers as
and when required.
6.5.5 All quarrying operations shall be carried out by the Contractor in organized and expeditious
manner, systematically and with proper planning. The Contractor shall engage licensed
blasters and adopt electric blasting and / or any other approved method which would ensure
complete safety to all the men engaged in the quarry and its surroundings. The Contractor
shall himself provide suitable magazines and arrange to procure and store explosives etc. as
required under the rules at his own cost. The designs and the location of the magazine shall
be got approved in advance from the Chief Inspector of Explosives and the Rules and
Regulations in this connection as laid down by the Chief Inspector of Explosives from time to
time shall be strictly adhered to by the Contractor. It is generally experienced that it takes time
to obtain the necessary license for blasting and license for storage of materials from the
concerned authorities. The Contractor must therefore, take timely advance action for
procuring all such licenses so that the work progress may not be hampered.
6.5.6 The approaches to the quarrying place from the existing public roads shall have to be
arranged by the Contractor at his own cost and the approaches shall be maintained by the
Contractor at his own cost till the work is over.
6.5.7 The Quarrying operations shall be carried out by the Contractor to the entire satisfaction of
the Engineer-in-charge and the development of the quarry shall be made efficiently so as to
avoid wastage of stones. Only such stones as are of the required quality shall be used on
the work. Any stone which is in the opinion of the Engineer-in-charge , not in accordance with
the specifications or of required quality will be rejected at any time, at the quarry or at the site
of work. The rejected stones shall not be used on the work and such rejected materials shall
be removed to the place shown at the Contractor's cost.
6.5.8 Since all stones quarried from Government quarry (if made available) by the Contractor
including the excavated over burden are the property of the Government, no stones or earth
shall be supplied by Contractor to any other agencies or works and are not allowed to be
taken away for any other works. All such surplus quarried materials not required for work
under this contract shall be the property of the Government and shall be handed over by the
Contractor to the Government free of cost at the quarry site duly heaped at the spots
indicated by the Engineer-in-charge.
6.5.9 Quarrying permission will have to be directly obtained by the Contractor, from the Collector of
the District concerned for which purpose the Department will render necessary assistance.
All quarry fees, royalty charges, Octroi duties, ground rent for staking material etc. if any to
be paid, shall be paid directly by the contractor as per prevailing rules in force.
6.5.10 The Contractor will be permitted to erect structures such as stores, office, huts for the labours
at his own risk and cost at the quarry site, if suitable vacant space in Government area is
available for the purpose at places approved by the Engineer-in-charge . On completion of the
work the Contractor shall remove all the structures erected by him and restore the site to its
original condition.
6.5.11 The Contractor shall not use any land in the quarry for cultivation or for any other purpose
except, that required for breaking or stacking or transporting stones.
6.6 COLLECTION OF MATERIALS:
(I) Where suitable and approved P.W. Department's quarries exist the Contractor or piece
worker will be allowed if otherwise there is no objection to obtain the materials to the extent
required for the work from the quarry. He will be, however, liable to pay compensation, if any
damage caused to the quarry either deliberately or through negligence or for wastage of
materials by himself or his staff or labour. The Contractor shall pay necessary royalty in
advance and claim refund according to rules, if admissible and shall submit detailed accounts
of materials quarried as directed.
(II) Where no suitable P.W. Department's quarries exist or when the quantity of the material
required cannot be obtained from a P.W. Department quarry, the Contractor or piece worker
shall make his own arrangements to obtain the material from existing or a new quarry in
Government waste land, private land or land belonging to other States or Talukas etc. After
opening the quarry but before starting collection, the quarry shall be got approved from the
Engineer-in-charge or his representatives. The Contractor or piece worker shall pay all royally
charges, compensation etc. No claims or responsibility on account of any of obstructions
caused to execution of the work by difficulties arising out of private owners of the land will be
entertained.
(III) The rates in the tender, include all incidental charges such as opening of a new quarry,
opening out a new portion in an existing quarry, removing top soil and the unsuitable material,
dewatering, quarry, cost of blasting powder and fuse, lift and lead, repairs to existing cart
tracks, making new cart tracks, control charges, Central/State Government or Municipal
Taxes, etc.
(IV) The rates in the tender are for the delivery of the approved material on road side, properly
stacked at the places specified by the Engineer-in-charge and are inclusive of conveyance
charges in respect of the leads and lifts. No claims on account of changes in lead will be
entertained.
(V) No material shall be removed from the land within the road boundary or from the land
touching it without the written permission of the Engineer-in-charge or his authorised agent. If
any material is unauthorisely obtained from such places, the Contractor or piece worker shall
have to make good the damages and pay such compensation, in addition as may be decided
by the Executive Engineer and will have to stop further collection.
(VI) Any material that falls on any P.W.D. Road from the cart etc. during conveyance shall be
immediately picked up and removed by the Contractor or piece worker, failing which it will be
got removed departmentally at his cost. No heap shall be left prior to stacking even
temporarily on the road surface or in any way so as to cause any obstruction or danger to the
traffic. The Contractor or the piece worker shall be liable to pay for any claims of
compensation etc. arising out of any accident, etc. Any such materials causing obstruction or
danger etc. will be got removed departmentally at his cost and no claim for any loss or
damage to the material, thus removed will be entertained. The Contractor shall also be
responsible for the damage or accident etc. arising out of any material that falls on the road
or track, not in charge of the Department and shall attend to any complaints which may be
received.
(VII) The materials shall not be stacked in place where it is liable to be damaged or lost due to
traffic passing over it, to be washed away by rain or floods, to be buried under the land slides
etc. or the slip down an embankment or hill side etc. No claims for any loss due to these and
similar causes will be entertained.
(VIII) Before stacking, the materials shall be free from all earth, rubbish, vegetable matter and other
extraneous substance and in the case of metal, screened to gauge if so directed when ready.
It shall be stacked entirely clear of the road way on ground which has been cleaned of
vegetation and levelled. On high banks, ghat roads etc. where it may not be practicable to
stack it entirely clear of the roadway, it may be stacked with the permission of the Engineer-
in-charge on terms in such a way as to cause minimum danger and obstruction to the traffic
or as may be directed by him.
(IX) The size of the stack of the materials other than rubble shall be 3 x 1.5 x 0.60 metre or such
other size as may be directed by the Engineer-in-charge and all but one stack in 200 metres
shall be of the same uniform size and shall be uniformly distributed over whole lengths. One
stack (at the end) in each 200 metres may be of length different from the rest in order to
adjust total quantity to be required but its width and height will be the same as those of the
rest.
(X) The Engineer in charge or his authorised representative shall supply the Contractor with
statement showing 200 metres wise quantities that will be required and the order in which the
collection is to be done. No materials in excess of requirements in that 200 metres shall be
stacked. Any excess quantity shall be removed at the expense of the Contractor or piece
worker to where it is required before the material in that 200 metres is finally measured.
(XI) All materials shall be examined and measured before it is spread. The labour for
measurements (and check measurements wherever carried out) shall be supplied by the
Contractor or piece worker. Immediately after the measurements are recorded, the stacks
shall be marked by the contractor or piece worker by white wash or otherwise as may be
directed by the Executive Engineer to prevent from any possibility of the same material being
measured and recorded over again and to prevent any unauthorized tampering with the
stacks. If the contractor or the piece worker fails to attend the measurements of materials
after receiving the notice from the Sub Divisional Officer or his subordinate stating date and
time of the intention to measure the work, the same shall be measured nevertheless and no
complaint in this respect will be entertained later-on. If the contractor or piece worker fails to
supply sufficient labour or the materials required at the time measurements or check
measurements, after due notice has been given to him, the expenses incurred on account of
employing departmental labour or material etc. shall be charged against his account.
The contractor shall himself engaged an authorised all time agent on the work capable of
managing and guiding the work and understand the specifications and contract condition. A
qualified and experienced, Engineer shall be employed by the contractor as his agent for
technical matters in case the Engineer-in-charge considers this as essential for the work and
so directs contractors. He will take orders as will be given by the Executive Engineer or his
representative and shall be responsible for carrying them out.
This agent shall not be changed without prior intimation to the Executive Engineer and his
representative on the work site. The Engineer-in-charge have the unquestionable right to ask
for change in the quality and strength of contractor’s supervisory staff and to order removal
from work of any of such staff. The contractor shall comply with such orders and effect
replacements to the satisfaction of the Engineer-in-charge.
A work order book shall be maintained on site and it shall be the property of the Government
and the contractor shall promptly sign orders given therein by the Executive Engineer or his
representative and his superior officers and comply with them. The compliance shall be
reported by the Contractor to the Engineer in good time so that it can be checked. The blank
work order with machine numbered pages will be provided by the Department free of charge
for this purpose. The contractor will be allowed to copy out instructions therein from time to
time.
64 Dy. Executive Engineer
The Contractor shall have to make his own arrangement for machinery required for the work.
However if the same is conveniently available with the Department it may be spared as per
the rules in force on recovery of necessary Security Deposit and rent at the rate approved
from time to time by the independent agreement to this contract and the supply or non supply
of machinery shall not form a ground for any claim or extension of time for this work.
iv) The contractor shall not be eligible for any claim or compensation either rising out of any
delay in the work or due to any corrective measure required to be taken on account of and as
a result of testing of the materials.
v) The contractor or his authorised representative will be allowed to remain present in the
Department laboratory which testing the samples furnished by him. However the results of all
the tests carried out in the Departmental laboratory whether in the presence or in absence of
the contractor or his authorised representative will be binding on the contractor.
vi) Quality Control Tests :- The contractor shall at his own cost set up Laboratory at site of work
to carry out the routine test of materials which are to be used on the work. The site laboratory
shall be approved and certified by the Engineer in charge. The quality control tests of material
to be carried out are mentioned in Annexure ‘A’ Page No.80 to 81. The frequency of testing
of construction material is mentioned in Annexure ‘B’ on page No.82 to 83. Out of the test
material in Annexure ‘A’ 70% tests shall be carried out in site laboratory and 30% tests shall
be carried out Vigilance & Quality Control laboratory at cost of contractor. At least 50% test
materials shall be carried out in Vigilance and Quality control laboratory of department which
are not included in Annexure ‘A’ at the cost of contractor.
7.2 CO-ORDINATION:
When several agencies for different sub-works of the project are to work simultaneously on
the project site, there must be full coordination between the contractors to ensure timely
completion of the whole project smoothly. The scheduled dates for completion specified in
each contract shall therefore, be strictly adhered to. Each contractor may make his
independent arrangements for water, power, housing etc. if they so desire. On the other hand
the Contractor are at liberty to come to mutual agreement in this behalf and make joint
arrangements with the approval of the Engineer. No Contractor shall take or cause to be
taken any steps or action that may cause, disruption, discontent, or disturbance of work,
labour or arrangement etc. of the contractor in the project localities. Any action by any
Contractor which the Engineer in his unquestioned discretion may consider as infringement of
the above code, would be considered as a breach of the contract conditions and shall be
dealt-with accordingly.
In case of any dispute of disagreement between the Contractors, the Engineer’s decision
regarding the co-ordination, co-operation and facilities to be provided by any of the Contractor
shall be final and binding on the contractors concerned and such a decision shall not vitiate
any contract nor absolve the Contractor of his obligations under the contract nor consider
from the grounds for any claim or compensation.
II) The contractor shall provide furnish, maintain and remove on completion of the work a
suitable office on the work site for the use of Executive Engineer or his representative. The
covered area exclusive of verandah should not be less than 40.00 sqm. It may have brick
walls and asbestos or corrugated iron roof, paved floor should be 45 centimetre. above
ground level. He should provide latrines, urinals and keep them clean daily. This will be
supposed to be included in his offer.
When the Contractor desires to use any designed device, materials or process covered by
letter of patent or copy right, the right for such use should be secured by suitable legal
arrangement and agreement with patent owner and a copy of their agreement shall be filed
with the Engineer-in-charge if so desired by the latter.
The Contractor shall make his own arrangements at his own cost for entering into contract
with concerned authorities for obtaining the connection and carry the water upto the work site
as required by him. The location of the pipe line with respect to the road shall be decided by
Engineer-in-charge and shall be binding on the Contractor.
The Contractor is advised to provide water storage tank of adequate capacity to take care of
possible shutdown of water supply system.
The Contractor shall have to supply water required by the Department for its establishment at
work site. The water consumed by the Department will be metreed. For providing the metre
permission, if necessary will be arranged by the Department. Charges for the water
consumed by the Department will be paid to the Contractor at the rates of 125% of the
recurring costs or actually charged to him by concerned authorities and no other charges
would be payable by the Department.
7.6 ELECTRICITY :
The Contractor will have to make his own arrangement at his own cost for obtaining or
providing electric supply at work site.
Electrical supply for the Departments use at work site shall be provided by the contractor. No
charges would be payable by the Department.
8. SAFETY MEASURES AND AMENITIES :
(i) Providing protective foot-wear to workers, in situations like mixing and placing of
mortar or concrete, in quarries and place where the work is to be done under too
much wet conditions as also for movements over surfaces infected with oyster growth
etc.
(ii) Providing protective head wear to workers, working in quarries etc. to protect them
against accidental fall of materials from above.
(iii) Taking such normal precautions like providing hand rails to the edges of the floating
platform or barges, not allowing nails or metal parts or useless timber to spread
around etc.
8.2 AMENITIES :
(I) Supporting workmen with proper belts, ropes etc. when working on any masts,
cranes, grabs, hoist, dredger etc.
(ii) Taking necessary steps towards training the workers concerned of the use of
machinery before they are allowed to handle it independently and taking all
necessary precautions in and around the areas where machines, hoists and similar
units are working.
(iv) Making all platforms, stagings and temporary structures sufficiently strong and not
causing the workmen and supervisory staff to take undue risks.
(v) Providing sufficient first aid trained staff and equipment to be available quickly at the
work site to render immediate first aid treatment in case of accidents due to
suffocation, drowning and other injuries.
(vi) Providing full length gum boots, leather hand gloves, leather jackets with fireproof
aprons to cover the chest and black reaching upto knees plain goggles for the eyes to
the labour working with hot asphalt handling vibrators in cement concrete and also
where use of any or all these items is, essential in the interest of health and well
being of the labourers in the opinion of the Engineer.
8.3 EXPLOSIVE :
The Contractor shall at his own expense construct and maintain proper magazines, if such
are required for the storage of explosives for use in connection with the work and such
magazines, being situated constructed and maintained in accordance with the Government
Rules applicable in that behalf. The Contractor shall at his own expenses obtain such license
or licenses as may be necessary for storing and using explosives. Notwithstanding that the
location etc. or storage of explosives are approved by the Engineer, the Government, shall
not bear any responsibility whatsoever in connection with the storage and use of explosives
on the site or any accident or occurrence what -so-ever in connection, therewith, all
operations of the Contractor in or for which explosives employed being at the risk of
contractor and upon his sole responsibility and the Contractor hereby gives to Government an
absolute indemnity in respect thereof.
POLICE PROTECTION:
For the Special Protection of camp of the Contractor's works, the Department will help the
Contractor as far as possible to arrange for such protection with the concerned authorities, if
so required by the contractor in writing. The full cost of such protection shall be borne by the
Contractor .
8.6 INDEMNITY:
The Contractor shall indemnify the Government against all actions, suits, claims and
demands brought or made against it in respect of anything done of committed to be done by
the contractor in execution of or in connection with the work of this contract and against any
loss or damage to the Government in consequence to any action or suit being brought against
the Contractor for anything done or committed to be done during the execution of this
contract.
The Government may at its discretion and entirely at the cost of the contractor defend such
suit, either jointly with the Contractor or single in case the latter chooses not to defend the
case.
a) The Contractor shall provide an adequate supply of pure and wholesome water for the use of
labourers on work and in camps.
b) The Contractor shall construct trench or semi permanent latrines for the use of the Labours.
Separate latrines shall be provided for men and women.
c) The Contractor shall build sufficient number of huts on a suitable plot of land for use of the
labourers according to the following specifications:-
1. Huts with Bamboo’s and Grass may be constructed.
2. A good site not liable to submergence shall be selected on high ground remote from
jungle but well provided with tress, shall be chosen wherever it is available. The
neighborhood of tank, jungle, trees or wood should be particularly avoided, Camps
should not be established close to large cutting of earth work.
3. The lines of huts shall have open space of atleast ten metres between rows. When a
good natural site cannot be procured, particular attention should be given to the
drainage.
4. There should be no over crowding. Floor space at the rate of 3 Sq. metre per head
shall be provided. Care should be taken to see that the huts are kept clean and in
good order.
5. The Contractor must find his own land and if he wants Government land, he should
apply for it. Assessment for it, if demanded will be payable by Contractor. However
the Department does not bind itself for making available the required land.
b) The Contractor shall engage a Medical Officer with a travelling dispensary for
a Camp containing 500 or more persons if there is no Government or other
private dispensary situated with 8 Kms. from the camp. In case of
emergency the Contractor shall arrange a this cost of transport for quick
medical help to his sick worker.
c) The Contractor shall provide the necessary staff for effecting satisfactory
conservancy and cleanliness of the camp to the satisfaction of the Engineer-
in-charge. Atleast one sweeper per 200 persons should be engaged.
f) The anti-malaria and other health measures shall be as directed by the Joint-
Director (Malaria and Filaria) Health Services, Pune.
h) Contractor shall carry out anti-malaria measures in the area as per guidelines
prescribed under National Malaria Eradication Programme and as directed by
the Joint Director, (M & F) of Health Services Pune.
i) In case of default in carrying out prescribed antimalaria measures resulting in
increase in Malaria incidence, contractor shall be liable to pay to Government
the amount spent by Government on anti-malaria measure to control the
situation in addition to fine.
j) The Contractor shall make sufficient arrangements for draining away the
surface and sullage water as well as water coming from the bathing and
washing places and shall dispose off this waste water in such way as not to
cause any nuisance. He shall also keep the premise clean by employing
sufficient number of sweepers.
k) The Contractor shall comply with all rules, regulation bye-law and directions
given from time to time by any local or public authority in connection with this
work and shall pay fees or charges which are leviable on him without any
extra cost to Government.
l) In addition to above all provisions of the relevant labour act pertaining to
basic amenities to be provided to the labourer shall be applicable which will
be arranged by the Contractor.
