SETUP APPROVAL REPORT Customer : SEPL-Autoliv DATE:

FINISHED
PART NO:6505242 PART NAME: SIDE BRACKET
UNFINISHED

JUDGEMENT: O - MEETS REQ, Δ - MEET REQ/ NEED IMPROVE,SUPPLIER: : MAT: GENERAL WEIGHT:
TOLERANCE
X - DOES NOT MEET REQ, O - REWORKED TO MEET REQ HARI BHARGO ENGINEERING
Drawing

CLASS INSPECTION MEASURMENT RESULTS JUDGE


Sl no CHARTERISTICS DIMENSION/SPECIFICATION SC/CC REMARKS
INSTRUMENTS 1 2 3 4 5 SUP Autoliv

No scratch, Burr, dent, crack, rust,


1 Appearance
Bend / Waviness...etc.
Visual

2 Material Thickness 2.0+/-0.3 Micrometer

3 Width 30.00+/-0.3 Digital Vernier Caliper

4 Bending height 37.0+/-0.3 Digital Vernier Caliper

5 Bending height 24+/-0.3 VERNIER

6 HOLE DIA 9.0+\-0.3 DVC

7 SLOT 6.5* 4.5+\-0.5 DVC

8 PITCH 25+/-0.3 HG

9 PERPENDICULARITY 0.25 MAX HG

10 LETTERING 6505239 &,<spfc 590> visual

0.25 max

NOTE: CHECK POINT ADDED FOR PERPENDICULARITY 0.25 MAX (SL NO-9)
REV NO-01
REV DATE-11.06.2020

QUALITY CONTROL DIVISION CHECKED BY INSPECTED BY

SUPPLIER: Hari Bhargo Engineering


For.No.:F-Q043 Issue.Date:01/Mar/13 Rev.No.:01
SETUP APPROVAL REPORT Customer : SEPL-Autoliv DATE:

FINISHED
PART NO:6505239 PART NAME: SIDE BRACKET
UNFINISHED

JUDGEMENT: O - MEETS REQ, Δ - MEET REQ/ NEED IMPROVE, SUPPLIER: : MAT: GENERAL WEIGHT:
TOLERANCE
X - DOES NOT MEET REQ, O - REWORKED TO MEET REQ HARI BHARGO ENGINEERING
Drawing

CLASS INSPECTION MEASURMENT RESULTS JUDGE


Sl no CHARTERISTICS DIMENSION/SPECIFICATION SC/CC
REMARKS
INSTRUMENTS 1 2 3 4 5 SUP Autoliv

No scratch, Burr, dent, crack, rust,


1 Appearance
Bend / Waviness...etc.
Visual

2 Material Thickness 2.0+/-0.3 Micrometer

3 Width 30.00+/-0.3 Digital Vernier Caliper

4 Bending height 37.0+/-0.3 Digital Vernier Caliper

5 Bending height 24+/-0.3 VERNIER

6 HOLE DIA 9.0+\-0.3 DVC

7 HOLE DIA 4.5+\-0.3 DVC

8 PITCH 25+/-0.3 HG

9 PERPENDICULARITY 0.25 MAX HG

10 LETTERING 6505239 &,<spfc 590> visual

0.25 max

NOTE: CHECK POINT ADDED FOR PERPENDICULARITY 0.25 MAX (SL NO-9)
REV NO-01
REV DATE-11.06.2020

QUALITY CONTROL DIVISION CHECKED BY INSPECTED BY