STSKK’s

TONTADARYA COLLEGE OF ENGINEERING, GADAG


Department of Civil Engineering
--------------------------------------------------------------------------------------------------------------------------

Internal Assessment – I
Subject :Water Supply and Wastewater Engineering (BCV304) Date:
Semester: III Time:
Note: Answer one FULL question from each part.
Assume missing data suitably. Max Marks: 25
PART-A CO (RBT)
Q1 a) Explain the factors affecting the per capita demand. 06 M 1 (I,II)
b) Compute the population of the year 2000 and 2006 for a city whose
6.5 M 1 (I,II)
population in the year 1930 was 25,000 and in the year 1970 was
47,000. Make use of geometric increase method.
Q2 a) What is population forecasting? Discuss any two methods of population 06 M 1(I,II)
forecasting.
b) The population (in thousands) of 5 decades from 1930 to 1970 is given 6.5 M 1(I,II)
below table. Find out the population after one, two and three decades
beyond the last known decade, by using Incremental increase method.
Year 1930 1940 1950 1960 1970
Pop 25 28 34 42 47
PART-B
Q3 a) Explain in detail i) Screening ii) Aeration 06 M 2(I,II)
b) Discuss the importance of physical, chemical characteristics of water 6.5 M 2(II,III)
Q4 a) Explain the different design consideration in plain sedimentation. 6M 2(II,III)
b) Discuss the principal of sedimentation. Explain the different plain 6.5 M 2(II,III)
sedimentation tank

RBT – Revised Bloom’s Taxonomy


I. Remembering II. Understanding III. Applying
IV. Analyzing V. Evaluating VI. Creating

CO mapping with RBT and POs:


CO BCV304: WATER SUPPLY AND WASTEWATER ENGINEERING
BCV304.1 Estimate the average and peak water demand for a community
BCV304.2 Evaluate water quality and environmental significance of various parameters and plan
suitable treatment system
BCV304.3 Design the different units of water treatment plant.
BCV304.4 Design the various units of wastewater treatment plant
BCV304.5 Design of various AOPs and low cost treatment units.
CO-PO/PSO Mapping
(COs) / (POs) 1 2 3 4 5 6 7 8 9 10 11 12 PSO1 PSO2 PSO3 PSO4
BCV304.1 2 3 2 2 1 1
BCV304.2 2 2 1 1 1 1
BCV304.3 2 2 2 1 1
BCV304.4 2 2 2 1 1
BCV304.5 2 2 2 1 1

Course File Format: Acad/01/Rev(i)


STSKK’s
TONTADARYA COLLEGE OF ENGINEERING, GADAG
Department of Civil Engineering
--------------------------------------------------------------------------------------------------------------------------
Internal Assessment – I
Subject :Water Supply and Wastewater Engineering (BCV304) Date:
Semester: III Time:
Note: Answer one FULL question from each part.
Assume missing data suitably. Max Marks: 25
PART-A CO (RBT)
Q1 a) Explain the need of planned water supply scheme in present day 06 M 1 (I,II)
community life.
b) With the help of following data, estimate by incremental increase
method, population of a city for the year 2030. 6.5 M 1 (I,II)
Year 1910 1920 1930 1940 1950 1960 1960
Population 25000 27500 34100 41500 47050 54500 61000
Q2 a) Explain the factors affecting the per capita demand 06 M 1(I,II)
b) The population (in thousands) of 5 decades from 1930 to 1970 is given
below table. Find out the population after one, two and three decades 6.5 M 1(I,II)
beyond the last known decade, by using Geometric increase method.
Year 1930 1940 1950 1960 1970
Pop 25 28 34 42 47
PART-B
Q3 a) Discuss the drinking water quality standards as per BIS for the following 06 M 2(I,II)
parameters with their effects when they are exceeding their limits:
1) Iron 2) Chlorides 3) Fluorides 4) Nitrate.
b) Explain in detail i) Screening ii) Aeration 6.5 M 2(II,III)
Q4 a) Explain the different design consideration in plain sedimentation. 6M 2(II,III)
Discuss the principal of sedimentation.
b) Explain the different plain sedimentation tank 6.5 M 2(II,III)
RBT – Revised Bloom’s Taxonomy
I. Remembering II. Understanding III. Applying
IV. Analyzing V. Evaluating VI. Creating
CO mapping with RBT and POs:
CO BCV304: WATER SUPPLY AND WASTEWATER ENGINEERING
BCV304.1 Estimate the average and peak water demand for a community
BCV304.2 Evaluate water quality and environmental significance of various parameters and plan
suitable treatment system
BCV304.3 Design the different units of water treatment plant.
BCV304.4 Design the various units of wastewater treatment plant
BCV304.5 Design of various AOPs and low cost treatment units.
CO-PO/PSO Mapping
(COs) / (POs) 1 2 3 4 5 6 7 8 9 10 11 12 PSO1 PSO2 PSO3 PSO4
BCV304.1 2 3 2 2 1 1
BCV304.2 2 2 1 1 1 1
BCV304.3 2 2 2 1 1
BCV304.4 2 2 2 1 1
BCV304.5 2 2 2 1 1

Course File Format: Acad/01/Rev(i)

You might also like