9. MISCELLANEOUS :
9.1 For providing electric wiring or water lines ete. recesses shall be provided if necessary
through walls, slabs, beams etc. and later on refilled it with bricks or stones, chipping cement
mortar without any extra cost.
9.2 In case it becomes necessary for the due fulfillment of contract for the Contractor to occupy
land outside the Department limits, the Contractor will have to make his own arrangements
with the land owners and pay such rents, if any, are payable as mutually agreed between
them.
9.3 The Contractor shall duly comply with the provision of the Apprentices Act 1961 (iii of 1961)
and the rules and orders made thereunder from time to time under the said Rules and on his
failure or neglect to do so he shall be subject to all the liabilities and penalties provided by the
said Act and Rules.
9.4 It is presumed that the Contractor has gone carefully through the Standard Specification (Vol.
I & II 1981 Edition) M.O.R.T. & H specifications (edition 2001) and Schedule of Rate of the
division, and studied the site conditions before arriving at rates quoted by him. The special
provisions and detailed specification of wording of any item shall gain precedence over the
corresponding contrary provisions (if any) in the standard specification given without
reproducing the details in contract. Decision of Engineer-in-charge shall be final in case of
interpretation of specification.
9.5 If the standard specifications fall short for the items quoted in the schedule of this contract
reference shall be made to the latest Indian Standard specifications, I.R.C. codes. If any of
items of this contract do not fall in reference quoted above, the decision and specifications as
directed by the Engineer-in-charge shall be final.
9.6 The stacking and storage of building materials at site shall be in such a manner as to prevent
deterioration or inclusion of foreign materials and to ensure the preservation of the quantity,
properties and fitness of the work. Suitable precautions shall be taken by Contractor to
protect the materials against atmospheric action fire and other hazards. The materials likely
to be carried away by wind shall be stored in suitable stores or with suitable barricades and
where there is likelihood of subsidence of soil, heavy materials shall be stored on paved
platforms. Suitable separating barricades and enclosure as directed shall be provided to
separate materials brought by contractor and from different sources of supply.
10. DEFINITIONS :
Unless excluding by or repugnant to the context :-
a) The expression "Government" as used in the tender documents shall mean the Public
Works Department of the Government of Maharashtra.
b) The expression "The Chief Engineer" as used anywhere in the tender papers shall mean
officer for the time being of the Government of Maharashtra who is designated as such.
c) The expression "Superintending Engineer" as used in the tender papers shall mean the
officer of Superintending Engineer rank (by whatever designation he may be known) under
whose control the work lies for the time being.
e) The expression "Contractor" as used in the tender papers shall mean the successful
tenderer that is the tenderer whose tender has been accepted, and who has been authorised
to proceed with the work.
f) The expression "Contract" as used in the tender papers shall mean the deed of contract
together with or its original accompaniment and those later incorporated in it by mutual
consent.
g) The expression "Plant" as used in the tender papers shall mean very temporary and
necessary means necessary or considered necessary by the Engineer to execute, construct,
complete and maintain the works and used in altered, modified, substituted and additional
works ordered in the time and in the manner herein provided and all temporary materials and
special and other articles of appliances of every sort, kind and description whatsoever
intended or used therefor.
h) The expression “Department” as used in the tender papers shall means Public Works
Department of Government of Maharashtra.
i) The “Accepting authority” shall mean the officer competent to accept the tender.
j) The “Site” shall mean the land and/or other places where the work is to be executed under
the contract including any other land or places which may be allotted by the Government or
use for the purpose of contract.
The Engineer in charge shall decide all questions which may arise as to quality and
acceptability of materials furnished and work executed, manner of execution, rate of progress
of the works, interpretation of the plans and specifications and acceptability of fulfillment of
the contract on the part of the Contractor . He shall determine the amount and quantity of
work performed and materials furnished and his decision shall be final. In all such matters,
and in any technical questions which may arise touching the contract, his decision shall be
binding on the Contractor.
The Engineer in charge shall have the power to enforce such decisions and orders if the
Contractor fails to carry them out promptly. If the Contractor fails to execute the work ordered
by the Engineer-in-charge . The Engineer in charge may give notice to Contractor specifying
a reasonable period therein and on the expiry of that period proceed to execute such work as
may be deemed necessary and recover the cost there of from the Contractor.
b) If the Contractor is dissatisfied with any decision of the Representative of the Engineer-in-
charge he shall be entitle to refer the matter to the Engineer-in-charge, who shall there
upon confirm/reverse or vary such decision.
Layout of the work will be done by the Contractor in consultation with the Executive Engineer of
the Department or his representative, some permanent marks should however be established to
indicate the demarcation of the structure or any component there of made to this permanent marks
in measurement books and drawing signed by the contractor and the departmental officer,
Responsibility regarding layout will be joint.
Setting out the works as spelt out in clause 109 of Ministry’s specifications for Road and Bridge
works (2nd Revision) will be carried out by the Contractor.
Immediately on receipt of the work order, the contractor shall at his own expenses clean the site
and take up a provisional and final setting out and lining out of the work under the supervision of
his responsible representative and shall provide necessary material, labour, tools, instruments etc.
required for the same.
Immediately on receipt of the work order, the Contractor shall at his own expense clean the site
and take up a provisional and final setting out and lining out of the work under the supervision of
his responsible representative and shall provide necessary material, labour, tools, instruments etc.
required for the same.
One tentative abutment location will be indicated by Engineer-in-charge and the centre line of the
bridge shall be defined by him. The Contractor will then have to fix up the location of the other
abutment. The abutment location will then be verified by the Department and may be adjusted.
Once the final location of abutments is so finalised, it will be the Contractor’s responsibility to line
out and locate the remaining foundations.
The Contractor shall be responsible for true and proper setting out of the works and for the
correctness of the positions, level dimensions and arrangements of all parts of works, and for
providing all necessary instruments appliances and labours in connection therewith at his own
cost. Officers may be allowed to be used for setting out of work for which no cost shall be
recovered from the Contractor. If at any time during the progress of work, any errors arise in
regard to levels or dimensions or alignment of any part of the work, rectification thereof, on being
required to do, will be carried out by the Contractor at his own cost, unless such errors are based
on incorrect data, supplied in writing, by the Engineer or his authorised representative in which
case the expenses of the rectification shall be refunded by Government.
The checking of any setting out or checking of levels by the Engineer or his authorised
representative shall not in any way relieve the Contractor of his responsibility for the correctness
thereof. The Contractor shall carefully protect and preserve all bench marks site rails, pegs and
other things used in setting out of works.
The Work of setting out shall be deemed to be a part of general works preparatory to the
execution of work and no separate payment shall be made for the same.
WATER :- If the potable water is not available in the river bed the contractor has to make his own
arrangements for potable water required for concrete mixing, its curing and other parts of the
construction for which no extra claim will be paid by the department.
16.2 The Contractor shall at his own expense engage watchman for guarding the materials and
plant and machinery and the work during day and night against any pilferage or damage and
also for prohibiting trespassers.
16.3 No materials brought to the site shall be removed from the site without the prior approval of
the Engineer-in-charge.
17.2 The Contractor shall provide at his cost necessary ladders and such arrangements as are
considered safe by the Engineer-in-charge for proper inspection of all parts of the work.
17.3 Contractor shall extend his full co-operation and make all necessary arrangements when
needed for carrying out inspection of the work or any part of the work by the local
representatives, M.L.As, M.Ps and officers and dignitories / delegates of various Government
departments, local bodies, private sectors etc. No compensation shall be paid to the
contractor on this account.
17.4 The work shall be carried out by the Contractor without causing damage to the existing
Government property and / or private property. If any such damage are caused, the
Contractor shall pay for restoration of the property to the original conditions, and any other
consequent damages.
17.5 In the event of the occurrence of an accident involving serious injuries or death of any person,
at site of work or quarry or at any place in connection with the work the same shall be
reported in writing within twenty-four hours of the occurrence to the Engineer-in-charge and
Commissioner of Workmen's compensation.
17.6 The Contractor after completion of work shall clean the site of all debris and remove all
unused materials other than those supplied by the department and all plant and machinery,
equipment, tools etc. belonging to him within one month form the date of completion of the
work, or otherwise the same will be removed by the department at his cost or disposed off as
per departmental procedure. In case the material is disposed off by the department, the sale
proceeds will be credited to the Contractor’s account after deducting the cost of sale incurred.
However, no claim of Contractor regarding the price or amount credited will entertained
afterwards.
17.7 All constructional plant, provided by the Contractor shall when brought on to the site be
deemed to be exclusively intended for the construction and the contractor shall not remove
the same or any part thereof (save for the purpose of moving it from one part of the site to
another) without the consent in writing of the Engineer-in-charge who shall record the reasons
for withholding the consent.
19.3 In case defects noticed by the Engineer-in-charge which in his opinion are not rectifiable but
otherwise work is acceptable at reduced payment, work shall be treated as completed. In
such cases completion certificate shall be issued by the Engineer-in-charge within 30 days
indicating the un-rectifiable defects for which reduction in payment is being made by him.
19.4 The issued of completion certificate shall not be linked up with the site clearance on
completion of the work.
21 SPECIAL CONDITIONS:
21.1 The Contractor should ensure that all safety precautions are observed by their laboures,
working closed to the State Highway and while closing the State Highway precautions are
taken including insurance etc., for their labour at the cost of the contractor and the contractor
will bear all the expenses, compensation etc. if any accident occurs to the labour etc. No
claim in this regard on whatsoever account shall be entertained and this decision of the
Department will be final and conclusive.
21.2 The Contractor shall observe the rules and regulation imposed by traffic police for smooth
flow of traffic on the diversion road and shall not be entitled for claims any compensation
arising thereof.
21.3 In case of delay in handing over the land required for the work, due to unforeseen cause, the
Contractor shall not be entitled for any compensation what-so-ever form the Government on
ground that the machinery or labour was idle for certain period. Contractor may, however
apply for extension of time limit which may be granted on the merit of the case.
Materials not corresponding in character and Quality with approved samples will be rejected
by the Engineer or his representative and shall be removed from site at the Contractor’s own
cost.
29. DIARY:
Contractor shall maintain, throughout the construction period, a diary in the from of a register
regarding the following:
i) Daily presence of all categories of labours.
ii) Daily availability and use of machinery and equipment’s on work.
iii) Daily procurement, Consumption and balance of materials on site.
iv) Daily record of various visiting authorities alongwith name of the officers visited &
timing.
v) Details of work executed per day. The register shall be closed on daily basis and
signature of Engineers in charge or his representative should be taken over it.
30.2 The orders issued by the Government in P.W. Department and the Superintending Engineer,
Thane (P.W.) Circle, Thane from time to time regarding construction procedure shall be
binding on the contractor in addition to the specification contained in P.W.D. hand book
Volume I & II and book of standard specification of P.W. Department and the specifications
enumerated above.
30.3 The contractor shall submit day to day account of the materials issued to him and its use and
also monthly progress and programme of work.
30.4 a) The concrete mix design shall be got approved from Engineer in charge and the mix
design shall give preliminary strength of 1.33 times working strength.
b) The maximum size of aggregate permisible would be as per A-7 page-8 of Standard
Specifications Book 1979 Edition.
30.5 The items provided with watering for curing include continuous watering operations through
out the day including lunch hours and also during holidays. For this purpose contractor shall
have to construct tank of appro. 5000 liters capacity near each building and provide
necessary Booster Pumps etc. to ensure adequate curing and wetting. Hold fasts coming in
contact with R.C.C. columns shall be of sizes 30 centimetre x 4 centimetre to be fitted with
two rows, nails fixed properly in concrete.
30.6 For all sand covering items, use of washed mixer sand (with sand washing machine) is
obligatory. No separate claim in this regard will be entertained.
30.7 Material testing requirement frequency and type of testing is enclosed separately. Material to
be used shall be tested accordingly and cost shall be borne by contractor.
30.8 For R.C.C. centering plywood and M.S. sheet of approved quality shall be used and
adjustable props and fasteners shall be used.
30.9 The execution of any work from external side of the building 'H' frame steel scaffolding shall
be used. No separate payment for claims in this regard shall be entertained.
30.10 The scaffolding shall not be supported on existing external walls of the building by making
holes in it and also the scaffolds shall not rest on any part of the building.
31 Quality Assurance Manual: Contractor shall prepare the quality assurance manual booklet in
consultation with the Executive Engineer. Quality assurance manual shall be comprehensive
document covering every aspect of the work. Superintending Engineer shall approve this
document. The quality manual document shall be used only after approval from
Superintending Engineer. Provision of the quality manual be binding on the contractor. Quality
manual shall be treated as a legal document as per with this contract document. It shall be
used till the work is completed in full respect.
33 Value Added Tax @ 2% of the contract amount will be recovered from the bill of contractor
who are registered under Maharashtra Value Added Tax Act 2005 and 4% of the contract
amount will be recovered from the contractor’s bill amount those who are not registered under
Maharashtra Value Added Tax Act 2005
1. CONTRACTOR’S FACILITIES:
According to the contract (See para 1.3 above) the Contractor is responsible for the quality of
the entire construction work and for this purpose hi is required to have his own independent
and adequate set up. To meet this requirement:
a) The Contractor shall up his own laboratory location(s) approved by the Engineer. The
laboratory shall be equipped with modem and efficient equipment with sufficient
standby’s suitable to carry out the tests prescribed fir different material and work
according to the specifications. The list of equipment to be procured and the facilities
to be provided shall be got approved by the Engineer. The equipment shall be
maintained in a workable condition to the satisfactory of the Engineer.
b) Sampling and testing procedures shall be in accordance with the relevant standards
of BIS (previously called ISI) or IRC, Frequency of testing shall be as laid down in the
Ministry’s specifications for Road and Bridge work (2nd Revision. 1990). In the
absence of relevant Indian standards sampling and testing procedures shall be as
approved by the Engineer.
c) The laboratory should be manned by a qualified Materials Engineer assisted by
Materials Inspector / Technicians, and the set up should be got approved by the
Engineer.
b) The Contractor should prepare printed Performa for recordings and results of each
type of test after getting the formats of the performance approved from the Engineer.
He should keep a daily record of all the tests conducted by him. Two copies of the
test results should be submitted to the Engineer for his examination and approval of
which one copy will be returned to the Contractor for being kept at site of work.
c) The Materials Engineer of the Contractor should keep close liaison with the Quality
Control Unit of the Engineer and keep the latter informed of the sampling and testing
programme so that the Engineer’s representative could be present during this activity,
if considered necessary.
b) The Engineer’s Quality Control Unit(s) shall have independent test checks on the
quality and compaction of the natural ground / cut formation.
EMBANKMENT CONSTRUCTION:
a) All borrow areas shall be got approved by the Engineer based on result of tests for
Alterberg Limits Proctor / modified proctor density, CBR and soil classification.
b) Layer thickness and in-situ density shall be checked and got approved by the
Engineer before proceeding to the next layer.
SUB-GRADE
a) Specific borrow areas having soil satisfying the requirements of specifications and
specified strength criteria shall be identified for use in sub-grade and got approval by
the Engineer based on tests on borrow material for proctor / modified proctor density
and CBR.
b) In-situ density and CBR of the constructed sub-grade shall be checked and to
approved by the Engineer before proceeding on with the next pavement layer.
c) The soil used in actual construction of sub-grade shall be remolded at density
referred in sub-grade (b) above at placement moisture content and checked for 4
days soaked and insolated CBR. A set 3 specimens shall be collected from each
3000 cum area of the sub-grade (i.e. top 0.5 embankment) for CBR test.
d) In case of any appreciable variation of in built sub-grade characteristic form the
designed ones the pavement design shall be reviewed to match the inbuild
characteristics of the sub grade.
SUB – BASE
a) The source of supply material shall be inspected, tested and got approved by the
Engineer before any material is delivered to the site of work(s).
b) Job-mix formula falling within the specified limits where applicable, shall be got
approved by the Engineer based on test results thereof.
c) Samples of material from the laid sub-base shall be tested for gradation, proctor
density, PI and CBR.
d) Field compaction shall be checked and got approved by the Engineer before
proceeding with the work on the next pavement layer.
e) In case of any appreciable variation of in-built sub-base characteristics from the
designed ones the pavement design shall be reviewed to match the in-built
characteristics of the sub-base.
SHOULDERS:
a) Checking for the quality of shoulders materials including gradation shall be done.
b) Field compaction shall be checked at site on the compacted layer.
c) Checking for the cross fall built shall be done.
d) In case of masonry work, control should be exercised on the quality of the material
(e.g. stone, brick, sand, cement, etc.) as also on mortar proportions.
e) For RCC work, quality of steel in each batch may be approved on the basis of test
certificate. The reinforcement layout should be checked for conformity with approved
drawings and bar bending schedules. All laps should be checked for conformity with
the specification. The reinforcement should be free of oil and loose rust scale and
should be properly tried with binding wire. The size and spacing of the bars as also
the cover should be checked for correctness.
