Compliance against slow Progress - Advance Warning Notice as per clause 8.4 of FIDIC Conditions of Contract 28.06.2024
Compliance against slow Progress - Advance Warning Notice as per clause 8.4 of FIDIC Conditions of Contract 28.06.2024
To
The Resident Engineer,
Dowha-MaRS Engineering Co. Ltd. (JV)
Sub:- “Improvement and Upgradation of Moran Naharkatia Road (Deesang Kinar Bangali to
Kathalguri) Under ASRIP, (Package No.ASRIP/A/RI-6)”
Reg:- “Complaince against slow Progress - Advance Warning Notice as per clause 8.4 of FIDIC
Conditions of Contract”.
Sir,
With reference to the above-mentioned subject, we have already started the work at ch
10+500 to ch 11+600 and ch 12+600 to ch 18+000 but FRL has been not yet approved from your end
so that the progress has been not showed till date only the structure work has been shown that is also
your calculation has been wrong.
And you are saying that the slow progress and 1st Milestones is going to be failed but its all due to
failure has been achieved being to earthwork work has been completed on structure stretches and also
plan and profile has been until till date it has been not received from your end.
The chainages of VUP which is soil tested has been done 3 months ago but till date no any reply from
your good office as well as Team Leader Office. So all that responsibilities is upon you so please look
after this matter for further progress of work without telling the 1 st milestone and other 2nd milestone.
Yours faithfully
(Samshool Hazarika)
Project Manager
SHREE GAUTAM-ANPL (JV).
Pkg No. ASRIP/A/RI-6
Copy to:-
1. The Executive Engineer, Chabua, Duliajan & Naharkatia Territorial Road Division, for
favour of kind information please.
2. The Team Leader, Dowha-MaRS Engineering Co. Ltd. (JV) for favour of kind information
Page No. 1 of 1