ANNEXURE – A
ANNEXURE – B
´ÉÉ®Æú´ÉÉ®úiÉÉ SÉÉSÉhÉÒ (Frequency Test) +x´ÉªÉä xɨÉÖnù Eäò±É䱪ÉÉ SÉÉSÉhÉÒxÉÖºÉÉ®úSÉ nùIÉiÉÉ ´É MÉÖhÉÊxɪÉÆjÉEò
¨ÉÆb÷³ýªÉÉSªÉÉ |ɪÉÉäMɶÉɳäýiÉÖxÉSÉ SÉÉSÉhªÉÉ +ɴɶªÉEò +ɽäþiÉ, iªÉÉ ºÉ´ÉÇ SÉÉSÉhªÉÉ {ÉÚhÉÇ Eò®úhªÉÉiÉ ªÉÉ´ªÉÉiÉ. xɨÉÖnù Eò®úhªÉÉiÉ
+ɱÉ䱪ÉÉ SÉÉSÉhªÉÉ{ÉèEòÒ EòɽþÒ SÉÉSÉhªÉÉ EòÉ¨É {ÉÚhÉÇ ZÉɱªÉÉxÉÆiÉ®½þÒ ¤ÉÉ¤É ÊxɽþÉªÉ ºÉÆ{ÉÚhÉÇ SÉÉSÉhªÉÉÆSªÉÉ ºÉÆJªÉäxÉÖºÉÉ®ú xɨÉÖnù
Eäò±ªÉÉ|ɨÉÉhÉä ZÉɱªÉÉ xɺɱªÉÉºÉ ºÉnù®ú½Úþ EòɨÉÉSªÉÉ +ÆÊiÉ¨É näùªÉEòÉiÉÖxÉ =´ÉÇÊ®úiÉ SÉÉSÉhÉÒ EòÊ®úiÉÉ +ɴɶªÉEò +ºÉhÉÉ®úÒ
¶É居 Eò (SÉÉSÉhÉÒSªÉÉ ºÉÆJªÉäxÉÖºÉÉ®ú) SÉÉSÉhÉÊxɽþÉªÉ {ÉÉSÉ {É]õÒxÉä +ÆÊiÉ¨É näùªÉEòÉiÉÖxÉ ´ÉºÉÖ±É Eò®hªÉÉiÉ ªÉä<DZÉ.ú
ADDITONAL SPECIFICATIONS
(For Concrete Work)
The contractor shall achieve that following requirements in respect of quantity of work and his contract
rate shall provided for the same.
1.1 ADMIXTURES :
Whenever necessary the admixture should be used to achieved the required workability. The
type of admixture should be got approved from Engineer-in-charge. The rate is inclusive of all
admixtures etc. if found necessary.
1.7 BAR SPACING : As per relevant I.S. codes and as detailed design drawing or as directed by
Engineer-in-charge.
1.8 HOLLOWS IN CONCRETE : After concreting is complete the concrete surface articularly
where there is congestion of reinforcement, shall be tested by light hammering or if possible
by Schmidtz hammer. Any portion showing signs of hollowness should be grouted
immediately.
I) FORMWORK :-
1.1 Formwork :- Formwork shall include all temporary forms of moulds required for forming the
concrete which is cst-in-situ, together with all temporary construction required for their
support. Unless otherwise stated all formwork shall conform to I.S. Specification.
1.2 Design of Formwork :- Formwork including complete false work shall be designed by the
contractor in accordance with I.S.: 2750 (1964), 4041 (1987) and all other relevant I.S. codes
without any extra cost to the Government and these shall be got approved from Engineer
before any formwork is taken up.
1.3 The contractor shall entirely be responsible for the adequancy and safety for false work not-
withstanding any approval or review by the Engineer of his drawing and design. Proprietary
system of formwork if used a detailed information shall be furnished to the Engineer for
approval.
2. QUALITY OF SHUTTERING: The shuttering shall have smooth and even surface and its
joints shall not permit leakage of cement slurry.
2.1 Ply-board shuttering materials to be used shall be steel shuttering/marine plywood well
seasoned free from projecting nails, splits or other defects that may mark on the surface of
concrete. It shall not be so dry as to absorb water from concrete, or so green or wet as to
shrink after erection. Mild steel plates or plywood shall be used for slab and beam bottoms.
2.2 The timber shall be accurately spawned planed on the sides and the surface coming in
contact with concrete.
2.3 So far as practicable, clamps shall be used to hold the forms together. Where use of nails is
unavoidable minimum number of nails shall be used and these shall be left projecting so that
they can be easily with drawn. use of double headed nails shall be prefered.
3. TOLERANCE :-
3.1 The formwork shall be made so as to produce finished concrete true to shape, lines, levels
plumb and dimensions as shown on the drawings, subject to the following tolerance unless
otherwise specified in these documents or drawings or as directed by the Engineer :
a) Section dimension = 5 mm
b) Plumb = 1 in 1000 of height
c) Levels = 3 mm before any deflection takes place.
3.2 Tolerance given above are specified for local aberrations in the finished concrete surface and
should not be taken as tolerance for the entire structure taken as a whole or for the setting
and alignment of formwork which should be as accurate as possible to the entire satisfaction
of the Engineer, Errors if noticed in any lift/ tilt of the structure after stripping of forms, shall be
corrected in the subsequent work to bring back the surface of the structure to its true
alignment.
5. REMOVAL OF FORMWORK :- The formwork shall be so removed that it shall not cause
damage to concrete. Centering shall be gradually and uniformly lowered in such a manner as
to avoid any shock or vibrations. Supports shall be removed in such a manner as to permit
the concrete to take stresses due to its own weight uniformly and gradually.
The whole of the formwork removal should be planned and definite scheme of operation shall
be worked out. Under no circumstances forms be struck until the concrete reaches a strength
of at least twice the stress to which the concrete may be subjected at the time of striking but
not before the period as mentioned in IS:456-2000 where ordinary portland cement is used.
2. For R.C.C. works formwork shall be of marine plywood of adequate thickness and grade only.
The centering and supporting arrangement such as standard steel trusses/ joists/ spans
standards adjustable/ fixed props. H type frames etc shall be designed by the Contractor and
approved from the Engineer before commencement of its erection. The Contractor with the
prior approval of the Engineer shall use standard steel centering arrangement which may be
manufactured by the reputed firm.
3. The supporting arrangement designed by the contractor shall conform to the relevant I.S.
code and Standard practice adopted in this type of work. The centering arrangement shall be
adequately braced and properly secured by using appropriate type of fastenings and fixtures
to ensure stability and rigidity of the centering to withstand all loads coming on it. The entire
responsibility for design, erection, maintenance and safety etc. will exclusively rest with the
contractor. The Engineer reserves right to call detailed design calculations of the entire
centering or part there of to verify its stability and also reserve tight to reject entire centering
arrangement or part there of and any material used for the centering in the event of which the
contractor shall have to arrange for its replacemnet at his own cost.
b) The design of concrete mixes for various concrete items in the work shall be obtained by the
contractor at his cost from and approved laboratory. The contractor shall submit in advance
details of such design to the Engineer-in-charge for his prior approval.
d) The concrete mix design shall give target strength of 1.33 times the working strength.
e) The minimum size of aggregate permissible shall be as per para A-7 of Page - 8 f of standard
specification book of 1979 Edition Vol. 1.
f) The provision of the specification No. B-7 at page - 38 to 40 of Vol. 1 1979 Edition of standard
specification book for controlled concrete shall be applicable for all the structural concrete
items. The maximum water cement ratio shall be 0.45. The mix design shall be done
accordingly.
g) All the expenses of preliminary mix design, subsequent field/ laboratory mix design, work
tests, shall be borne by the contractor.
2. FROMWORK FOR CONCRETE WORK :- The forms of concrete shall be of the materials as
directly by the Executive Engineer-in-charge and shall preferably be of steel or plywood,
Forms shall be of the required shape, profile and lines. Suitable devices shall be used to hold
corners, adjacent ends, edges of panel or other forms together in accurante alignment. The
forms and joints shall tight enough. Forms used for circular curved or structures of unusual
shape, petal dome etc. shall be of such a character that will result in smooth concrete surface
and exact shape. They shall be prepared such that they will not warp or distort during erection
or while placing concrete. Their design and layout shall be got approved form the Executive
Engineer-in-charge in advance.
3. ERECTION AND REMOVAL OF FORM WORK :- The centering and strutting shall be of
steel or plywood board exclusively for concreting. The design and drawing should be got
approved in advance from the Department. For minor members the Engineer-in-charge may,
at his discretion, permit use of wooden shuttering. The centering and shuttering shall be close
and tight to prevent leakage of cement slurry. The centering shall have the necessary props,
bracing and edges sufficiently strong and stable which shall not yield or displace while or after
laying of concrete. They shall be made in such way that they can be slackened and removed
gradually and slowly without distributing the concrete. Centering and shuttering shall not be
removed before the design strength is achieved.
4. MIXTURE OF CONCRETE :- Design mix concrete as well as nominal mix concrete shall be
mixed by following the provision in Standard specification at B. 6.4 unless otherwise directed
by the Engineer.
Unless otherwise agreed by the Engineer concrete shall be mixed in a batch type mixer of
such other type of mixer as the Engineer my approve.
During hot weather the Contractor shall ensure that the constituent materials are sufficiently
cool to prevent the concrete from stiffening in the intervals between its discharge from the
mixer and its final position.
No concreting shall be carried out during period of continuous heavy rains unless, it is
completely covered during mixing, transporting and placing, In extreme hot weather,
concreting shall be restricted to morning and evenings The time between mixing and placing
of concrete shall be kept to the minimum and formwork shall be cooled by sprinkling with
water.
8. FINISHING : Finishing work shall comply with requirement of section B.6.10 of Standard
Specification unless otherwise specified herein below :
Immediately on removal of forms, the R.C.C. work shall be examined by the Engineer before
any defects are made good.
a) The work that has sagged or contains honey combing to an extent detrimental to
structural safety or architectural concept shall be rejected.
i) Surface defects which require rectification when forms are removed usually consist of
bulges due to movement of forms, ridges at form joints, honeycombed areas, damage
resulting from the stripping of forms and bolt hole. Bulges and ridges shall be
removed by careful chipping or tooling and the surface is then rubbed with a grinding
stone. Honey combed and other areas shall be chipped out, the edges being cut as
straight as possible and perpendicular to the surface, or preferably slightly under cut
to provide a key at the edge, of the patch. Bolt holes shall be closed by cement
mortar to ensure thorough filling.
ii) Shallow patches shall be treated with a coat of thin grout composed of one part of
cement and one part of sand and then filled with mortar similar to that used in
concrete. The mortar is placed in layers not more than 10 mm thick and each layer
shall be given a scratch finish to secure bond with the succeeding layer. The last
layer shall be finished to match the surrounding concrete by floating, rubbing or
tooling on formed surfaces by pressing the form material against the patch while the
mortar is still plastic.
iii) Large and deep patches requires filling up with concrete held in place by forms. Such
patches shall be reinforced and carefully dowelled to the hardened concrete.
iv) The same amount of care to cure the material in the patches shall be taken for the
whole structure. Curing shall be started, as soon as possible after the patch is
finished to prevent early drying. Damp Hessian cloth may be used. But in some
locations it may be difficult to hold it in place, a membrane curing compound in these
cases will be most convenient.
9. CONSTRUCTIONS JOINTS : Construction joints shall be provided and treated following the
provisions of Specification and as directed by the Engineer-in-charge.
10. DURABILITY :- Minimum cement contents for different exposures and sulphate attack are
given in Tables 4 and 5 o I.S. 456, 2000 shall be followed for design mix.
11.2 DEFECTIVE CONCRETE : Any concrete which gives substandard results, or is severely
damaged due to cracking or shows excessive honey combing and exposure of reinforcement,
if exhibits any fault which in the opinion of the Engineer, seriously impairs its function, may be
declared as defective concrete. Such non acceptable concrete shall be removed from the site
and replaced by fresh concrete of the specified quality by the contractor at his own expenses.
Alternatively in case of acceptable concrete, the Contractor shall carry out whatever other
remedy the Engineer may reasonably suggest "Small rendering shall be done by the
Contractor without extra cost."
12 KEEPING RECORDS : The record of mix design, mixing, slum, testing of C.C. cubes etc.
shall be maintained in accordance with Section B-6.13 of the Standard Specification.
CHAPTER – IV
In consideration of the Governor of Maharashtra (here in after called “The Government”) having
agreed to exempt ______________________________ (here in after referred to as “The Contractor”)
from depositing with the Government in cash the sum of Rs. ______________ (Rupees___________
_____________________________________________ Only) being the amount of security deposit
payable by the Contractor to the Government under the terms and conditions of the agreement dated
the _______________ day of __________ and made between the Government of the on part and the
Contractor of the other part (here in after referred to as “the said agreement”) for _______ as security
for the observance and performance by the Contractor of the terms and conditions of the said
Agreement, on the contractor furnishing to the Government and guarantee in the prescribed form of a
Schedule Bank in India being in fact these presents in the like sum of Rs.________ (Rupees_______
______________________________________ Only). We __________________________________
BANK/LIMITED registered in India under __________________ Act and having one of our local Head
Office at _________________ do hereby:
2. Undertake to pay to the Government on demand and without demand and not withstanding
any dispute or disputes raised by the Contractor(s) in any suit or proceeding filed in any court
or tribunal relating there to the said sum of Rs._________ (Rupees__________________
___________________________Only) or such less may be demanded by the Government
from us our liability hereunder being absolute and unequivocal and agree that.
3. a) The guarantee herein contained shall remain in full force and effect during the subsistence
of the said agreement and the same will continue to be enforceable till all the dues of the
Government under or by virtue of the said agreement have been duly paid and its claims
satisfied or discharged and till the Government certifies that the terms and conditions of the
said agreement have been fully, properly carried out by the Contractor.
b) We shall not be discharged or released from the liability under this guarantee by reason of:
i) Any change in the constitution of the bank or the Contractor or ;
ii) Any arrangement entered in between the Government and the Contractor
with or without our consent ;
iii) Any forbearance or indulgence shown to he Contractor ;
iv) Any variation in the terms covenants or contained in the said agreement;
v) Any time given to the Contractor ;
vi) Any other conditions or circumstance under which, in law, a surety would be
discharged ;
c) Our liability here under shall be joint and several with that of the Contractor as if we
were principal debtors in respect of the said sum of Rs.____________(Rupees_____
________________________________________________ Only. ) and
d) We shall not revoke this guarantee during its currency except with the previous
consent in writing of the Government. IN WITNESS WHERE OF the common seal of
________________ has been herein to affixed this ________ day of _____20____.
The common seal of __________________________________ was pursuant to the
resolution of the Board of Directors of the company dated the _____________ day
of ____________________ herein affixed in the presence of who, in token thereof,
have here to set their respective hands in the presence of.
1. __________________________
2. __________________________
I/We hereby declare that I/We have made myself / ourselves thoroughly conversant with the
sub-soil conditions, the local conditions regarding all materials (such as stone, murum, sand etc.) and
labour of which I/We have based my/our rates for this work. The specifications, conditions, bore
results and lead of materials on this work have been carefully studied and understood by me/us
before submitting his tender. I/We undertake to use only the best materials approved the Executive
Engineer, Public Works Division No.1, Thane or his duly authorized assistant, before starting the
work and to abided by his decision.
I/We hereby undertake to pay the labourers engaged on the work as per Minimum Wages
Act, 1948 applicable to the zone concerned.
Signature of Contractor(s)
INTEGRITY PACT
Between
hereinafter referred to as
and
_________________________________________________________________________________
[Insert the name of the Sole Bidder / Lead Partner of ]oint Venture]
_________________________________________________________________________________
(Insert full Address)
and
_________________________________________________________________________________
[Insert the name of the Partner(s) of Joint Venture, as applicable]
_________________________________________________________________________________
(Insert full Address)
hereinafter referred to as
"The Bidder/Contractor"
Preamble
PUBLIC WORKS DEPARTMENT intends to award, under laid-down organizational procedures,
contract(s) for
(Signature) (Signature)
(For & On behalf of Public Works Department) (For & On behalf of Bidder/ Partner(s) of Joint Venture/ Contractor)
PUBLIC WORKS DEPARTMENT values full compliance with all relevant laws and regulations, and
the principles of economical use of resources, and of fairness and transparency in its relations with its
Bidders/ Contractors
In order to achieve these goals, PUBLIC WORKS DEPARTMENT and the above named Bidder/
Contractor enter into this agreement called 'Integrity Pact' which will form a part of the bid.
(1) PUBLIC WORKS DEPARTMENT commits itself to take all measures necessary to prevent
corruption and to observe the following principles:
b) PUBLIC WORKS DEPARTMENT will during the tender process treat all Bidder(s) with equity and
fairness. PUBLIC WORKS DEPARTMENT will in particular, before and during the tender process,
provide to all Bidder(s) the same information and will not provide to any Bidder(s) confidential/
additional information through which the Bidder(s) could obtain an advantage in relation to the tender
process or the contract execution.
c) PUBLIC WORKS DEPARTMENT will exclude from evaluation of Bids its such employee(s) who
has any personnel interest in the Companies/ Agencies participating in the Bidding/Tendering
process.
(2) If Principle Secretary PWD, Maharashtra Government obtains information on the conduct of
any employee of PUBLIC WORKS DEPARTMENT which is a criminal offence under the relevant Anti-
Corruption Laws of India, or if there be a substantive suspicion in this regard, he will inform its Chief
Vigilance Officer and in addition can initiate disciplinary actions under its Rules.
(1) The Bidder/Contractor commits himself to take all measures necessary to prevent corruption. He
commits himself to observe the following principles during his participation in the tender process and
during the contract execution:
(a) The Bidder/Contractor will not, directly or through any other person or firm, offer, promise or give
to PUBLIC WORKS DEPARTMENT, or to any of PUBLIC WORKS DEPARTMENT's employees
involved in the tender process or the execution of the contract or to any third person any material or
other benefit which he/she is not legally entitled to, in order to obtain in exchange an advantage
during the tender process or the execution of the contract.
(b) The Bidder/Contractor will not enter into any illegal agreement or understanding, whether formal
orinformal with other Bidders/Contractors. This applies in particular to prices, specifications,
certifications, subsidiary contracts, submission or non-submission of bids or actions to restrict
competitiveness or to introduce cartelization in the bidding process.
(c) The Bidder/Contractor will not commit any criminal offence under the relevant Anti-corruption Laws
of India; further, the Bidder/Contractor will not use for illegitimate purposes or for purposes of
restrictive competition or personal gain, or pass on to others, any information provided by PUBLIC
WORKS DEPARTMENT as part of the business relationship, regarding plans, technical proposals
and business details, including information contained or transmitted electronically.
(Signature) (Signature)
(For & On behalf of Public Works Department) (For & On behalf of Bidder/ Partner(s) of Joint Venture/ Contractor)
(d) The Bidder/Contractor of foreign origin shall disclose the name and address of the Agents/
representatives in India, if any, involved directly or indirectly in the B1ddmg. Similarly, the Bidder /
Contractor of Indian Nationality shall furnish the name and address of the foreign principals, if any,
involved directly or indirectly m the Bidding.
(e) The Bidder/Contractor will, when presenting his bid, disclose any and all payments he has made,
or committed to or intends to make to agents, brokers or any other intermediaries in connection with
the award of the contract and/ or with the execution of the contract.
(f) The Bidder/ Contractor will not misrepresent facts or furnish false/forged documents/informations in
order to influence the bidding process or the execution of the contract to the detriment of PUBLIC
WORKS DEPARTMENT.
(2) The Bidder/Contractor will not instigate third persons to commit offences outlined above or be an
accessory to such offences.
Section-III - Disqualification from tender process and exclusion from future contracts
(1) If the Bidder, before contract award, has committed a serious transgression through a violation of
Section II or in any other form such as to put his reliability or credibility as Bidder into question,
PUBLIC WORKS DEPARTMENT may disqualify the Bidder from the tender process or terminate the
contract, if already signed, for such reason.
(2) If the Bidder/Contractor has committed a serious transgression through a violation of Section II
such as to put his reliability or credibility into question, PUBLIC WORKS DEPARTMENT may after
following due procedures also exclude the Bidder/Contractor from future contract award processes.
The imposition and duration of the exclusion will be determined by the severity of the transgression.
The severity will be determined by the circumstances of the case, in particular the number of
transgressions, the position of the transgressors within the company hierarchy of the Bidder/
Contractor and the amount of the damage. The exclusion will be imposed for a minimum of 12
months and maximum of 3 years.
(3) If the Bidder/Contractor can prove that he has restored/recouped the damage caused by him and
has installed a suitable corruption prevention system, PUBLIC WORKS DEPARTMENT may revoke
the exclusion prematurely.
(1) If PUBLIC WORKS DEPARTMENT has disqualified the Bidder from the tender process prior to
the award under SectiOn Ill, PUBLIC WORKS DEPARTMENT may forfeit the Bid Guarantee under
the Bid.
(2) If PUBLIC WORKS DEPARTMENT has terminated the contract under Section-Ill, PUBLIC
WORKS DEPARTMENT may forfeit the Contract Performance Guarantee of this contract besides
resorting to other remedies under the contract.
(1) The Bidder shall declare in his Bid that no previous transgressions occurred in the last 3 years with
any other Public Sector Undertaking or Government Department that could justify his exclusion from
the tender process.
(2) If the Bidder makes incorrect statement on this subject, he can be disqualified from the tender
process or the contract, if already awarded, can be terminated for such reason.
(Signature) (Signature)
(For & On behalf of Public Works Department) (For & On behalf of Bidder/ Partner(s) of Joint Venture/ Contractor)
(2) PUBLIC WORKS DEPARTMENT will disqualify from the tender process any bidder who does not
sign this Pact or violate its provisions.
(1) PUBLIC WORKS DEPARTMENT has appointed a panel of Independent External Monitors (IEMs)
for this Pact with the approval of Central Vigilance CommissiOn (CVC), Government of India, out of
which one of the IEMs has been indicated in the NIT/IFB.
(2) The IEM is to review independently and objectively, whether and to what extent the parties comply
with the obligations under this agreement. He has right of access to all project documentation. The
IEM may examine any complaint received by him and submit a report to Principle Secretary PWD,
Maharashtra Government, PUBLIC WORKS DEPARTMENT, at the earliest. He may also submit a
report directly to the CVO and the CVC, in case of suspicion of serious irregularities attracting the
provisions of the PC Act. However, for ensuring the desired transparency and objectivity in dealing
with the complaints arising out of any tendering process, the matter shall be referred to the full panel
of IEMs, who would examme the records, conduct the investigations and submit report to Principle
Secretary PWD, Maharashtra Government, PUBLIC WORKS DEPARTMENT, giving Joint findings
(3) The IEM is not subject to instructwns by the representatives of the parties and performs his
functions neutrally and independently. He reports to the Principle Secretary PWD, Maharashtra
Government, PUBLIC WORKS DEPARTMENT.
(4) The Bidder(s)/Contractor(s) accepts that the IEM has the right to access without restriction to all
documentation of PUBLIC WORKS DEPARTMENT related to this contract including that provided by
the Contractor/Bidder. The Bidder/Contractor will also grant the IEM, upon his request and
demonstration of a valid interest, unrestricted and unconditional access to his documentation. The
same is applicable to Subcontractors. The IEM IS under contractual obligation to treat the information
and documents of the Bidder(s)/Contractor(s)/Subcontractor(s) with confidentiality.
(5) PUBLIC WORKS DEPARTMENT will provide to the IEM information as sought by him which could
have an impact on the contractual relations between PUBLIC WORKS DEPARTMENT and the
Bidder/Contractor related to this contract.
(6) As soon as the IEM notices, or believes to notice, a violation of this agreement, he will so inform
the Principle Secretary PWD, Maharashtra Government, PUBLIC WORKS DEPARTMENT and
request the Principle Secretary PWD, Maharashtra Government, PUBLIC WORKS DEPARTMENT to
discontinue or take corrective action, or to take other relevant action. The IEM can in this regard
submit non-binding recommendations. Beyond this, the IEM has no right to demand from the parties
that they act in a specific manner, refrain from action or tolerate action. However, the IEM shall give
an opportunity to PUBLIC WORKS DEPARTMENT and the Bidder/Contractor, as deemed fit, to
present its case before making its recommendations to PUBLIC WORKS DEPARTMENT.
(7) The IEM will submit a written report to the Principle Secretary PWD, Maharashtra Government,
PUBLIC WORKS DEPARTMENT within 8 to 10 weeks from the date of reference or intimation to him
by PUBLIC WORKS DEPARTMENT and, should the occasion arise, submit proposals for correcting
problematic situations.
(Signature) (Signature)
(For & On behalf of Public Works Department) (For & On behalf of Bidder/ Partner(s) of Joint Venture/ Contractor)
(8) If the IEM has reported to the Principle Secretary PWD, Maharashtra Government, PUBLIC WORKS
DEPARTMENT, a substantiated suspicion of an offence under relevant Anti-Corruption Laws of India, and
the Principle. Secretary PWD, Maharashtra Government, PUBLIC WORKS DEPARTMENT has not, within
the reasonable time taken visible action to proceed against such offence or reported it to the CVO, the
Monitor may also transmit this Information directly to the CVC, Government of India.
(9) The word 'IEM' would include both singular and plural.
(*) This Section shall be applicable for only those packages wherein the IEMs have been identified in
Section-I: lnvitation for Bids and/or Clause ITB 9.3 in Section-III: Bid Data Sheets of Conditions of Contract,
Volume-! of the Bidding Documents.
This Pact begins when both parties have legally signed it. It expires for the Contractor after the closure of
the contract and for all other Bidder's six month after the contract has been awarded.
(1) This agreement is subject to Indian Law Place of performance and jurisdiction is the establishment of
PUBLIC WORKS DEPARTMENT. The Arbitration clause provided in the main tender document / contract
shall not be applicable for any issue/ dispute arising under Integrity Pact.
(2) Changes and supplements as well as termination notices need to be made in writing.
(3) If the Contractor is a partnership firm or a consortium or Joint Venture, this agreement must be signed
by all partners, consortium members and joint Venture partners.
(4) Nothing in this agreement shall affect the rights of the parties available under the General Conditions of
Contract (GCC) and Special Conditions of Contract (SCC)
(5) Views expressed or suggestions/ submissions made by the parties and the recommendations of the
CVO/IEM• in respect of the violation of this agreement, shall not be relied on or introduced as evidence in
the arbitral or judicial proceedings (arising out of the arbitral proceedings) by the parties in connection with
the disputes/ differences arising out of the subject contract.
# CVO slzall be applicable for packages wherein IEM are not identified in Section IFB/BDS of Condition of
Contract, Volume-I. IEM shall be applicable for packages wherein IEM are identified in Section IFB/BDS of
Condition of Contract, Volume-!.
(6) Should one or several provisions of this agreement turn out to be invalid, the remainder of this
agreement remains valid. In this case, the parties will strive to come to an agreement to their original
intentions.
(Signature) (Signature)
(For & On behalf of Public Works Department) (For & On behalf of Bidder/ Partner(s) of Joint Venture/
Contractor)
Name: Name:
Designation: Designation:
Witness 1: Witness 1:
(Name & Address) (Name & Address)
________________________________________ ________________________________________
Witness 1: Witness 1:
(Name & Address) (Name & Address)
________________________________________ ________________________________________
(Signature) (Signature)
(For & On behalf of Public Works Department) (For & On behalf of Bidder/ Partner(s) of Joint Venture/ Contractor)
DRAWINGS
CONTRACT DRAWINGS:
The contract drawings provided for tendering purpose with the tender documents shall be used as
reference only. Contractor should visualise the nature of type of work contemplated and to ensure
that the rates and prices quoted by him in the bill of quantities take due consideration of the
complexities of work involved during actual execution / construction as experienced Contractors in the
field.
The tendered rates / prices for the work shall be deemed to include the cost of preparation, supply
and delivery of all necessary drawings, prints, tracings and negatives which the Contractor is required
to provide in accordance with the contract.
DOCUMENTATION:
If so ordered by the Engineer-in-charge the Contractor will prepare drawings of the work at
constructed and will supply original and three copies to the Engineer who will verify and certify these
drawings. Final as constructed drawings shall then be prepared by the Contractor and supplied in
triplicate along with a micro film of the same to the Engineer for record and reference purposes at the
Contractor’s cost.
SCHEDULE ‘B’
NOTES:-
1) All the quantities shown in the schedule ‘B’ are likely to vary at the time of actual execution,
as such claims on this account shall be entertained.
2) Rate of all items include all leads and lifts, labour, material involved for completed item and
site clearance
3) All rates are inclusive of all taxes, octroi chargers and royalty charges.
4) Work shall be carried out as per the instructions / orders and to the enter satisfaction of
Engineer-in-charge.
5) Government Circulars issued previously and will be issued hereafter are also binding on the
contractor.
6) The detailed specifications are as One Standard Specification Book Volume I Edition 1979
and Volume II Edition 1981 Published by the Govenement of Maharashtra in Public works
Department and Specification for road and bridge work published by Ministry of road
th th
Transport and Highway 2001 Edition 4 and 5 revision.
7) Government Circulars issued previously and will be issued hereafter are biding on the
Contractor.
Name of Work :- Supplying and Installation of Furniture and Required Amenities for New Thane court Building at Thane.
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
1 57.00 Nos Office Table :- Providing and supplying for Office 26175.00 Rupees Nos 1491975.00 -- -- As directed by
Table of size 1500 W X 600 D X 750 H in mm. twenty-six Engineer in
Using Commercial plywood with HGL and SF thousand one charge.
laminate. Table top 18mm thick. HGL laminate, hundred
edge cover by 1.3 x 22mm PVC edge binding with seventy-five
PUR glue. Gable end 18mm thick. SF laminate, and paise nil
edge cover by 2 x 22mm PVC edge binding with only
PUR glue. modesty panel having both side SF
laminate, edge cover by 0.8 x 22mm PVC edge
binding with PUR glue. Provided wooden keyboard
and 2 drawer fix pedestal with telescopic slide,
locks and handles. Fitted necessary hardware etc.
(As Per RA. 01) (Stilt floor to Eight floor)
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
2 22.00 Nos Judge Table (Court Hall):- Providing and supplying 65329.00 Rupees sixty- Nos 1437238.00 -- -- As directed by
for Judge Table(Court Hall) of size 2400 W X 900 five thousand Engineer in
D X 825 H in mm. Using Commercial plywood three hundred charge.
with HGL and SF laminate. Table top 36mm thick. twenty-nine
HGL laminate, edge cover by 1.3 x 45mm PVC and paise nil
edge binding with PUR glue. Gable end 36mm only
thick. SF laminate, edge cover by 2 x 45mm PVC
edge binding with PUR glue. modesty panel 18mm
thk. having both side SF laminate, edge cover by
0.8 x 22mm PVC edge binding with PUR glue.
Provided Foot rest, and 2 drawer fix pedestal with
telescopic slide, locks and handles. Provided 6mm
thk. clear glass on table top. Fitted necessary
hardware etc. (As Per RA. 02) (Third Floor to
Eight Floor)
3 23.00 Nos Advocate Table:- Providing and supplying for 52444.00 Rupees fifty- Nos 1206212.00 -- -- As directed by
Advocate Table of size 3400 W X 900 D X 750 H two thousand Engineer in
in mm. Using Commercial plywood with HGL and four hundred charge.
SF laminate. Table top 36mm thick. HGL laminate, forty-four and
edge cover by 1.3 x 45mm PVC edge binding with paise nil only
PUR glue. Gable end 36mm thick. SF laminate,
edge cover by 2 x 45mm PVC edge binding with
PUR glue. modesty panel 18mm thk. having both
side SF laminate, edge cover by 0.8 x 22mm PVC
edge binding with PUR glue. Fitted necessary
hardware etc. (As Per RA. 03) ( First floor,
Third floor to Eight floor)
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
4 66.00 Nos Writing Desk :- Providing and Supplying Writing 4814.00 Rupees four Nos 317724.00 -- -- As directed by
Desk of size 550 mm x 450 mm x 450 mm. Using thousand Engineer in
Commercial plywood with HGL and SF laminate. eight hundred charge.
Table top 18mm thick. HGL laminate, edge cover fourteen and
by 1.3 x 22mm PVC edge binding with PUR glue. paise nil only
Gable end 18mm thick. SF laminate, edge cover by
2 x 22mm PVC edge binding with PUR glue.
modesty panel having both side SF laminate, edge
cover by 0.8 x 22mm PVC edge binding with PUR
glue. Fitted necessary hardware etc. (As Per RA.
04) (Third floor to Eight floor)
5 22.00 Nos Judge Table (Chamber):- Providing and supplying 54595.00 Rupees fifty- Nos 1201090.00 -- -- As directed by
for Judge Table (Anti-Chamber) of size 2200 W X four thousand Engineer in
900 D X 825 H in mm. Using Commercial plywood five hundred charge.
with SF laminate. Table top having 36mm thick. ninety-five
With top surface in PU Polyurethane paint , and paise nil
Hammer finish & at bottom 18mm thick. strip only
pasting, edge cover by 0.8 x 22mm PVC edge
binding with PUR glue. Gable end 36 mm thick.
pasting 18mm panel with SF laminate, edge cover
by 2 x 45mm PVC edge binding. 18 mm thick.
modesty panel having both side SF laminate, edge
cover by 0.8 x 22mm PVC edge binding with PUR
glue. Provided wooden keyboard and 2 drawer
pedestal with telescopic slide,locks and handles.
Provided 6mm thk. clear glass on table top. Fitted
necessary hardware etc. (As Per RA. 05) (Third
floor to eight floor)
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
6 22.00 Nos Side Return :- Providing and supplying for Side 28304.00 Rupees Nos 622688.00 -- -- As directed by
Return of size 1200 W X 450 D X 825 H in mm. twenty-eight Engineer in
Using Commercial plywood with HGL and SF thousand charge.
laminate. 2 openable shutter & 2 drawer facia three hundred
18mm thick. HGL laminate. drawer and shutter four and paise
having locks, handles and hing, edge cover by 1.3 x nil only
22 mm PVC edge binding with PUR glue. And all
outer structure in SF laminate excluding shutter &
drawer facia. edge cover by 0.8 x 22mm PVC edge
binding with PUR glue. Fitted necessary hardware
etc. (As Per RA. 06) (Third floor to Eight floor)
7 25.00 Nos Steno Table :- Providing and supplying for Steno 29945.00 Rupees Nos 748625.00 -- -- As directed by
Table of size 1500 W X 750 D X 750 H in mm. twenty-nine Engineer in
Using Commercial plywood with HGL and SF thousand nine charge.
laminate. Table top 36mm thick. HGL laminate, hundred
edge cover by 1.3 x 45mm PVC edge binding with forty-five and
PUR glue. Gable end 36mm thick. SF laminate, paise nil only
edge cover by 2 x 45mm PVC edge binding with
PUR glue. modesty panel 18mm thk. having both
side SF laminate, edge cover by 0.8 x 22mm PVC
edge binding with PUR glue. Provided 2 drawer fix
pedestal with telescopic slide, locks and handles.
Providedd 6mm thk. clear glass on table top. Fitted
necessary hardware etc. (As Per RA. 07) (Third
floor to Eight floor)
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
8 Clerk Table :- Providing and supplying for Office -- -- As directed by
Table of size 1500 W X 750 D X 750 H in mm. Engineer in
Using Commercial plywood with HGL and SF charge.
laminate. Table top 18mm thick. HGL laminate,
edge cover by 1.3 x 22mm PVC edge binding with
PUR glue. Gable end 18mm thick. SF laminate,
edge cover by 2 x 22mm PVC edge binding with
PUR glue. modesty panel having both side SF
laminate, edge cover by 0.8 x 22mm PVC edge
binding with PUR glue. Provided wooden keyboard
and 2 drawer fix pedestal with telescopic slide,
locks and handles. Fitted necessary hardware etc.
(As Per RA. 08) (First floor, Fourth floor to Eight
floor)
8a 11.00 Nos First Floor 30174.76 Rupees thirty Nos 331922.40 -- -- As directed by
thousand one Engineer in
hundred charge.
seventy-four
and paise
seventy-six
only
8b 3.00 Nos Fourth Floor 31071.04 Rupees thirty- Nos 93213.10 -- -- As directed by
one thousand Engineer in
seventy-one charge.
and paise four
only
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
8c 2 Nos Fifth Floor 31220.42 Rupees thirty- Nos 62440.80 As directed by
one thousand Engineer in
two hundred charge.
twenty and
paise forty-
two only
8d 6 Nos Sixth Floor 31369.80 Rupees thirty- Nos 188218.80 -- -- As directed by
one thousand Engineer in
three hundred charge.
sixty-nine and
paise eighty
only
8e 3.00 Nos Seventhth Floor 31519.18 Rupees thirty- Nos 94557.50 -- -- As directed by
one thousand Engineer in
five hundred charge.
nineteen and
paise eighteen
only
8f 13.00 Nos Eight Floor 31668.56 Rupees thirty- Nos 411691.30 -- -- As directed by
one thousand Engineer in
six hundred charge.
sixty-eight
and paise
fifty-six only
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
9 222.00 Nos Side Return :- Providing and supplying for Side 20458.00 Rupees Nos 4541676.00 -- -- As directed by
Return of size 900 W X 450 D X 750 H in mm. twenty Engineer in
Using Commercial plywood with HGL and SF thousand four charge.
laminate.Top panel, 2 openable shutter & 2 drawer hundred fifty-
facia 18mm thick. HGL laminate. drawer and eight and
shutter having locks, handles and hing, edge cover paise nil only
by 1.3 x 22 mm PVC edge binding with PUR glue.
And all outer structure in SF laminate excluding
shutter & drawer facia. edge cover by 0.8 x 22mm
PVC edge binding with PUR glue. Fitted necessary
hardware etc. (As Per RA. 09) (Stilt floor to eight
floor)
10 162.00 Nos Computer Table :- Providing and supplying for 21408.00 Rupees Nos 3468096.00 -- -- As directed by
Computer Table of size 1200 W X 600 D X 750 H twenty-one Engineer in
in mm. Using Commercial plywood with HGL and thousand four charge.
SF laminate. Table top 18mm thick. HGL laminate, hundred eight
edge cover by 1.3 x 22mm PVC edge binding with and paise nil
PUR glue. Gable end 18mm thick. SF laminate, only
edge cover by 2 x 22mm PVC edge binding with
PUR glue. modesty panel having both side SF
laminate, edge cover by 0.8 x 22mm PVC edge
binding with PUR glue. Provided wooden keyboard
and 2 drawer fix pedestal with telescopic slide,
locks and handles. Fitted necessary hardware etc.
(As Per RA. 10) (Stilt floor to eight floor)
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
11 343.00 Nos Full Height Storage :- Providing and supplying for 33063.00 Rupees thirty- Nos 11340609.00 -- -- As directed by
Full Height Storage of size 800 W X 450 D X 2100 three Engineer in
H in mm. Using Commercial plywood with HGL thousand charge.
and SF laminate. 4 openable shutter 18mm thick. sixty-three
HGL laminate. shutter having locks, handles and and paise nil
hing, edge cover by 1.3 x 22 mm PVC edge binding only
with PUR glue. And all outer structure in SF
laminate excluding shutter. edge cover by 0.8 x
22mm PVC edge binding with PUR glue. Fitted
necessary hardware etc. (As Per RA. 11) (Stilt floor
to eight floor)
12 85.00 Nos Full Height Book Rack :- Providing and supplying 36281.00 Rupees thirty- Nos 3083885.00 -- -- As directed by
for Full Height Book Rack of size 900 W X 400 D six thousand Engineer in
X 2100 H in mm. Using Commercial plywood with two hundred charge.
HGL and SF laminate. 4 openable glass shutter eighty-one
18mm thick. HGL laminate with handles and hinge, and paise nil
edge cover by 1.3 x 22mm PVC edge binding with only
PUR glue. And all outer structure in SF laminate
excluding glass shutter. edge cover by 0.8 x 22mm
PVC edge binding with PUR glue. Fitted necessary
hardware etc. (As Per RA. 12) (Stilt floor, Third
flloor to Eight floor)
13 26.00 Nos Center Table :- Providing and supplying for Center 13525.00 Rupees Nos 351650.00 -- -- As directed by
Table of size 900 W X 600 D X 450 H in mm. thirteen Engineer in
Using Commercial plywood with HGL and SF thousand five charge.
laminate. Top panel HGL laminate, edge cover by hundred
1.3 x 22mm PVC edge binding with PUR glue. And twenty-five
all outer structure in SF laminate excluding Top and paise nil
panel. edge cover by 0.8 x 22mm PVC edge binding only
with PUR glue. Fitted necessary hardware etc. (As
Per RA. 13) (Stilt floor, Third flloor to Eight floor)
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
14 24.00 Nos 2 Door Wardrobe (Judges Chember) :- Providing 41222.00 Rupees forty- Nos 989328.00 -- -- As directed by
and supplying for 2 Door Wardrobe of size 800 W one thousand Engineer in
X 580 D X 2100 H in mm. Using Commercial two hundred charge.
plywood with HGL and SF laminate. 2 openable twenty-two
shutter 18mm thick. HGL laminate. shutter having and paise nil
locks, handles and hing, edge cover by 1.3 x 22 mm only
PVC edge binding with PUR glue. And all outer
structure in SF laminate excluding shutter. edge
cover by 0.8 x 22mm PVC edge binding with PUR
glue. Provided Single drawer & Hanging
arrengement. Fitted necessary hardware etc. (As
Per RA. 14) (Third flloor to Eight floor)
15 22.00 Nos Dressing Table (Judges Chember) :- Providing and 11972.00 Rupees Nos 263384.00 -- -- As directed by
Supplying Dressing Table of size 600 W x 350 D x eleven Engineer in
1450 H in mm. Using Commercial plywood with SF thousand nine charge.
laminate. all outer structure in SF laminate. edge hundred
cover by 0.8 x 22mm PVC edge binding with PUR seventy-two
glue. Single Drawer & Hanging Mirror With fitted and paise nil
necessary hardware etc. (As Per RA. 15) (Third only
flloor to Eight floor)
16 22.00 Nos DAIS (Court Hall):- Providing and supplying for 113419.00 Rupees one Nos 2495218.00 As directed by
DAIS of size 8200 W X 2400 D X 450H in mm. lakhs thirteen Engineer in
Using Commercial plywood with SF laminate. MS thousand four charge.
Welded frame having pipe size 50 x 25mm 1.2mm hundred
thk. with powder coating. Covering with 18mm thk. nineteen and
ply with sf laminate, edge cover by 0.8 x 22mm paise nil only
PVC edge binding with PUR glue. Fitted necessary
hardware etc. (As Per RA. 16) (Third flloor to
Eight floor)
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
17 1 Nos DAIS (Conferance Hall):- Providing and supplying 194806.00 Rupees one Nos 194806.00 -- -- As directed by
for DAIS of size 13200 W X 2800 D X 450H in lakhs ninety- Engineer in
mm. Using Commercial plywood with SF laminate. four thousand charge.
MS Welded frame having pipe size 50 x 25mm eight hundred
1.2mm thk. with powder coating. Covering with six and paise
18mm thk. ply with sf laminate, edge cover by 0.8 x nil only
22mm PVC edge binding with PUR glue. Fitted
necessary hardware etc. (As Per RA. 17) (Eight
floor)
18 2.00 Nos Conference Table :- Providing and supplying for 69186.00 Rupees sixty- Nos 138372.00 -- -- As directed by
Conference Table of size 2400 W X 1200 D X 750 nine thousand Engineer in
H in mm. Using Commercial plywood with HGL one hundred charge.
and SF laminate. Table top 18mm thick. HGL eighty-six and
laminate, edge cover by 1.3 x 22mm PVC edge paise nil only
binding with PUR glue. Gable end 18mm thick. SF
laminate, edge cover by 2 x 22mm PVC edge
binding with PUR glue. Fitted necessary hardware
etc. (As Per RA. 18) (Eight floor)
19 125.00 Nos Low Height Storage :- Providing and supplying for 16572.00 Rupees Nos 2071500.00 -- -- As directed by
Low Height Storage of size 900 W X 400 D X 750 sixteen Engineer in
H in mm. Using Commercial plywood with HGL thousand five charge.
and SF laminate. Top panel & 2 openable shutter hundred
18mm thick. HGL laminate. shutter having locks, seventy-two
handles and hing, edge cover by 1.3 x 22 mm PVC and paise nil
edge binding with PUR glue. And all outer structure only
in SF laminate excluding shutter & top panel. edge
cover by 0.8 x 22mm PVC edge binding with PUR
glue. Fitted necessary hardware etc. (As Per RA.
19) (First floor to eight floor)
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
20 59.00 Nos Bench :- Providing and supplying for Bench of size 10410.00 Rupees ten Nos 614190.00 -- -- As directed by
1800 W X 400 D X 450 H in mm. Using thousand four Engineer in
Commercial plywood with SF laminate. Bench all hundred ten charge.
panels are made in 18 mm ply with Lamination with and paise nil
selected color. All tuching edge are cover with 22 x only
2 mm pvc. Edge banding. fitted with necessary
hardware. (As Per RA. 20) (Stilt floor, first floor
and Third floor to eight floor)
21 22.00 Nos TV Panel :- Providing and supplying for TV Panel 49681.00 Rupees forty- Nos 1092982.00 -- -- As directed by
of size 2400 W X 400 D X 2100 H in mm. Using nine thousand Engineer in
Commercial plywood with SF laminate. TV Panel six hundred charge.
all panels are made in 18 mm ply with Lamination eighty-one
with selected color. All tuching edge are cover with and paise nil
22 x 2 mm pvc. Edge banding. fitted with necessary only
hardware. (As Per RA. 21) (Third floor to eight
floor)
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
22 2.00 Nos DGP / Registar Table :- Providing and supplying 60106.00 Rupees sixty Nos 120212.00 -- -- As directed by
for DGP Table of size 1800 W X 800 D X 750 H in thousand one Engineer in
mm. Using Commercial plywood with SF laminate. hundred six charge.
Table top having 36mm thick. With top surface in and paise nil
PU Polyurethane paint , Hammer finish & at only
bottom 18mm thick. strip pasting, edge cover by 0.8
x 22mm PVC edge binding with PUR glue. Gable
end 36 mm thick. pasting 18mm panel with SF
laminate, edge cover by 2 x 45mm PVC edge
binding. 18 mm thick. modesty panel having both
side SF laminate, edge cover by 0.8 x 22mm PVC
edge binding with PUR glue. Provided wooden
keyboard and 2 drawer pedestal with telescopic
slide,locks and handles. Provided 6mm thk. clear
glass on table top. Fitted necessary hardware etc.
(As Per RA. 22) (Sixth floor and eight floor)
23 4.00 Nos Library Table-1 (With Middle Partition) :- 32240.00 Rupees thirty- Nos 128960.00 -- -- As directed by
Providing and supplying for Library Table-1 (With two thousand Engineer in
Middle Partition) of size 1600 W X 1200 D X 750 / two hundred charge.
1200 H in mm. Using Commercial plywood with forty and
HGL and SF laminate. Table Top panel Made in paise nil only
HG. Finish another All panels are made in sf. finish
Laminated. in middle of table partition. all edge are
cover with 22 x 1.3 mm pvc. edge Banding with
PUR glue. Fitted with necessary Hardware. (As
Per RA. 23) (Sixth Floor)
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
24 8.00 Nos Library Table-2 :- Providing and supplying for 20526.00 Rupees Nos 164208.00 -- -- As directed by
Library Table-2 of size 1600 W X 600 D X 750 / twenty Engineer in
1200 H in mm. Using Commercial plywood with thousand five charge.
HGL and SF laminate. Table Top panel Made in hundred
HG. Finish another All panels are made in sf. finish twenty-six
Laminated. all edge are cover with 22 x 1.3 mm and paise nil
pvc. edge Banding with PUR glue. Fitted with only
necessary Hardware. (As Per RA. 24)
(Second Floor)
25 1.00 Nos Podium :- Providing and Supplying Podium of size 15788.00 Rupees Nos 15788.00 -- -- As directed by
600 W x 500 D x 1200 H in mm. Using fifteen Engineer in
Commercial plywood with HGL and SF laminate. thousand charge.
all outer structure in SF laminate. edge cover by 0.8 seven
x 22mm PVC edge binding with PUR glue. hundred
Provided 2 shelf. Fitted necessary hardware etc. eighty-eight
(As Per RA. 25) (Eight Floor) and paise nil
only
26 8.00 Nos Round Table :- Providing and supplying for Round 12828.00 Rupees Nos 102624.00 -- -- As directed by
Table of size Dia 1200 W X 750 H in mm. Using twelve Engineer in
Commercial plywood with HGL and SF laminate. thousand charge.
Table top 18mm thick. HGL laminate, edge cover eight hundred
by 1.3 x 22mm PVC edge binding with PUR glue. twenty-eight
Gable end 18mm thick. SF laminate, edge cover by and paise nil
2 x 22mm PVC edge binding with PUR glue. Fitted only
necessary hardware etc. (As Per RA. 26)
(Third & Eight Floor)
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
27 4 Nos Single Bed :- Providing and supplying for Single 27271.00 Rupees Nos 109084.00 As directed by
Bed of Size 2025 LX 1000DX 650H The bed unit is twenty-seven Engineer in
made up of 18mm thick Alternate Ply with both thousand two charge.
side decorative laminate. All exposed edges are hundred
sealed with 2mm thick PVC edge Banding. All seventy-one
exposed edges are sealed with 2mm thick PVC edge and paise nil
Banding, Fitted necessary hardware etc. (As Per only
RA. 27) (Stilt Floor)
28 132.00 Nos Metal Rack @ 1200 L x 450D x 2400 HT 31870.00 Rupees thirty- Nos 4206840.00 -- -- As directed by
Providing & Fixing of Metal Rack @ 1200 one thousand Engineer in
L x 450D x 2400 HT:- To be made out of complete eight hundred charge.
body in 25 x 25 Square Pipe & 1.2mm thick seventy and
CRCA in Powder coating finish as per drawing. as paise nil only
per drawing. (As Per RA. 29) (Stilt
to First Floor & Third to Eight Floor)
29 1.00 Nos Auditorium Table :- Providing and supplying for 50020.00 Rupees fifty Nos 50020.00 -- -- As directed by
Auditorium Table of size 2400 W X 800 D x 750 H thousand Engineer in
in mm. Using Commercial plywood with HGL and twenty and charge.
SF laminate. Table top 18mm thick. HGL laminate, paise nil only
edge cover by 1.3 x 22mm PVC edge binding with
PUR glue. Gable end 18mm thick. SF laminate,
edge cover by 2 x 22mm PVC edge binding with
PUR glue. Fitted necessary hardware etc. (As Per
RA. 30) (Eight Floor)
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
30 40.00 Nos FULL HEIGHT PARTITION :- Providing and 32501.00 Rupees thirty- Nos 1300040.00 -- -- As directed by
supplying of Full Height Partition size - 1200 x 80 x two thousand Engineer in
2400 mm . Inner Side frame is made in Teak wood five hundred charge.
than cover with 16 mm ply board. After than one and paise
pesting with glue 1 mm Laminate with selected nil only
color . Fitted with necessary Hardware. as per given
Drawing . (As Per RA. 31) (First Floor to Eight
Floor)
31 20.00 Nos FULL HEIGHT PARTITION :- Providing and 40636.00 Rupees forty Nos 812720.00 -- -- As directed by
supplying of Full Height Partition size - 1800 x 80 x thousand six Engineer in
2400 mm . Inner Side frame is made in Teak wood hundred charge.
than cover with 16 mm ply board. After than thirty-six and
pesting with glue 1 mm Laminate with selected paise nil only
color . Fitted with necessary Hardware. as per given
Drawing . (As Per RA. 32) (First Floor to Eight
Floor)
32 FULL HEIGHT PARTITION :- Providing and -- --
supplying of Full Height Partition size - 1800 x 80 x
2400 mm . Inner Side frame is made in Teak wood
than cover with 16 mm ply board. After than
pesting with glue 1 mm Laminate with selected
color . Fitted with necessary Hardware. as per given
Drawing .
32a 52.18 Sqm Stilt floor 9406.50 Rupees nine Sqm 490793.50 -- -- As directed by
thousand four Engineer in
hundred six charge.
and paise fifty
only
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
32b 28.80 Sqm First Floor 9500.57 Rupees nine Sqm 273616.30 -- -- As directed by
thousand five Engineer in
hundred and charge.
paise fifty-
seven only
32c 38.78 Sqm Second Floor 9594.63 Rupees nine Sqm 372118.10 -- -- As directed by
thousand five Engineer in
hundred charge.
ninety-four
and paise
sixty-three
only
32d 92.36 Sqm Third Floor 9688.70 Rupees nine Sqm 894847.90 -- -- As directed by
thousand six Engineer in
hundred charge.
eighty-eight
and paise
seventy only
32e 75.08 Sqm Fourth Floor 9782.76 Rupees nine Sqm 734489.60 -- -- As directed by
thousand Engineer in
seven charge.
hundred
eighty-two
and paise
seventy-six
only
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
32f 4.32 Sqm Fifth Floor 9829.79 Rupees nine Sqm 42464.70 As directed by
thousand Engineer in
eight hundred charge.
twenty-nine
and paise
seventy-nine
only
32g 87.62 Sqm Sixth Floor 9876.83 Rupees nine Sqm 865387.70 -- -- As directed by
thousand Engineer in
eight hundred charge.
seventy-six
and paise
eighty-three
only
32h 91.35 Sqm Seventhth Floor 9923.86 Rupees nine Sqm 906564.20 -- -- As directed by
thousand nine Engineer in
hundred charge.
twenty-three
and paise
eighty-six
only
32i 164.41 Sqm Eight Floor 9970.89 Rupees nine Sqm 1639334.00 -- -- As directed by
thousand nine Engineer in
hundred charge.
seventy and
paise eighty-
nine only
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
33 Providing and fixing solid core flush door shutter in
single leaf 32 mm thick decorative type of exterior
grade as per detailed drawings approved face
veneers 3 mm thick on both faces or as directed, all
necessary beads, mouldings and lipping, wrought
iron hold fasts, chromium plated fixtures and
fastenings, with brass mortise lock, chromium
plated handles on both sides, and finishing with
French Polish etc. complete
33a 5.67 Sqm Stilt floor 3200.62 Rupees three Sqm 18147.50 BD-T-34 499 Door shutter
thousand two and fixtures
hundred and and fastenings
paise sixty- shall be got
two only approved by
Engineer in-
charge.
33b 3.78 Sqm First Floor 3232.63 Rupees three Sqm 12219.30 BD-T-34 499 Door shutter
thousand two and fixtures
hundred and fastenings
thirty-two and shall be got
paise sixty- approved by
three only Engineer in-
charge.
33c 5.67 Sqm Second Floor 3264.63 Rupees three Sqm 18510.50 BD-T-34 499 Door shutter
thousand two and fixtures
hundred and fastenings
sixty-four and shall be got
paise sixty- approved by
three only Engineer in-
charge.
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
33d 3.78 Sqm Third Floor 3296.64 Rupees three Sqm 12461.30 BD-T-34 499 Door shutter
thousand two and fixtures
hundred and fastenings
ninety-six and shall be got
paise sixty- approved by
four only Engineer in-
charge.
33e 3.78 Sqm Fourth Floor 3328.65 Rupees three Sqm 12582.30 BD-T-34 499 Door shutter
thousand and fixtures
three hundred and fastenings
twenty-eight shall be got
and paise approved by
sixty-five Engineer in-
only charge.
33f 3.78 Sqm Fifth Floor 3344.65 Rupees three Sqm 12642.80 BD-T-34 499 Door shutter
thousand and fixtures
three hundred and fastenings
forty-four and shall be got
paise sixty- approved by
five only Engineer in-
charge.
33g 5.67 Sqm Sixth Floor 3360.65 Rupees three Sqm 19054.90 BD-T-34 499 Door shutter
thousand and fixtures
three hundred and fastenings
sixty and shall be got
paise sixty- approved by
five only Engineer in-
charge.
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
33h 1.89 Sqm Seventhth Floor 3376.65 Rupees three Sqm 6381.90 BD-T-34 499 Door shutter
thousand and fixtures
three hundred and fastenings
seventy-six shall be got
and paise approved by
sixty-five Engineer in-
only charge.
33i 7.20 Sqm Eight Floor 3392.66 Rupees three Sqm 24427.10 BD-T-34 499 Door shutter
thousand and fixtures
three hundred and fastenings
ninety-two shall be got
and paise approved by
sixty-six only Engineer in-
charge.
34 21.00 Sqm Door Closure: (For 2 Hr fire Rated EN-3 Door 4062.37 Rupees four Sqm 85309.70 -- -- As directed by
Closure) Supplying, fitting & fixing Surface thousand Engineer in
mounted overhead Door Closer for 2 hour fire rated sixty-two and charge.
doors of different size(e.g size-EN-3 for leaf width paise thirty-
upto 900mm ) CE certified, marked & conforming seven only
to EN-1154 of approved quality (Internationally
reputed brand like Dorma, Geze, Hafele, Assabloy
& Magnumetc.) fitted and fixed Complete as per
direction & satisfaction of Engineer -in Charge
including all taxes & incidental charges.SSR Rate
2022-23
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
35 305.85 Sqm Providing & Fixing of Roller Blinds AMI Make or 2237.00 Rupees two Sqm 684187.70 -- -- As directed by
Approved Make & shade of 38 mm round thousand two Engineer in
Alluminium Channel with Blackout fabric & tilting hundred charge.
with chain ball system with all nessary fixtures & thirty-seven
fittings etc. (AS per SSR 2022-23 Sr no. 1877, Item and paise nil
No. 51.19 Page no. 452) (Stilt only
Floor to Eight Floor)
36 368.63 Sqm Providing and Fixing Vertical Blinds of approved 1065.49 Rupees one Sqm 392771.60 -- -- As directed by
Make and shade of 100mm regular fabric with thousand Engineer in
powder coated aluminium channel with telting PVC sixty-five and charge.
chain & bottom weight plate with all necessary paise forty-
fixtures and fitting etc. complete. (Sample to be nine only
final by Engineer In-charge prior execution of
work) (AS per SSR 2022-23 Sr no. 1877, Item No.
51.20 Page no. 453)(Stilt to Eight floor)
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
37 96.00 Nos Double Faced Mobile Unit for Compactor 141172.42 Rupees one Nos 13552551.90 -- -- As directed by
2150mmH x 2745mmW x 900mm D Providing lakhs forty- Engineer in
and fixing Double Faced Mobile Unit for one thousand charge.
Compactor 2150mmH x 2745mmW x 900mmD - one hundred
BASE FRAME : Base Frame shall be fabricated in seventy-two
channel Type from minimum 2.5 mm thick MS and paise
Sheet Size of Channel 25mm x 100mm x 45mm. forty-two
GUIDE RAILS : The guide rails shall be made only
out of 28mm Bright bar placed on 1.2 mm thick
M.S. Plate which will be above the floor and are as
per the international standard of safety. SUPER
STRUCTURE : Super structure of the Mobile
storage system will consist of knock down type
panels. All the components such as shelves,
front panel, end panel, vertical rear panel,
central partition etc. Will act as an integral
member of the Unit. SHELVES : Shelves made
of 22SWG thick Prime Quality C.R.C.A. having 10
folds each will be provided each designed to
carry a U.D.L. of 70 kgs. VERTICAL PANEL :
Vertical panel consists of the front, Centre & rear
panel shall be made out of 20SWG thick
C.R.C.A. Prime quality Mild Steel & designed to
take the load of shelves. (AS per SSR 2022-23 Sr
no. 1870, Item No. 51.45 Page no. 360)
(Godrej / equivalent Specifications )
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
38 9.00 Nos Single Faced Mobile Unit for Compactor 103708.84 Rupees one Nos 933379.50 -- -- As directed by
2150mmH x 2745mmW x 457mm D Providing lakhs three Engineer in
and fixing Single Faced Mobile Unit for thousand charge.
Compactor 2150mmH x 2745mmW x 457mmD - seven
BASE FRAME : Base Frame shall be fabricated in hundred eight
channel Type from minimum 2.5 mm thick MS and paise
Sheet Size of Channel 25mm x 100mm x 45mm. eighty-four
GUIDE RAILS : The guide rails shall be made only
out of 28mm Bright bar placed on 1.2 mm thick
M.S. Plate which will be above the floor and are as
per the international standard of safety. SUPER
STRUCTURE : Super structure of the Mobile
storage system will consist of knock down type
panels. All the components such as shelves,
front panel, end panel, vertical rear panel,
central partition etc. Will act as an integral
member of the Unit. SHELVES : Shelves made
of 22SWG thick Prime Quality C.R.C.A. having 10
folds each will be provided each designed to
carry a U.D.L. of 70 kgs. VERTICAL PANEL :
Vertical panel consists of the front, Centre & rear
panel shall be made out of 20SWG thick
C.R.C.A. Prime quality Mild Steel & designed to
take the load of shelves. DRIVE COVER PANEL :
Made out of 22SWG thick C. R.C. A. prime quality
Steel to cover the entire drive mechanism.
CENTRE PARTITION : The (AS per SSR 2022-23
Sr no. 1871, Item No. 51.46 Page no. 361) (Godrej
/ equivalent Specifications )
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
39 62.00 Nos Providing & Fixing Alluminium foldable ladder for 4117.46 Rupees four Nos 255282.50 -- -- As directed by
storeProviding & Fixing Foldable Alluminum thousand one Engineer in
Ladder 1500 mm. Ht. (AS per SSR 2022-23 Sr no. hundred charge.
1877, Item No. 51.52 Page no. 365) SSR Rate 2022- seventeen and
23 paise forty-six
only
40 145.00 Nos Providing & Supplying of double sided name plate 1761.95 Rupees one Nos 255483.10 -- -- As directed by
made out of 6 mm thick sunboard size of 15"x8" thousand Engineer in
pasting vinyl yellow golden letter patch on both side seven charge.
on black patch etc. complete. hundred
sixty-one and
paise ninety-
five only
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
41 1.00 Nos Anti Chamber Judge Chair (PDJ cabin) - Halo Very 72893.00 Rupees Nos 72893.00 -- -- As directed by
High Back Chair - The Chair should be green seventy-two Engineer in
assured validated thousand charge.
by TUV India as per SOV, TUV-ECO-2011/008. eight hundred
The seat should be made up of1.2 ± 0.1cm. thick hot ninety-three
pressed plywood measured as per QA method and paise nil
described in OCP-QLTA-P14-18 and upholstered only
with leather and moulded Polyurethane Foam. The
back foam should be designed with contoured
lumber support for extra comfort. Back size is
53.0cm.(W) X 95.4cm.(H) SEAT SIZE is
54.6cm.(W) X 49.0cm.(D). The HR polyurethane
foam should be moulded with density = 45 +/-2
kg/m3 and Hardness load 16 ± 2 kgf as per IS:7888
for 25% compression. The seat and back should be
arrested together
with spine made of 0.8±0.05 cm thk HR Steel and is
black powder-coated (OFT 40-60 microns ). The
armrest assy. should be comprised of three parts viz.
the armrest support tube and P.U. armrest and the
armrest top. The armrest tube assy. is made of
2.54±0.03cm x 0.16±0.0128cm M.S.E.R.W.
support tubes and Chrome plated. The P.U. armrest
should be made of black integral skin polyurethane
with 50-70 shore 'A' Hardness and reinforced
withM.S. insert.The armrest top should be made of
ABS & upholstered with foam & leather.
The mechanism should be designed with the
following features: •360° revolving type. •Seat back
tilting ratio of 1 : 1.5 •Front pivot for tilt with feet
resting on ground ensuring more comfort. •Tilt
tension adjustment. •5- position locking with anti-
shock back mechanism, which prevents the backrest
from impacting the user when the lock should be
released.Signature
•Static seatof Contractor
depth adjustment = 5.0 ± No. of Corrections Executive Engineer
0.5cm with 5 position locking. Pneumatic
height adjustment should have an adjustment stroke
of 9.0 ± 0.3cm. The bellow should be 1 piece and
125
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
42 28.00 Nos Marvel High back Chair - 1) SEAT ASSEMBLY : 20820.00 Rupees Nos 582960.00 As directed by
The Cushioned seat should be made of Injection twenty Engineer in
molded Plastic outer & inner. Plastic Inner should thousand charge.
be upholstered with leatherette and moulded High eight hundred
Resilience (HR) Polyurethane foam of Density twenty and
45±2 kg/m3,and hardness load 16 ± 2 kgf as per paise nil only
IS:7888 for 25% compression.*Seat SIZE : 47.0
cm. (W) x 48.0 cm. (D) 2) BACK ASSEMBLY:
The Cushioned back should be made of PU Foam
with insitu molded MS E.R.W Round Tube of size
1.9±0.03cm x 0.16 ±0.0128cm. It upholstered with
Leatherette. HIGH BACK SIZE: 47.7 cm. (W) x
76.4 cm3) ARMRESTS : The armrest top should be
moulded from polyurethane(PU) and mounted on to
a drop lift adjustable type tubular armrest support
made of 03.81±0.03 cm x 0.2±0.01 cm thk M.S.
E.R.W tube having chrome plated finish.The
armrest height adjustable up to 6.5±0.5cm in 5
steps. (Godrej company or Equivalent)
43 605.00 Nos Staff Mid Back chair Option - 3 Oxbo Mid Back 7560.00 Rupees seven Nos 4573800.00 -- -- As directed by
Chair -Back: (W)46.5 cm x (H)60.5cm, Seat : thousand five Engineer in
(W)47.0cm x (D) 48.0cm Overall Dimensions of hundred sixty charge.
Chair Seat Height - min 43.3 to max 54.3cm.Height and paise nil
- min 89.5 to max 100.5cm.Width & Depth of Chair only
as measured from pedestal - Width-76.3 cm and
Depth-76.3 cm. (Product Colour may vary as per
Engineer Incharge Instructions)
(Godrej company or Equivalent)
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
44 126.00 Nos Staff Mid back chair - "CANDID" ERGONOMIC 9033.00 Rupees nine Nos 1138158.00 -- -- As directed by
MESH BACK CHAIR thousand Engineer in
* NYLON SLEEK & DOUBLE FRAME thirty-three charge.
* ADJUSTABLE LUMBAR SUPPORT and paise nil
* 4 WAY / 2 DIMENSIONAL ADJUSTABLE only
ARMS WITH SOFT PU PAD
* MOULDED PU FOAM WITH PLANO FABRIC
UPHOLSTERY (FIRE RETARDANT, HIGH
STRENGTH, HIGH COLOR FASTNESS TO
LIGHT)
* HIGH DENSITY FOAM WITH PLY AND PP
BACKING - DUST & MICROBES PREVENTION
* CLASS IV GASLIFT - GLOBAL BEST
QUALITY
* SYNCHRO 1 MECHANISM (1:3)
ERGONOMIC UPRIGHT LOCKING
* NYLON BASE - GLASS REINFORCED -
TESTED FOR 1250 KG
* TWIN WHEEL HEAVY DUTY NYLON
CASTORS
* BIFMA COMPLIANT (Wipro
company or Equivalent)
45 125.00 Nos Visitors Chair - ANNEXE CHAIR 7451.00 Rupees seven Nos 931375.00 -- -- As directed by
* CUSHION SEAT & BACK thousand four Engineer in
* MS UNDERSTRUCTURE hundred fifty- charge.
(Wipro company or Equivalent) one and paise
nil only
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
46 282.00 Nos Anti Chamber Visitor Chair - Kareena Visitor - 10378.00 Rupees ten Nos 2926596.00 -- -- As directed by
SEAT SIZE 51.0cm.(W) X 48.0cm.(D)2.HIGH thousand Engineer in
RESILIENCE (HR) POLYURETHANE FOAM: three hundred charge.
The HR polyurethane foam for seat and back should seventy-eight
be moulded with density = 45±2 kg/m³ and and paise nil
Hardness load 16 ± 2 kgf for 25% only
compression.3.ARMRESTS: The armrest top
should be made of moulded polyurethane (P.U) and
mounted on to a fixed type M.S. tubular armrest
support which should be chrome plated. The arm
support has static vertical adjustment of
±1.5±0.05cm. 4.FIXED BACKREST: The backrest
consshould be ts of a fixed type mechanism i.e. no
back up/down adjustment.
5.LEG FRAME ASSEMBLY: The leg frame
welded assembly should be chrome plated, made
from 3.5 ±0.03cm. x 1.5 ±0.02cm. x
0.16±0.0128cm. thk Elliptical M.S. ERW tube and
provided with a base plate for seat fixing. (Product
Colour may vary as per Engineer Incharge
Instructions) (Godrej company and equivalent)
47 401.00 Nos PVC luxury heavy duty chair. Made from superior 1902.29 Rupees one Nos 762816.30 -- -- As directed by
material quality and workmanship ,low dead thousand nine Engineer in
weight, user friendly and Extra Strong heavy Duty hundred two charge.
Brand name Nilkamal One year Warranty and paise
twenty-nine
only
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
48 927.00 Nos Public Waiting Area and Court Hall - Nano Perch - 20019.00 Rupees Nos 18557613.00 -- -- As directed by
Waiting Area - It should be made up of black twenty Engineer in
powder coated rectangular M.S.ERW tube having thousand charge.
8.0 ± 0.03 cm x 4.0 ± 0.03 cm x 0.2 ± 0.014 cm nineteen and
size. It should be chrome plated made of cold rolled paise nil only
steel with 0.12 ± 0.013 cm thinkness. It should be
powder-coated perforated shell made from cold
rolled M.S. sheet (DIN1623 Partl ST-12 Grade)
0.14 ± 0.013 cm thickness.The Side Bar should be
made of Chrome plated solid steel 3.0 ± 0.03 cm x
1.2 ± 0.3 cm with fluting and plastic inserts. The
Shell should be assembled on the Cross Beam with
help of M8 Bolts (Per Seat - 8 nos. Seat to Bracket
and 4nos. Bracket to Cross Beam).
49 18.00 Nos Relish Canteen Table S.S. - 19783.00 Rupees Nos 356094.00 -- -- As directed by
Relish Table With SS Top 1200 W size shall be nineteen Engineer in
1180 Width mm x 460 Depth mm x 750 Height thousand charge.
mm. The top shall be in Stainless Steel brushed seven
finish with PLB insert for Durability. Easy to clean hundred
and maintain hygiene . The Understructure shall eighty-three
have side frames shall be made from 30 mm x 30 and paise nil
mm x 1.5 mm thick MS Powder Coated tubes at only
base which are welded and are fixed to top with
screws . The bottom ends are closed with plastic
bottles. MS Shade : S/G Metallic Dark Grey . The
Cross Member shall be made from 30 mm x 30 mm
x 1.5 mm thick MS powder coated tube,which is
welded and bolted to side frames. (Godrej company
or Equivalent)
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
50 200.00 Nos Conferance Hall- WIPRO AUDI CHAIR 12928.00 Rupees Nos 2585600.00 -- -- As directed by
SYMPHONY twelve Engineer in
* PUSHBACK WITH SEAT AUTO-TIPUP thousand nine charge.
* FABRIC (FIRE RETARDANT & FOAM hundred
BACKED) twenty-eight
* UNIQUE TECH. OF FLUMATIC SLIDER and paise nil
MECHANISM (ENSURING ERGONOMIC only
DESIGN WITH EASY MOVEMENT)
* AUTOMOTIVE GRADE FOAM (HIGH
DENSITY)
* ARM WITH TRAINING FLAP
* METAL SKELETON & HIGH TORSION
SPRING
* AISLE NUMBERING, LIGHTS
* COMMON ARMRESTS CONSIDERED (Wipro
company or Equivalent)
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
51 6.00 Nos Conference Hall Desklet Chair Option 2 - 7004 11211.00 Rupees Nos 67266.00 -- -- As directed by
Non Revolving with Full Desklet Chair - eleven Engineer in
1)SEAT/BACK ASSEMBLY: The seat and back thousand two charge.
should be made up of 1.2 ±0.1cm, thick hot pressed hundred
plywood, upholstered with fabric and moulded eleven and
Polyurethane foam with PVC lipping all around. paise nil only
The back foam should be designed with contoured
lumbar support for extra comfort. PCH-7004 (MID
BACK) SIZE: 49.0cm. (W) X 47.0cm. (H) SEAT
SIZE: 49.0cm. (W) X 44.0cm. (0)
2)POLYURETHANE FOAM: The polyurethane
foam should be moulded with density = 45 ±2 kg/m'
and Hardness = 20 ±2 on Hampden machine at 25%
compression.3)TUBULAR FRAME: The tubular
frame should be cantilever type & made of 0 2.54
±0.03cm. x 0.2 +0.016cm. M.S. E.R.W. tube and
black powder coated ( DFT 40-60 microns ).The
Armrest Tube of 0 2.54+0.03cm. x 0.2 ±0.016cm.
M.S. E.R.W. tube should be welded to mainframe.
The desklet should be fitted on the right hand
side.4)DESKLET ASSEMBLY: The wooden
desklet should be made of 1.8 ±0.05cm. thk. pre-
laminated particleboard with 0.15 ±0.03cm. thk.
P.V.0 lipping all around.SIZE: 58.0±0.1cm. (W) X
29.0±0.1cm. (0).5)ARMRESTS: The one-piece
armrests should be made of black integral skin
polyurethane foam with 50-70 Shore hardness and
reinforced with M.S. insert. The armrests should be
scratch and weather resistant tant. 6) PAPER
TRAY: The paper tray should be made of 0 0.4
+01- 0.005cm. M.S. wire spot welded to form a
mesh. It should be
black powder coated ( DFT 40-60 microns ).SIZE:
35.0±1.0cm.
Signature of
(W) X 36.0±1.0cm. (D).Contractor
X 12.5±1.0cm.(H) (Godrej No. of Corrections Executive Engineer
company or Equivalent)
131
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
52 22.00 Nos. Judge Chair : Providing and fixing an executive 22226.00 Rupees Nos. 488972.00 -- -- As directed by
chair made in well seasoned old Burma teak with twenty-two Engineer in
carved details. The chair shall be constructed in old thousand two charge.
burma hundred
teak wood as per the image in the drg. The seat shall twenty-six
be covered with composite leather (instead of cane) and paise nil
and the back shall be netted in cane as shown. All only
wooden surfaces shall be finished with approved
french polish. Basic rate of leater rate: 300/m Item
to include spray coating all the surfaces with
approved
anti termite solution including providing 10 year
guarantee for the same as direxted by the Architect
or Engineer in Charge (Rate depend upon Mira
Bhaindar Court building's Furniture TS estimate)
53 24.00 Nos Pisa Sofa - Judges Cabin (3+1+1) 90553.00 Rupees ninety Nos 2173272.00 As directed by
(Godrej company or equivalent) thousand five Engineer in
hundred fifty- charge.
three and
paise nil only
54 47.52 Sqm Witness Box :- Providing and Supplying Witness 13340.00 Rupees Sqm 633916.80 -- -- As directed by
Box in court hall of size 900 W x 900 D x 1200 H thirteen Engineer in
in mm. Using Solid wood (Teak wood) framing thousand charge.
with polish. One side will be open with Fitted three hundred
necessary hardware etc. forty and
paise nil only
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
55 PROVIDING AND FIXING MODULAR Rupees nil 0.00 -- -- As directed by
ACOUCTICAL WOODEN WALL PANELLING: and paise nil Engineer in
Of nominal width 100 / 150mm, having 80mm wide only charge.
panel with 20mm reveal having a thickness of
15mm thickness and length 2400 mm. The panel
shall be made of a Moisture resistant fibre board
substrate having a minimum density of 595 Kg/m3
with a laminated facing as per the approved shade
(Portland Maple, Sea Beech, Siam Wood &
Mystique Walnut) and a melamine balancing layer
on the reverse side. The panel shall have 0.7mm
PVC edge banding along the length side with a
similar finish as that of the face. The back of the
panel shall have a black acoustic felt to cover the
reveal
of 20mm to attain an NRC of 0.4 for 150mm. / 0.5
for 100mm. module (Average value of Absorption
Co-efficient readings taken at 250 Hz, 500 Hz, 1000
Hz and 2000 Hz) as per ASTM C423. The panels
shall provide a Humidity Resistance (RH) of 70%
with camber limit less than 1mm/1000mm and bow
less than 1mm/300mm. The back of the panels shall
be profile-grooved to receive 3600mm special main
beam carrier with integrated
factory fitted clips for installation. SUSPENSION:
The panels shall be upward mounted on 24 mm
wide T - section flanges having rotary stitching
along the length of the beam with a web height of
43mm. The Main Beam shall have integrated
(factory fitted) locking clips installed at 100 /
150mm centre to centre distance. The deflection
loading of the main beam tested as per ASTM C635
(Deflection limit less than L/360) shall be at least
21.4kg/m. The end details of the main beam shall be
made ofSignature
pre hardened ofsteel
Contractor
and fixed to the ends No. of Corrections Executive Engineer
with 3 point fixing. All main beam to main beam
connection shall have a pull out strength of more
than 100kg. The T Sections shall be made of hot
133
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
55a 96.76 Sqm Third Floor 11653.34 Rupees Sqm 1127576.70 -- -- As directed by
eleven Engineer in
thousand six charge.
hundred fifty-
three and
paise thirty-
four only
55b 96.76 Sqm Fourth Floor 11766.47 Rupees Sqm 1138524.10 -- -- As directed by
eleven Engineer in
thousand charge.
seven
hundred
sixty-six and
paise forty-
seven only
55c 96.76 Sqm Fifth Floor 11823.04 Rupees Sqm 1143997.80 -- -- As directed by
eleven Engineer in
thousand charge.
eight hundred
twenty-three
and paise four
only
55d 72.57 Sqm Sixth Floor 11879.61 Rupees Sqm 862103.60 -- -- As directed by
eleven Engineer in
thousand charge.
eight hundred
seventy-nine
and paise
sixty-one only
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
55e 96.76 Sqm Seventh Floor 11936.18 Rupees Sqm 1154945.10 -- -- As directed by
eleven Engineer in
thousand nine charge.
hundred
thirty-six and
paise eighteen
only
55f 72.57 Sqm Eight Floor 11992.75 Rupees Sqm 870314.10 -- -- As directed by
eleven Engineer in
thousand nine charge.
hundred
ninety-two
and paise
seventy-five
only
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
56 4.00 Nos Pigeon Hole - Inward Outward Tapal - Overall 32968.00 Rupees thirty- Nos 131872.00 -- -- As directed by
Dimensions of Pigeon Hole Base 1200 H Add On two thousand Engineer in
Modish Oak shall be 264mm(W)x 400mm(D) nine hundred charge.
x1200mm(H) . The Construction shall be Rigid sixty-eight
Knock Down Construction . Material used shall be and paise nil
all side panels , top/bottom panels and shelf panels only
shall be made from 18 mm thick Pre- Laminated
Board (interior grade) with 2 mm thick PVC edge
beading . Back panel shall be made from 9 mm
thick Pre- Laminated board . Stackability shall have
Add on units stacked width wise to form a bank of
racks having common side panel (max . 6 Add ons)
. The shelfs shall be 6' Main Module has 12 shelves
placing in 207 mm distance , 4' Main module has 8
shelves placing in 270 mm distance . The
Configuration shall have 6 ' Main Module , 4 ' Main
Module also 6' Add on module , 4' Add on module
.(Godrej company or equivalent)
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
57 39.00 Nos Storwel (Plain) - Administration Branch - Storwel 23321.00 Rupees Nos 909519.00 -- -- As directed by
plain shall have an overall size of twenty-three Engineer in
916mm(W)x486mm(D)x1981mm(H) with welded thousand charge.
construction. It should have the shelf thickness of three hundred
0.7 mm, Back thickness of 0.8mm, Door thickness twenty-one
of 0.8mm (high yield strength) and all other and paise nil
components shall have a thickness of 0.9mm. These only
components shall be made of CRCA ‘D’ grade high
yield strength as per IS:513. The Storwel Plain
should have a Mazak handle and Three way locking
mechanism with Shooting Bolts. It should have a
height wise adjustable shelf mounting which shall
have a Uniformly Distributed Load Capacity of max
40 Kg. It should also have a M10 Screw type
Leveller with Hex plastic base. The finishing shall
include Epoxy powder coated to the thickness of 50
microns (+/- 10). Plenty of colour options and
shelving options shall be available. (Godrej
company or equivalent)
58 38.00 Nos Edward Corner Table - PDJ Chember, Conference 12528.00 Rupees Nos 476064.00 -- -- As directed by
Hall & VIP Waiting Area (Godrej company or twelve Engineer in
equivalent) thousand five charge.
hundred
twenty-eight
and paise nil
only
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
59 34.00 Nos Gain Pro Locker Unit 2 Door - Bar Room 12647.00 Rupees Nos 429998.00 -- -- As directed by
(Godrej company or equivalent) twelve Engineer in
thousand six charge.
hundred
forty-seven
and paise nil
only
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
60 72.00 Nos Shine Canteen Chair - 3477.00 Rupees three Nos 250344.00 -- -- As directed by
1. SHELL : The single piece seat back shell is made thousand four Engineer in
up of injection hundred charge.
moulded high impact strength glass filled seventy-seven
polypropylene polymer compound (refer product and paise nil
catalogue for colourchart).* SHELL SIZE : 44.0 only
cm. (W) x 50.2 cm. (D) x 40.5 cm. (H)2. M.S.
POWDER COATED UNDERSTRUCTURE
OPTION (SM6): The powder
coated (DFT 50±10 microns) welded tubular frame
is made from ∅ 2.22 ± 0.03 cm x 0.16 ± 0.0128 cm
M.S. E.R.W tube. The 0.16 ± 0.008 cm thk CRCA
sheet is welded to tubes for fixing shell to the frame.
The shoe is made of high impact strength
polypropylene polymer
compound and are fitted at the end of the tubular
frame.
3. S.S. UNDERSTRUCTURE OPTION (SM6) :
The tubular welded frame is made from Dia 2.22 ±
0.03 cm x 0.15 ± 0.0128 cm Stainless Steel 304
grade tube which is buff polished. The 0.16 ± 0.008
cm thk Stainless Steel 304 CRCA sheet is welded to
tubes for fixing shell to the frame.The shoe is made
of high impact strength polypropylene polymer
compound and are fitted at the end of the tubular
frame. (Godrej company or equivalent)
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
61 88.00 Nos Decorative teak wood chair of size 0.45 x 0.45 cms 11226.60 Rupees Nos 987940.80 -- -- As directed by
for the seat and seat height of 0.40 cms having back eleven Engineer in
height of 0.75 cms, as per catalogue approved by thousand two charge.
Chief Architect to the Govt. of Maharashtra, hundred
including teak wood frame by using Burma twenty-six
Teakwood 50 x 50 mm for legs support in H shape and paise
by using Burma teakwood 50 x 25 mm. The chair sixty only
should be without hand, high density foam of
required thickness for seat and back and covering
the foam by using best quality approved tepestry
costing Rs. 450/- per Rmt. Including melamine
polish in two coats to the wooden surface etc.
complete. The exposed area of the teakwood and
ply should be finished by melamine polish.
62 2.00 Nos ALYSIA 3 SEATER + 1 SEATER + 1 SEATER 61056.00 Rupees sixty- Nos 122112.00 -- -- As directed by
* LEATHERETTE UPHOLSTERY one thousand Engineer in
* INTERNAL STRUCTURE - PLY + METAL fifty-six and charge.
* HIGH DENSITY PU FOAM FOR SEAT & paise nil only
BACK
* WOOD LEGS (Wipro company or Equivalent)
63 3.00 Nos Aristocrat Sofa - Conference VIP Waiting area 146278.00 Rupees one Nos 438834.00 -- -- As directed by
(3+1+1) (Godrej company or equivalent) lakhs forty- Engineer in
six thousand charge.
two hundred
seventy-eight
and paise nil
only
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
64 ACOUSTICAL WOODWOOL WALL -- -- As directed by
PANELLING: Providing & fixing of 100% Natural Engineer in
Material- Magnesite (Hygroscopic & biologically charge.
sound binding agent) bonded woodwool Heradesign
planks of 600Mm*1200Mm *25Mm thickness
made out of wood wool fibre of width 1Mm Fiber
thickness mixed with Natural water & Magnesite
(NoCement) with open & smooth surface texture,
Weight of panel to be 11.3 Kg/m2. A Completly
harmless Envirenment & Human Friendly & also a
disposable or recyclable Material & can last for
more than 80 Years in building interiors As it has
long lifespan & suitable for Indoor conditions with
relative air humidity of upto 90%. Magnesite
protects the wood cells against ageing & fungal
attack. To achive upto NRC=1.00 it should be
aclear gap of 200Mm from wall slab along with the
backing of Mineral wool of 50mm thick with 64
kg/m3 density. Ecologically Sound Material with
high mechanical strength with Crash test of
90Km/H with Ball Impact Test DIN18032 &
EN13964 with flying colors & A sustainable
material (PEFC & FSC Certified) along with EPD
Certified Acc. to EN ISO 14025 (AUB
Envirenmental Product declaration). Manufacturing
tolerance for nominal size: Length, Width &
Thickness ± 1 mm, & In a Standard Climate of 23°
C and 50% rel. humidity. FIXING &
SUBSTRUCTURE: Impact Resitant According to
DIN18023 or EN13964 to be Fixed on CD Sections
Profile framework with Screw 9Pc/Panel & Centre
Distance Support of 300Mm & Centre distance of
Cross Profile would be at 600Mm & Main Profile at
900Mm CD Profile is made out of GI( Sections
Signature of Contractorx 60Mm Width No. of Corrections
Profile 60/27/0.6Mm-0.6MmThick Executive Engineer
x 0.27Mm height). The Main Profile is in the legth
of 3000Mm & to form a section of 600mm x
1200mm. Heradesign Superfine panels to be fixed
141
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
64a 126.54 Sqm Stilt floor 7158.00 Rupees seven Sqm 905772.90 -- -- As directed by
thousand one Engineer in
hundred fifty- charge.
seven and
paise ninety-
nine only
64b 181.65 Sqm Eight Floor 7551.69 Rupees seven Sqm 1371763.90 -- -- As directed by
thousand five Engineer in
hundred fifty- charge.
one and paise
sixty-nine
only
65 Providing and Fixing of GI Lay in Plain metal -- -- As directed by
ceiling consisting of 600x600mm Lay in tiles of pre Engineer in
coated galvanized steel in 0.5mm thickness in charge.
Global whte color tile to be laid on grid systems
with 15 mm wide T-section flanges color white
having rotary stitching on the Main Runner,
1200mm and 600mm Cross Tees. Providing and
Fixing of GI Layin Plain metal ceiling consisting of
600x600mm Lay in tiles of precoated galvanized
steel in 0.5mm thickness in Global whte color tile to
be laid on grid systems with 15mm wide T-section
flanges color white having rotary stitching on the
Main Runner, 1200mm and 600mm Cross Tees.
products approved as per GRIHA and BS 476 etc.
complete. (Third Floor to Eight Floor)
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
65a 472.84 Sqm Third Floor 2149.94 Rupees two Sqm 1016575.50 -- -- As directed by
thousand one Engineer in
hundred charge.
forty-nine and
paise ninety-
four only
65b 472.84 Sqm Fourth Floor 2170.81 Rupees two Sqm 1026445.20 -- -- As directed by
thousand one Engineer in
hundred charge.
seventy and
paise eighty-
one only
65c 472.84 Sqm Fifth Floor 2181.25 Rupees two Sqm 1031380.00 -- -- As directed by
thousand one Engineer in
hundred charge.
eighty-one
and paise
twenty-five
only
65d 472.84 Sqm Sixth Floor 2191.68 Rupees two Sqm 1036314.80 -- -- As directed by
thousand one Engineer in
hundred charge.
ninety-one
and paise
sixty-eight
only
65e 472.84 Sqm Seventh Floor 2202.12 Rupees two Sqm 1041249.70 -- -- As directed by
thousand two Engineer in
hundred two charge.
and paise
twelve only
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
65f 685.33 Sqm Eight Floor 2212.55 Rupees two Sqm 1516330.30 -- -- As directed by
thousand two Engineer in
hundred charge.
twelve and
paise fifty-
five only
66 Providing and Fixing of Mineral Fibre Board -- -- As directed by
Acoustical Suspended Ceiling System with ultima Engineer in
(Bevelled Tegular) Edge Tiles of size 15mm charge.
Exposed GRID. The tiles should have Humidity
Resistance (RH) of 99%, NRC 0.7, Light
Reflectance 85%, Thermal Conductivity k = 0.052 -
0.057 w/m K, Colour White, Fire Performance UK
Class 0 / Class 1 (BS 476 pt - 6 &7) in module size
of 600 x 600 x 20mm suitable for Green Building
application, with Recycled content of 32%. The tile
shall be laid on precoated G.I.channel on XL2 Clip
having a web height of 32 mm with 15 mm wide
T - section flanges colour white having rotary
stitching on all T sections i.e. the Main Runner,
1200 mm and 600 mm Cross Tees with a web
height of 32 mm and a load carrying capacity of 7.7
Kilograms/M2 and minimum pull out strength of
100 Kilograms.. The T Sections have a Galvanizing
of 90 grams per M2 and need to be installed with
Suspension system. The Tile and Grid system used
together should carry a 10 year warranty. products
approved as per GRIHA and BS 476 etc. complete.
(AS per SSR 2022-23 Sr no. 1185, Item No. 38.45
Page no. 241) (Third Floor to Eight Floor)
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
66a 582.88 Sqm Third Floor 2815.90 Rupees two Sqm 1641332.70 -- -- As directed by
thousand Engineer in
eight hundred charge.
fifteen and
paise ninety
only
66b 582.88 Sqm Fourth Floor 2843.24 Rupees two Sqm 1657268.00 -- -- As directed by
thousand Engineer in
eight hundred charge.
forty-three
and paise
twenty-four
only
66c 582.88 Sqm Fifth Floor 2856.91 Rupees two Sqm 1665235.60 -- -- As directed by
thousand Engineer in
eight hundred charge.
fifty-six and
paise ninety-
one only
66d 437.16 Sqm Sixth Floor 2870.58 Rupees two Sqm 1254902.40 -- -- As directed by
thousand Engineer in
eight hundred charge.
seventy and
paise fifty-
eight only
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
66e 582.88 Sqm Seventh Floor 2884.25 Rupees two Sqm 1681170.90 -- -- As directed by
thousand Engineer in
eight hundred charge.
eighty-four
and paise
twenty-five
only
66f 437.16 Sqm Eight Floor 2897.92 Rupees two Sqm 1266853.90 -- -- As directed by
thousand Engineer in
eight hundred charge.
ninety-seven
and paise
ninety-two
only
67 52.20 Sqm Providing and fixing on site notice board made out 1655.92 Rupees one Sqm 86439.20 -- -- As directed by
of 6mm marine ply of the requisite manufacture thousand six Engineer in
generally confirming to I.S.310/I.S.710-1980 hundred fifty- charge.
backing and 12 mm thick soft board convered with five and paise
tapestry/up to Rs. 200 per meter including necessary ninety-two
lipping (BTC), moulding, hardware, polishing etc only
and Anti-termite treatment to plywood and
woodwork with ten years guarantee bond etc.
including all leads & lifts etc. complete as per
Architect Drawing and instructions of Engineer in
charge.
68 29.00 Nos Supplying and fixing of white magnestic board 8281.70 Rupees eight Nos 240169.20 -- -- As directed by
mounted in frame size 8' x 4' as per requirement. thousand two Engineer in
hundred charge.
eighty-one
and paise
seventy only
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
69 49.00 Nos Supplying of Tip-up type molded ergonomicaly 4620.58 Rupees four Nos 226408.30 -- -- As directed by
design P.U. cushaning with flap type conceled thousand six Engineer in
writing table, fully pholstered for acostice as per hundred charge.
specification. twenty and
paise fifty-
eight only
70 Supplying glass table top 8 mm thick in required Rupees nil -- -- As directed by
size and shape including finishing the all side edges and paise nil Engineer in
machnically smoothly etc complete. only charge.
70a 23.94 Sqm Stilt floor 835.76 Rupees eight Sqm 20008.00 -- -- As directed by
hundred Engineer in
thirty-five and charge.
paise seventy-
six only
70b 33.80 Sqm First floor 844.12 Rupees eight Sqm 28526.90 -- -- As directed by
hundred Engineer in
forty-four and charge.
paise twelve
only
70c 10.80 Sqm Second floor 852.47 Rupees eight Sqm 9206.70 -- -- As directed by
hundred fifty- Engineer in
two and paise charge.
forty-seven
only
70d 46.62 Sqm Third Floor 860.83 Rupees eight Sqm 40131.90 -- -- As directed by
hundred sixty Engineer in
and paise charge.
eighty-three
only
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
70e 56.48 Sqm Fourth Floor 869.19 Rupees eight Sqm 49087.40 -- -- As directed by
hundred Engineer in
sixty-nine and charge.
paise nineteen
only
70f 59.67 Sqm Fifth Floor 873.37 Rupees eight Sqm 52113.80 -- -- As directed by
hundred Engineer in
seventy-three charge.
and paise
thirty-seven
only
70g 52.11 Sqm Sixth Floor 877.55 Rupees eight Sqm 45728.90 -- -- As directed by
hundred Engineer in
seventy-seven charge.
and paise
fifty-five only
70h 58.64 Sqm Seventh Floor 881.72 Rupees eight Sqm 51699.90 -- -- As directed by
hundred Engineer in
eighty-one charge.
and paise
seventy-two
only
70i 58.23 Sqm Eight Floor 885.90 Rupees eight Sqm 51586.20 -- -- As directed by
hundred Engineer in
eighty-five charge.
and paise
ninety only
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
71 1.00 Nos Palana : Supplying Premium Cradle of size around 6390.85 Rupees six Nos 6390.80 -- -- As directed by
39 x 24 x 40 inches includes removable, washable, thousand Engineer in
cover with detachable mosquito net and waterproof three hundred charge.
mattress, cradle trolley can be detached and used as ninety and
cot, cradle trolley comes with wheels for easy paise eighty-
movement on the indoor floor. Can be adjusted at five only
three heights with height auto lock system, Two
side bearings of the cradle provide very smooth
swinging motion, cradle cover is made from fine
quality fabric, it comes with a swing lock to shop
the motion and keep it in steady position. (Material
supplied should be standard company)
72 194.00 Nos Supplying and fixing of Acrylic board 4 mm thick 550.94 Rupees five Nos 106881.40 -- -- As directed by
mounted in steel frame size 45 cm x 30 cm as per hundred fifty Engineer in
requirement with required lettering. and paise charge.
ninety-four
only
73 90.00 Nos Auto Glow Signages 4781.70 Rupees four Nos 430353.00 -- -- As directed by
Supplying and fixing Auto glow signage screen thousand Engineer in
printed material A robust self andhesive sheet this seven charge.
can be fixed an surface which used photolumiscent hundred
material for safety signs, size 400 mmx 400 mm. eighty-one
and paise
seventy only
74 469.98 Sqm Providing & Fixing in position, Carpet more than 1507.28 Rupees one Sqm 708389.10 -- -- As directed by
800+ gsm, made with100% stain proof fibres of thousand five Engineer in
approved make along with 5mm underlay as per hundred charge.
Architectural & Acoustical seven and
Design & Instructions & Complete in all aspects paise twenty-
including all materials labour,finishing eight only
etc complete
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
75 9.00 Nos Providing & Supplying WHEEL DUSTBIN 7179.83 Rupees seven Nos 64618.50 -- -- As directed by
120LTR. Capacity120Ltr.Made from superior thousand one Engineer in
material quality and workmanship,low dead hundred charge.
weight,userfriendly.These are the out standing seventy-nine
features of the wheel plastic container.Wheelss are and paise
made from solid rubber tyres. eighty-three
only
76 207.00 Nos Providing & Supplying Plastic Dust Bin 396.42 Rupees three Nos 82058.90 -- -- As directed by
hundred Engineer in
ninety-six and charge.
paise forty-
two only
77 151.00 Nos Providing & Supplying Jet Connector with Jet 1280.66 Rupees one Nos 193380.30 -- -- As directed by
Sprey Pipe Jaguar and Shower Hook thousand two Engineer in
hundred charge.
eighty and
paise sixty-six
only
78 151.00 Nos Providing & Supplying Plastic Buckets (5 Liters) 154.17 Rupees one Nos 23279.40 -- -- As directed by
hundred fifty- Engineer in
four and paise charge.
seventeen
only
79 151.00 Nos Providing & Supplying Plastic Mug 89.40 Rupees Nos 13499.40 -- -- As directed by
eighty-nine Engineer in
and paise charge.
forty only
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
80 800.00 Nos Providing & Supplying Paper Weight Glass 120.58 Rupees one Nos 96465.60 -- -- As directed by
medium size hundred Engineer in
twenty and charge.
paise fifty-
eight only
81 413.00 Nos Providing & Supplying Lock 7 Lever Godrej 782.74 Rupees seven Nos 323273.07 -- -- As directed by
hundred Engineer in
eighty-two charge.
and paise
seventy-four
only
82 194.00 Nos Providing & Supplying Coir foot mat 3' x2' 2547.81 Rupees two Nos 494276.00 -- -- As directed by
thousand five Engineer in
hundred charge.
forty-seven
and paise
eighty-one
only
83 27.00 Nos Providing & Supplying Coir Mattresses 10729.72 Rupees ten Nos 289702.40 -- -- As directed by
6" thick - 1" MM foam & 5" HR foam thousand Engineer in
8" thick - 2" MM foam & 6" HR foam seven charge.
Removable zipper cover for easy maintenance VOC hundred
& hazard free MM foam twenty-nine
and paise
seventy-two
only
84 400.00 Nos Providing & Supplying Scissor Medium Size 220.37 Rupees two Nos 88149.60 -- -- As directed by
hundred Engineer in
twenty and charge.
paise thirty-
seven only
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
85 400.00 Nos Providing & Supplying Calculator Casio 12 Digit. 484.41 Rupees four Nos 193762.80 -- -- As directed by
hundred Engineer in
eighty-four charge.
and paise
forty-one only
86 400.00 Nos Providing and supplying foot rest below table as per 1746.36 Rupees one Nos 698544.00 -- -- As directed by
approved typical drawing size and height using thousand Engineer in
commercial plywood 18mm thick with french seven charge.
polishig and finishing etc complete hundred
forty-six and
paise thirty-
six only
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
87 395.20 Sqm METAL FALSE CEILING WITHOUT SUSPENSION 6768.18 Rupees six Sqm 2674786.50 -- -- As directed by
SUPPORT FROM TRUE CEILING : Providing & fixing
thousand Engineer in
horizontal level suspended metal ceilings comprising of Metal
works F-H 600 Hook-on corridor system manufactured by seven charge.
Armstrong Ceiling Solutions with Rectangular panels made of hundred
0.7mm thick Galvanised Steel (GI) of 120gsm, post coated to sixty-eight
Global White colour, suitable for Interior applications and
and paise
architectural finishes, double grid concealed system and butt joint
panels. The panel width shall be 300mm, length ranging from eighteen only
1500mm to 2660mm. General Specifications: Entire system to be
designed for Interior applications, and concealed Grid, Butt joint
panels. Panel Specifications: Material: The F-H 600 rectangular
Hook-on panels to be made of galvanized steel (GI) of minimum
120gsm hot dipped galvanization (both sides included) as per
IS277 (2003), zero or minimum spangled, in minimum base
material thickness of 0.7mm as per in IS:513(1994). Dimensions:
The panel Length varies between 1500mm to 2660mm, panel
Width shall be 300mm. The dimensional tolerances for length
shall be ±1.0m upto 1000mm L; ±1.5mm between 1001 to
2000mm L; ±2.0mm between 2001 to 3000mm L. The
dimensional tolerances for width shall be ± 0.5m up to 300mm
W. Dimensional Tolerances for panel Thickness/panel
width/panel length-to be measured in accordance with TAIM
standards. Edge detail: the panels shall ha+A3ve Square Edge,
with a 3mm(W) x 8mm(H) black foam gasket glued at the edges,
typically on one long and one short side. All adjacent panels shall
touch each other forming a butt joint and concealed grid visuals.
Up turns: The short side of the panel shall have vertical up turns of
minimum 30mm (H) and shall be bent appropriately bent as per the
manufacturer’s specifications for providing hook-on ends. The long side
shall have in side horizontal bends of 5-15mm for rigidity and vertical up
turns of 40mm (for length ranging from 1251-2660mm). Surface Finish:
Plain: The panels shall be in plain unperforated finish (without any
acoustical backing/felt). Colour and finishes: The panel surface shall be
electrostatically powder coated (post coat) on visible side after mechanical
production, using RoHS compliant powder, to achieve coating thickness
ranging from 60-80μ and architectural quality finish. The powder coating
shall pass Salt Spray Test for 750 Hours as per ASTM B117, QUV –
A Test for 1000hours as per ASTM G-154 – (Cycle – 1) and
Humidity test for 1000hours as per DIN 50017, 250 hours of
(Stilt Floor)
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
88 10.00 Nos Providing & Supplying Sanitary Pad Machine 4620.00 Rupees four Nos 46200.00 -- -- As directed by
thousand six Engineer in
hundred charge.
twenty and
paise nil only
89 10.00 Nos Providing & Supplying Push cart and Airport trolley 10500.00 Rupees ten Nos 105000.00 -- -- As directed by
thousand five Engineer in
hundred and charge.
paise nil only
90 119.00 Nos Providing & Supplying Wall clock 3150.00 Rupees three Nos 374850.00 -- -- As directed by
thousand one Engineer in
hundred fifty charge.
and paise nil
only
91 400.00 Nos Providing & Supplying Table Bell 682.50 Rupees six Nos 273000.00 -- -- As directed by
hundred Engineer in
eighty-two charge.
and paise fifty
only
92 22.00 Nos Providing & Supplying Hanging pin 157.50 Rupees one Nos 3465.00 -- -- As directed by
hundred fifty- Engineer in
seven and charge.
paise fifty
only
93 22.00 Nos Providing & Supplying Aluminium thick hanger 131.25 Rupees one Nos 2887.50 -- -- As directed by
hundred Engineer in
thirty-one and charge.
paise twenty-
five only
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
94 151.00 Nos Providing & Supplying Broom and Broom with 241.50 Rupees two Nos 36466.50 -- -- As directed by
long beard hundred Engineer in
forty-one and charge.
paise fifty
only
95 151.00 Nos Providing & Supplying Plastic dust pan 336.00 Rupees three Nos 50736.00 -- -- As directed by
hundred Engineer in
thirty-six and charge.
paise nil only
96 400.00 Nos Providing & Supplying Pen stand 409.50 Rupees four Nos 163800.00 -- -- As directed by
hundred nine Engineer in
and paise fifty charge.
only
97 400.00 Nos Providing & Supplying Writing Pad 330.75 Rupees three Nos 132300.00 -- -- As directed by
hundred thirty Engineer in
and paise charge.
seventy-five
only
98 4.00 Nos Providing & Supplying Vaccum cleaner 22785.00 Rupees Nos 91140.00 -- -- As directed by
twenty-two Engineer in
thousand charge.
seven
hundred
eighty-five
and paise nil
only
99 45.00 Nos Providing & Supplying Plastic strong tray in big 154.35 Rupees one Nos 6945.80 -- -- As directed by
size hundred fifty- Engineer in
four and paise charge.
thirty-five
only
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
100 800.00 Nos Providing & Supplying Plastic strong tray in small 317.10 Rupees three Nos 253680.00 -- -- As directed by
size hundred Engineer in
seventeen and charge.
paise ten only
101 200.00 Nos Providing & Supplying Transperant name plate and 105.00 Rupees one Nos 21000.00 -- -- As directed by
hundred five Engineer in
and paise nil charge.
only
102 200.00 Nos Providing & Supplying wooden strong name plate 299.25 Rupees two Nos 59850.00 -- -- As directed by
hundred Engineer in
ninety-nine charge.
and paise
twenty-five
only
103 44.00 Nos Providing & Supplying Curtain 2588.25 Rupees two Nos 113883.00 -- -- As directed by
thousand five Engineer in
hundred charge.
eighty-eight
and paise
twenty-five
only
104 Providing and fixing Country cut teak wood partly -- -- As directed by
veneered and partly glazed partition with 75mm x Engineer in
50mm frame at 60cm center and 9mm thick charge.
commercial ply on both sides, decorative veneer of
4mm thick and plain glass 5mm thick ,including
French polishing etc.complete
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
104a 1.22 Sqm Stilt floor 3293.14 Rupees three Sqm 4017.60 -- -- As directed by
thousand two Engineer in
hundred charge.
ninety-three
and paise
fourteen only
104b 41.31 Sqm First floor 3326.07 Rupees three Sqm 137399.80 -- -- As directed by
thousand Engineer in
three hundred charge.
twenty-six
and paise
seven only
104c 4.46 Sqm Third Floor 3391.93 Rupees three Sqm 15128.00 -- -- As directed by
thousand Engineer in
three hundred charge.
ninety-one
and paise
ninety-three
only
104d 23.39 Sqm Fifth Floor 3441.33 Rupees three Sqm 80492.60 -- -- As directed by
thousand four Engineer in
hundred charge.
forty-one and
paise thirty-
three only
104e 37.26 Sqm Sixth Floor 3457.79 Rupees three Sqm 128837.40 -- -- As directed by
thousand four Engineer in
hundred fifty- charge.
seven and
paise seventy-
nine only
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
104f 28.36 Sqm Seventh Floor 3474.26 Rupees three Sqm 98530.00 -- -- As directed by
thousand four Engineer in
hundred charge.
seventy-four
and paise
twenty-six
only
104g 14.18 Sqm Eight Floor 3490.72 Rupees three Sqm 49498.50 -- -- As directed by
thousand four Engineer in
hundred charge.
ninety and
paise seventy-
two only
Work :- 142024895.00
Portion
Testing of Material
105 Wood
50.00 1 Test Density, Moisture Content. 1060.00 Rupees one 1 Test 53000.00 -- --
thousand
sixty and
paise nil only
106 Flush door -- --
15.00 1 Test Knife Test, Adhesion Test, End Immersion Test. 2710.00 Rupees two 1 Test 40650.00 -- --
thousand
seven
hundred ten
and paise nil
only
107 PLYWOOD -- --
Item No Quantity Unit Item of Work Estimated Rate Unit Total Reference to Additional
Estimate Amount Standard 2012 Specifications
d but In Figures In Words according to Specifica Page No , if any
may be (Rs.) Estimated tion No
more or Quantities
less
1 2 3 4 5 6 7 8 9 10 11
65.00 1 Test Determination of Resistance to dry 3400.00 Rupees three 1 Test 221000.00 -- --
heat,Determination of Moisture thousand four
Content,Determination of Density,Thickness of hundred and
Plywood. paise nil only
65.00 1 Test Test for Glue Adhesion 530.00 Rupees five 1 Test 34450.00 -- --
hundred thirty
and paise nil
only
108 ALUMINIUM SECTION -- --
10.00 1 Test Thickness, Mass Per Running meter, 690.00 Rupees six 1 Test 6900.00 -- --
hundred
ninety and
paise nil only
testing 3,56,000
GRAND TOTAL :- 142380895.00